| 1 | Items : |
| 2 | Labour Charges for fitment per 300 sq.mm. × 4C or 3.5C (or equivalent) Straight through Joint |
| 3 | Labour Charges for fitment per 25 sq.mm. × 4C/70 sq.mm. × 4C/120 sq.mm. × 4C Straight through Joint |
| 4 | Labour Charges for Decompounding per 'T' Joint (25 sq.mm. x 4C, / 70 sq.mm. x 4C, / 120 sq.mm. x 4C made over existing 300 sq. mm. x 4C or PVC/ HRPVC/PILC/XLPE Cable or 0.15 sq. inch x 4C PILC) |
| 5 | Labour Charges for Decompounding per Straight Joint of 25 sq.mm. / 70 sq.mm. x 4C PVC/HRPVC/PILC/XLPE cable |
| 6 | Labour Charges for Decompounding per Straight Joint of 120 sq.mm. / 300 sq.mm. x 4C PVC/HRPVC/PILC/XLPE cable or 0.15 sq. inch x 4C PILC |
| 7 | Labour Charges for fitment per ‘T’ Joint (25 sq.mm. × 4C/70 sq.mm. × 4C/120 sq.mm. × 4C over 300 sq.mm. × 4C or PVC/HRPVC/PILC/XLPE Cable or 0.15 sq. inch × 4C PILC, as the case may be) |
| 8 | Labour Charges for fitment per Termination of 300 sq.mm. × 4C or 3.5C Termination (Gland) in ADP/MP/MMP/DSS LV Board/ Service Cutouts with Earthing in electrically Live environment |
| 9 | Labour Charges for fitment per Termination for 25 sq.mm. × 4C/70 sq.mm. × 4C/120 sq.mm. × 4C Termination (Gland) in ADP/MP/MMP/DSS LV Board/Service Cutouts with Earthing in electrically Live environment |
| 10 | Cost of Excavation per cub. mtr. on Cement Concrete Road/Cement Concrete Footpath using demolition hammer, concrete / marble cutter or by any other tools/equipments as per BMC Guidelines |
| 11 | Cost of Excavation per cub. mtr. on Cement Concrete Road/Cement Concrete Footpath using diamond cutter as per BMC Guidelines |
| 12 | Cost of Excavation per cub. mtr. on Cement Concrete Road/Cement Concrete Footpath using JCB as per BMC Guidelines |
| 13 | Cost of Excavation per cub. mtr. on Cement Concrete Footpath / Stamped / Concrete Footpath / Cement Concrete surface in private premises using demolition hammer, concrete / marble cutter / by any other tools/ specialized equipment. |
| 14 | Cost of Excavation per cub. mtr. on Cement Concrete Footpath / Stamped / Concrete Footpath / Cement Concrete surface in private premises using diamond cutter. |
| 15 | Cost of Excavation per cub. mtr. on Cement Concrete Footpath / Stamped / Concrete Footpath / Cement Concrete surface in private premises using JCB |
| 16 | Cost of Excavation per cub. mtr. on Asphalt Road using demolition hammer, concrete / marble cutter or by any other tools/equipments as per BMC Guidelines |
| 17 | Cost of Excavation per cub. mtr. on Footpath with Paver Blocks/Kaccha Road/Tiled/Private premises using demolition hammer, concrete / marble cutter or by any other tools/equipments as per BMC Guidelines |
| 18 | Cost of Excavation per cub. mtr. across road (where open trench cable laying is permitted) with provision of sand filled gunny bags to fill up trenches and covering the same with adequate size Iron Checker plates |
| 19 | Cost of Laying Cable per running mtr. in excavated trenches by open trenching method with proper barricading and illumination if required, Laying of Pipe wherever required, Pulling of Cable, bedding, tiling, backfilling, removal & disposal of debris from the site in the area of Electric Supply Distribution of the BEST Undertaking, Mumbai |
| 20 | Labour Charges for Installation per Mini Pillar/Modified Mini Pillar |
| 21 | Labour Charges for Installation per Auxiliary Distribution Pillar (6 way to 10 way) |
| 22 | Labour Charges for Installation per Auxiliary Distribution Pillar (more than 10 way up to 16 way) |
| 23 | Installation & Connection charges per Earthing Pipe Assembly to ADP/ Mini Pillar/Modified Mini Pillar/Cutout Board according to standard earthing practices (excluding the cost of excavation) |
| 24 | Labour Charges for disconnection of temporary overhead wires connected to Bottom / Top terminals of services / ADP and to insert fuses (RYB Phases) at services position in cut outs (to take the service on load) per service |
| 25 | Labour Charges for removal per old/unserviceable cutout board and installation of new cutout board (and/or MCB) at service position |
| 26 | Pot heading per service cable/distributor at appropriate location Please Enable Macros to View BoQ information |