| 1 | Erecrion Part |
| 2 | Erection of 33KV HT Line Double pole str. 11 mtr long:- Re-Digging of Pit, Straightening of tilted pole, Filling of Pit And Ramming, complete in all respects |
| 3 | Sagging of GI 8SWG mm sizes Single Wire :-D-Stringing of conductor , re-jointing , resagging , binding with Disc/Pin insulators complete in all respects as directed by Engineer in-Charge. |
| 4 | Sagging of ACSR 6/1/4.72 mm sizes (100mm2) Single Wire :-D-Stringing of conductor , re-jointing , resagging , binding with Disc/Pin insulators complete in all respects as directed by Engineer in-Charge. |
| 5 | Erection of HT Stay Set:-Digging Of Pit,Fixing of Stay Rod,Nozzeling & Tightening complete in all respects |
| 6 | Erection of Earthing Set:-Digging Of Pit,Fixing Of GI Wire To The Earthing System,Filling Of Pit complete in all respects |
| 7 | Manual Carriage for 1.00 Km. average lead from road head to site of work. Average lead= 1Km. |
| 8 | Dismantled of Double pole structure:-Digging of Pole ,Lifting of Pole along with allied Materials Complete in all respect(Dismentled Materials will be return to divisional store) |
| 9 | Supply Part |
| 10 | Prov. RCC Muff with Concrete Filling 2000mm length. |
| 11 | Prov. G.I.No. 6/ 8 SWG for Earth wire for S/T Pole |
| 12 | Prov. C.I.X-arm (100X50X5mm), for D. Pole Str. (2800x4=11.2 mtr) |
| 13 | Prov. Stay Set Complete in all respect i/c Guy Assembly with Helically Fitting |
| 14 | Prov. Stay Wire 7.400 mm ( @ 9.00 Kg per Stay Set) |
| 15 | Prov. Full Clamp with nuts & bolts M.S. Flat 50x6 mm |
| 16 | Prov. Stay Clamp with nuts & bolts M.S. Flat 50x6 mm |
| 17 | Prov. Earth Hook for Earth Wire |
| 18 | Prov. Nuts & Bolts Of various sizes ( Gaivanised/ Coated) ( Preferably 16 mmɸ or more with flat and spring washers) |
| 19 | Prov. Barbed Wire |
| 20 | Prov. Alluminium Paint |
| 21 | Prov. Red oxide Please Enable Macros to View BoQ information |