| 1 | Dismantling one damaged 11kV PSC/RCC pole after disconnecting stays, strut etc.attached thereon and stacking the same. |
| 2 | Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm)0.45x0.45x1.5m, Plastering (1:3) 12mm0.45x0.45mx5sides. |
| 3 | Additional rate for refitting/redoing one Disc set while renewing any type of 11kV cut pole. |
| 4 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 5 | Additional rate for providing one disc set, PG clamp etc. complete, on any type of HT pole for making cut point. |
| 6 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 7 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 8 | Fiting One no MVT on existing cross arm including 2 nos end termination (for One phase) of any rating for 11 kV AB Cable |
| 9 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 10 | Dismantling (without damage) one HT stay including digging pit in all classes of soil and backfilling, and bringing back to section store. |
| 11 | Dismantling one Anchor clamp /dead end clamp from 11 KV ABC |
| 12 | Erection of Anchor clamp / dead end clamp for 11kV ABC of any size |
| 13 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole including conveyance of materials. |
| 14 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 15 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 16 | Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 17 | Fitting one Additional2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 18 | Dismantling (without damage) one AB switch from existing structure and bringing back to section store. |
| 19 | Fitting one set AB switch on existing DP, giving connection and drawing sufficient length of GI earthing leads to the ground for earthing, excluding provision of earthing. |
| 20 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 21 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 22 | Fitting and erecting one HT PSC Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 23 | Fitting one Additional V cross arm in existing single pole including conveyance of materials. |
| 24 | Providing additional jumper from AB to line |
| 25 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 26 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 27 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 28 | Fitting and erecting one HT Double Pole Structure using PSC pole in position including fitting 2 channel cross arms, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 29 | Fitting and providing one HT Fly stay for 11kV pole using HT PSC pole including digging and back filling pits in ordinary soil, drawing sufficient length of GI earth leads to the ground for earthing (excluding provision of earthing). |
| 30 | Labour charges for loading HT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 31 | Additional rate for providing one HT Pin with insulator, complete on any type of HT pole. |
| 32 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 33 | Redoing three phase WP service connection complete including lowering down the guy wire portion, repairing or changing WP wire, GI wire, Fuse unit etc., changing Energy Meter cutout, neutral link etc., if necessary and reconnecting the same including conveyance of material to site from Section office at various location. |
| 34 | Redoing single phase WP service connection complete including lowering down the guy wire portion, repairing or changing WP wire, GI wire, Fuse unit etc., changing Energy Meter cutout, neutral link etc., if necessary and reconnecting the same including conveyance of material to site from Section office at various location. |
| 35 | Reshackling one span LT three phase 4 wire OH line including pin binding, jumpering, replacing insulators/cross arms/shackle, tightening stay, cutting tree branches etc. wherever necessary including conveyance of all materials. |
| 36 | Reshackling one span LT OH Additional conductor including pin binding, jumpering, replacing insulators/cross arms/shackle, tightening stay, cutting tree branches etc. wherever necessary including conveyance of all materials complete. |
| 37 | Reshackling one span LT single phase 2 wire OH line including pin binding, jumpering, replacing insulators/cross arms/shackle, tightening stay, cutting tree branches etc. wherever necessary including conveyance of all materials. |
| 38 | Dismantling (without damage) one LT PSC/RCC pole after disconnecting stays, strut etc. attached thereon and stacking the same. |
| 39 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 40 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc. |
| 41 | Dismantling one section fuse from structure and bringing back to section store. |
| 42 | Stringing of one km 11kV line with ACSR Raccoon (3 conductors) after fitting insulators and giving jumper connections including cutting and removing tree branches wherever necessary excluding cut point works. |
| 43 | Additional rate for providing one F top bracket complete, on any type of HT pole. |
| 44 | Renewal of existing damaged/old 11kV PSC/RCC Pole with new PSC pole in place including excavation, erection of new pole, backfilling pit and refitting of all items etc. and conveyance of all materials except pole. |
| 45 | Additional rate for reinstalling LT line on the renewed 11kV pole having both HT and LT (HT/LT) lines. |
| 46 | Renewal of existing damaged/broken old 11kV Stay to the existing stay rod. |
| 47 | Renewal of existing damaged/old 11kV Stay with new stay in place including excavation & backfilling of pit, dismantling, refitting of all items and conveyance of all materials. |
| 48 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works. |
| 49 | Dismantling of 11 kV Aerial bunched cable XLPE insulated of size 3 x 150+ 1 x 120 sqmm with bare insulated Messenger |
| 50 | Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 51 | Providing WP support with PSC pole including digging & back filling pit in ordinary soil. excluding transportation of poles. |
| 52 | Insertion of one LT PSC pole in existing single phase OH line including digging & back filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation of poles. |
| 53 | Fitting one set (3No.) 11kV LA and giving connections excluding earthing. |
| 54 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 55 | Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc. using ACSR Rabbit for Phase and Neutral, for one km LT single phase 2 wire line including cutting and removing tree branches wherever necessary and conveyance of all materials (except poles) from stacking place. |
| 56 | Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. |
| 57 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 58 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 59 | Stringing, shackling, fitting cross arms, insulators and binding, giving jumper connection etc. using ACSR Rabbit for Phase and ACSR Weasel for Neutral & Street Main, for one km LT 3ph 5 wire line including cutting and removing tree branches wherever necessary and conveyance of all materials (except poles) from stacking place. |
| 60 | Erection of suspension clamp for 11KV ABC of any size |
| 61 | Dismantling one suspension clamp from 11 KV ABC |
| 62 | Stringing of 11 kV Aerial bunched cable of size 3 x 150+ 1 x 120 sqmm with bare/insulated Messenger through existing poles |
| 63 | Doing one cable end termination on HT ABC of sizes Up to 3x150+1x120 sqmm and connecting to existing MVT or other terminals,using the cable end termination kit supplied departmentally including charges for cable jointer etc. complete as per the direction of the departmental officers. |
| 64 | Providing bridging at Cut points for 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalent (1 conductors) using IPC and respective conductors |
| 65 | Renewal of any type of existing damaged/old 11kV Strut with new PSC strut in place including excavation & backfilling of pit, consolidating, dismantling and refitting of all items and conveyance of all materials except pole. |
| 66 | Fitting and providing one Strut using HT PSC pole including digging and back filling pit in ordinary soil. |
| 67 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the bunched cable of size 3 x 150+ 1 x 120 sqmm with bare/insulated Messenger through existing poles |
| 68 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. Please Enable Macros to View BoQ information |