| 1 | Dismentling and removing cement concrete including stacking the useful materials for reuse and removing the debries within 50 m. Lead etc. complete |
| 2 | Earth work in stoney earth and gravels mixed with stone and boulder not exceeding 0.014 cum. In volume within 50 m. initial lead and1.5 m. initial lift including rough dressing etc. complete. |
| 3 | Cutting and disintegrated rock not requiring blasting to be removed by pick axes and crow bars and depositing materials with in 50 mtr initial lead and 1.5 mtr initial lift including rough dressing etc. complete |
| 4 | Cutting and disintegrated rock not requiring blasting to be removed by pick axes and crow bars and depositing materials with in 50 mtr initial lead and 1.5 mtr initial lift including rough dressing etc. Complete |
| 5 | Supplying & Laying of 5ft. (1.52mt.)x 1.00 ft. RCC ring including cost and transportation etc. complete. |
| 6 | Laying of stone boulders dry packing in apron and revetment with hard granite stone including spalls for filling and wedging cost, carriage etc. Complete. |
| 7 | Cement Concrete (1:3:6) by using 4cm. Size H.B.G. (C.B.) metal including cost, conveyance etc. complete. |
| 8 | Cement Concrete (1:2:4) with 12mm. Size C.B.granite chips (Crusher broken) for Rcc works including all cost, conveyance , royality etc. complete. |
| 9 | Supplying,fitting & Placing of HYSD bar Reinforcement cover plate including cost and carriage etc. complete. (Steel ) |
| 10 | Rigid and smooth centering and shuttering for R.C.C. works including false works and dismentalingthen after casting including cost of materials complete. |
| 11 | Flyash Brick masonary in cement mortar (1:6) of size (23x11x8cm)by using 9\\" size including all cost, conveyance etc. complete.(Including Parapet wall) |
| 12 | Site clearance for cutting bushes cleaning the sites etc. Complete. |
| 13 | Filling of 6mm to 8mm C.B. Granite Chips including cost, carriage etc., complete. |
| 14 | Filling foundation and plinth with sand and well watered & rammed etc . Complete including cost, carriage etc. complete. |
| 15 | Drilling of perfectly vertical Bore Hole of 125/100mm dia in hard rock formation as required to the site condition as per direction including cost of accessories ,tools,& plants,consumables & rig charges etc. Complete |
| 16 | Cost & Carriage of 125mm dia, 80 Sch. PVC Pipe in perfectly vertical position including cost of pipes Etc. Complete |
| 17 | Washing and Development of walls by compresure. |
| 18 | Supplying & laying and Fixing of 160mm (OD) PVC pipe ( 4 kg/cm2) of including all cost for socket ,bend,solvent transporation of pipes etc. complete. |
| 19 | Supplying & laying and Fixing of 110mm (OD) PVC pipe ( 4 kg/cm2) of including all cost for socket ,bend,solvent transporation of pipes etc. complete. |
| 20 | Supplying & fitting of 110x160mm R/S |
| 21 | Suppling and Fixing Vitrified Floor Tiles in floors of Primium Grade having thickness 8mm to 10mm. confirming IS 15622: 2006 coloured of Size 600mm x600mm of Special coloured / Printed Series fioor tiles dedoes Skirting & riser of Steps in 25mm thick Cement mortar (1;1)with jointed with neat cement slurry Mixed with pigment to match the shades of the tiles including Rubbing and polising complete including Cost, Conveyance, taxes and Royality all Materials,labour with T & P Complete in all respect. |
| 22 | Filling foundation & plinth with excavated material including watering & ramming etc. complete |
| 23 | 12 mm Thick cement plaster over brick work in C.M. (1:6) including cost,conveyance,royality of materials etc complete. |
| 24 | Supplying and Fixing of 110mm dia PVC Gate Valve etc. complete. |
| 25 | Supplying & fixing of Man hole size 2ft x 2ft including cost of G.I plate, 11/2\\" angle and labour charges transportation, fabrication, coloring etc. complete. |
| 26 | MS Well cap |
| 27 | Supplying & fitting of MS flat clamp with priming and painting. |
| 28 | Supplying & fixing of GI.Plate size 3ft x 3ft and 11/2\\" angle,Colouring,Writing of name plate,transpotation,Earth work Excevation ,C:C(1:2:4),C:C(1:3:6)and labour charges for fabrication works,Colouring red oxide,emulsion paint,Writting of name plate & Deptt. information etc. complete. |
| 29 | Fabrication,carriage & installation of MS Metal protection chamber made of 18 gauge steel with handle and locking arrangement including denting, priming & Colouring,transpotation and labour charges for fabrication works with Writting of name plate and other Deptt. information etc. complete. Please Enable Macros to View BoQ information |