| 1 | Conducting Subsurface Utility Engineering (SUE) Survey in a corridor of 4–6 metre width for detection and mapping of buried underground utilities such as water supply pipes, sewer lines, storm water drains, electrical cables, telecom cables, gas pipelines, etc |
| 2 | Dismantling tile work in floors and roofs laid in cement mortar including stacking material within 50 metres lead For thickness of tiles above 25 mm and up to 40 mm |
| 3 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge.Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 4 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge.Nominal concrete 1:4:8 or leaner mix (i/c equivalentdesign mix) |
| 5 | providing and laying 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 6 | Providing and laying in footpath and pavement etc. factory made precast cement concrete slabs of size 400 x 400 x 50mm of mix M-30 Grade manufactured at an appropriate plant by compacting concrete in joint less moulds in two stages vibration & compression and finished smooth as per shapes size and pattern over a base of 12mm thick (average) cement mortar 1:5 (1cement: 5coase sand) and having joints not exceeding 10mm thick (average ) cement mortar 1:5 (1cement: 5coarse sand) neatly finishing etc. plete as per directions and instruction of Engineer-in-Charge (Nothing extra shall be paid to the contractor by laying slabs in approved pattern and using precast slabs of required shapes at end of footpath.) |
| 7 | Horizontal Directional Drilling for Steel Ducts/Pipes Installation of Steel product pipe by HDD method including preparing and setting up the plant and equipment, preparing new pipe-work material, installing new pipe-work and commissioning system or making the system ready for commissioning by HDD operation including, all related civil and mechanical works like excavation, shoring/strutting, etc. drilling. stringing, reaming, and pulling back the new pipe-work on the designed bore path alignment, proper disposal of drilling fluid and back fill of site after completion all inclusive as per IndSTT:101-2018: Code of Practice for Horizontal Directional Drilling Technique Suiting Indian Conditions. Steel pipes above 200mm and upto 300mm dia. In mixed soil |
| 8 | Providng and laying 300 mm internal dia HDPE/DWC of SN-8 classification as per entire satisfaction of Engineer-in-Charge |
| 9 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavatedearth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-incharge.All Kinds of soil. |
| 10 | Constructing brick masonry circular type manhole 1.22 m internal dia at bottom and 0.56m dia at top in cement mortar 1:4 (1 cement : 4 coarse sand), inside cement plaster 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement, foundation concrete 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size), and making necessary channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement, all complete as per standard design : 1.67 m deep with S.F.R.C. cover and frame (heavy duty, HD-20 grade designation) 560 mm internal diameter conforming to I.S. 12592, total weight of cover and frame to be not less than 182 kg., fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) including centering, shuttering all complete. (Excavation, foot rests and 12mm thick cement plaster at the external surface shall be paid for separately) : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 11 | Extra depth for circular type manhole 1.22 m internal dia (at bottom) beyond 1.68 m to 2.29 m With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 12 | Providing and Laying Cement Concrete of Specified grade excluding the cost of centring and shuttering-All works up to Plinth Level.1:5:10 (1 Cement: 5 Manufacture Sand : 10 graded recycled aggregate 40mm nominal size) |
| 13 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 14 | Providing orange colour safety foot rest of minimum 6 mm thick plastic encapsulated as per IS : 10910, on 12 mm dia steel bar conforming to IS: 1786, having minimum cross section as 23 mmx25 mm and over all minimum length 263 mm and width as 165 mm with minimum 112 mm space between protruded legs having 2 mm tread on top surface by ribbing or chequering besides necessary and adequate anchoring projections on tail length on 138 mm as per standard drawing and suitable to with stand the bend test and chemical resistance test as per specifications and having manufacture’s permanent identification mark to be visible even after fixing, including fixing in manholes with 30x20x15 cm cement concrete block 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) complete as per design. |
| 15 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. |
| 16 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leadsincluding all lifts involved. |
| 17 | Plugging the total sewerage from Existing sewer line at Manhole to reduce the discharge of sewer line to minimize the wet and foul condition by placing gunny bags filled with earth and stiched properly including supply and laying in position filled up gunny begs in full length of required of manhole as directed by the engineer-in-charge and subsequent removal of the same after completion of the work to the entire satisfaction of the engineerin-charge. For 100mm to 300mm dia Sewer line. |
| 18 | Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse and), finished with a floating coat of neat cement and making necessary channels for the drain etc. complete For pipes 100 to 250 mm diameter. |
| 19 | dewatering of water /sewerage, including necessary suction and delivery pipes, fuel, operator, all T&P, handling and disposal of sewerage water to nearest municipal sewer drain manhole, complete in all respects. Measurement shall be taken only for the actual running time of the pump in hours and minutes. |
| 20 | Constructing brick masonry circular manhole 1.52 m internal dia at bottom and 0.56 m dia at top in cement mortar 1:4 (1 cement : 4 coarse sand) inside cement plaster 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement, foundation concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size) and making necessary channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement, all complete as per standard design : 2.30 m deep with SFRC Cover and frame (heavy duty HD- 20 grade designation) 560 mm internal diameter conforming to I.S. 12592, total weight of cover and frame to be not less than 182 kg. fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) including centering, shuttering all complete. (Excavation, foot rests and 12 mm thick cement plaster at the external surface shall be paid for separately). With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 |
| 21 | Extra depth for circular type manhole 1.52 m internal dia (at bottom) beyond 2.30 m : With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 Please Enable Macros to View BoQ information |