| 1 | CARMEL NAGAR SJVS |
| 2 | Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared. |
| 3 | Earthwork in open well excavation (above water) for wells of diameter above 6.0m and up to 9.0m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift up to 1.5m including neat banking. |
| 4 | Earthwork in open well excavation (above water) for wells of diameter above 6.0m and up to 9.0m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift from 1.50m to 3.0m including neat banking. |
| 5 | Earthwork in open well excavation (in or under water) for wells of diameter above 6.0m and up to 9.0m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift from 3.0m to 4.5m including neat banking. |
| 6 | Earthwork in open well excavation (in or under water) for wells of diameter above 6.0m and up to 9.0m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift from 4.5m to 6.0m including neat banking. |
| 7 | Earthwork in open well excavation (in or under water) for wells of diameter above 6.0m and up to 9.0m in all kinds of soil and conveying and depositing the spoil within initial lead of 50m and lift from 6.0m to 7.5m including neat banking. |
| 8 | Granite rock blasting in wells, measured in solids, including collecting and stacking spoil for measurement within the initial lead of 50m and lift up to 6.0m (4.5m to 6.0m) but excluding bailing out water and including providing protection by earth 2f3il1le0:d00c:e2m0.0e4n2t bags (300 Nos. of ear1th filled cement bags / 10 m3 blasting) to avoid damages to the nearby structures) |
| 9 | Reinforced cement concrete work in well - steining excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (Zone - III) derived from naturalsources derived from naturalsources: 3 graded stone aggregate 20 mm nominal size derived from natural sources derived from naturalsources) |
| 10 | Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete above plinth level.Thermo - Mechanically Treated bars of grade Fe-500D or more |
| 11 | Centering and shuttering including strutting, etc. and removal of form for:Well steining |
| 12 | Bailing out water with 5HP engine and pump set including conveyance to the site, erecting, dismantling and taking back of engine and pump, cost of fuel lubricating oil and other stores pay of staff etc., complete. |
| 13 | Supplying ,Fabricating and fixing pump house of size 120x60 cm and height at front side 2.0m and back side 1.80m. Using 16guage MS sheet 25x25x6 mm MS angle and 25x25 mm size GP tube 16g. And a door of size .75m x 1.80m with locking arrangements. Roofing with .35mm thick prepainted GS troffold sheet over 2 nos of 25 x 25 mm size GP tube, purlin of 16g.flooring with suitable size GP tube and aluminum checked sheet and Painting the whole structure with 2 coats of synthetic enamel paint over a coat of zinc chromate yellow primer and fixing the same to the roof of well frimly using suitabie size of anchor bolts etc. complete as directed |
| 14 | Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil |
| 15 | Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 90 mm nominal outside diameter pipes. |
| 16 | Supply of HDPE Pipe PE 100 (IS 4984/1995), 10kg, 90mm Outer Dia. |
| 17 | Supplying and installation of pump and accessories including panel board ,coloumn pipe all fittings as per direction of departmental engineer 10 HP with discharge 15000/LPH and 100m head Please Enable Macros to View BoQ information |