| 1 | Bank protection |
| 2 | 5.9.6:Centering and shuttering including strutting, etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts |
| 3 | 5.9.5:Centering and shuttering including strutting, etc. and removal of form for:Lintels, beams, plinth beams, girders bressumers and cantilevers |
| 4 | 5.33.1.1:Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cementAll work upto plinth levelConcrete of M25 grade with minimum cement content of 330 kg /cum |
| 5 | OD29847/2024-2025:Conveying, lifting, handling, hoisting, aligning and fixing R.C.C 300 mm pile , from the place of casting to placing site driving plant up to a distance of 150 m including hire charges for planks, wooden scantling, coir rope, crow bars, etc. complete |
| 6 | OD29849/2024-2025:Driving and installing Pre-cast reinforced cement concrete piles of any size andlength to the required depth in line and levels and shifting the casted piles to the driving spot without damaging the pile with necessary lifting equipments placing in correct position to line and driving down to required depth with the helpof driving equipment including hire charges for driving equipment, machinery,planks, fuels,labour charges etc complete as per the direction of the departmental officers at site |
| 7 | 2.22.2:Open timbering over areas including strutting, shoring etc. complete (Measurements to be taken of the face area timbered):Depth exceeding 1.5 m but not exceeding 3 m |
| 8 | OD34244/2025-2026:Engaging Hydraulic Excavator (110 & above capacity) with Barge including Diesel, lubrication oil and wages of driver etc.. complete for Excavation operations underwater as directed by the Engineer- in-charge |
| 9 | OD22407/2025-2026:Providing, conveying, hoisting and fixing precast reinforced cement concrete in slabs including setting in cement mortar 1:3(1 cement : 3 coarse sand), cost of required centering, shuttering and finishing but excluding the cost of reinforcement, with machine batched and machine mixed design mix M-25 grade cement concrete (based on DSR 5.16 ) |
| 10 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 11 | 50.2.26.1:Filling with contractor own earth (excluding rock) in open areas in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m as per direction of site Engineer-in-charge. |
| 12 | 60.7.6:Supplying and stacking granite stone 20 to 45 dm3 for dumping works- Supplying at site of work granite stone 20 to 45 dm3 in size (60% 45m3,30%30 to 40dm3 and 10% 20 to 30dm3 stones) for measurement ( deducting not less than 15% for voids as fixed by the departmental officer at site) including all cost, conveyance, loading and unloading charges all other incidental charges all leads and lifts etc. complete as per the direction of the departmental officers at site. |
| 13 | 60.7.7:Conveyance and dumping of departmental granite stones-Conveyance of departmental granite stone 20 to 45 dm3 in size from stack at site and dumping in position (60% 45m3,30%30 to 40dm3 and 10% 20 to 30dm3 stones) to lines and levels to from the core of the sea wall as per approved design including all leads and lifts etc. complete as per the direction of the departmental officers at site. |
| 14 | 60.7.1:DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site |
| 15 | 60.6:PVC WEEP HOLES- Providing weep holes using 75mm dia. PVC pipes working pressure 4kg /sq.cm including cost of materials, conveyance, labour charges etc. complete. Please Enable Macros to View BoQ information |