| 1 | 600LPM, 45m head 2900 rpm 10 HP submersible clear water pumping plant suitable to operate 0n 415± 5% volt, 50Hz 3- phase AC supply. |
| 2 | Switch gear with cubical panel having with following items- |
| 3 | Timer for automatic operartion of mini tubewell. |
| 4 | Main Piping and valves 80mm dia 5.4mm thick MS column pipe with both end flanged and grooved for passing submersible cable in each length in 3m long 30m with 1m long top pipe with cap and sealing ring |
| 5 | Cost of additional 80mm dia 3m long MS flange column pipe |
| 6 | Tools in Tool kit |
| 7 | 1 tone capacity 4.5m lift, spur geared chain pulley block |
| 8 | Gauges |
| 9 | Misc. items such as protection ring cutout transformer oil electric resistance rubbersheet |
| 10 | 1 month watch & ward during the period of installation |
| 11 | Painting of pumping plant with approved anticorrosive and specified colour paint 2 coat |
| 12 | Three month trail run |
| 13 | Installation of pumping plant along with all neccessory fitting including by pass & delivery arrangements, airline and gauges fitting etc. complete in all respect with power wiring & earthing. |
| 14 | Transportation of pumping plant complete with all materials from store to site of work including loading and unloading and return trip. |
| 15 | Rig machine- Transportation of rig machine to site |
| 16 | Loading of T&P etc |
| 17 | Unloading of T&P etc |
| 18 | After completion of work return back |
| 19 | Air compressor - Transportation of air compressor to sie of work by tractor and return to store |
| 20 | Loading of T&P etc |
| 21 | Unloading of T&P etc |
| 22 | After completion of work return back |
| 23 | O.P. unit - Transportation of O.P. unit from store to site of work by tractor and return to store |
| 24 | Loading of T&P etc |
| 25 | Unloading of T&P etc |
| 26 | After completion of work return back |
| 27 | Tubewell assembly- Transportation of tubewell assembly from store to site of work. |
| 28 | Loading of T&P etc |
| 29 | Unloading of T&P etc |
| 30 | Erection of Rig machine and drilling work |
| 31 | Dismantling of rig machine |
| 32 | Drilling of 550mm dia bore from GL to 65m BGL |
| 33 | Drilling of 500mm dia bore from 65m to 80m BGL |
| 34 | Drilling of 500mm dia bore from 80m to 120m BGL |
| 35 | Lowering of 200mm dia MSERW plain pipe 7.1 mm thick pipe from GL to 60m BGL |
| 36 | Lowering of 150mm dia MSERW plain/ slotted pipe 7.1mm thick from 60m BGL to 80m BGL |
| 37 | Lowering of 150mm dia MSERW plain/ slotted pipe 7.1mm thick from 80m BGL to 110m BGL |
| 38 | Unforseen items as per site condition of tubewell for approach purpose of units and T&P and necessary work around pin point of TW and ebtrance of units and placing of such units and T&P at site as required as per site condition. |
| 39 | 200mm. dia size MSERW housing pipe 7.1 mm thick. |
| 40 | 150mm.dia MSERW 7.1mm thick slotted pipe. |
| 41 | 200X150 mm. dia M.S reducer 16.0 mm. thick. |
| 42 | 200mm. size M.S. well cap. 12mm thick. |
| 43 | 200mm size M.S. half thread nipple. |
| 44 | 200 mm. size M.S. ring 100mmx12mm tihck. |
| 45 | 150 mm. size M.S. ring 100mmx12mm tihck. |
| 46 | 200mm.dia size M.S. S/I clamp. |
| 47 | Tubewell supporting Frame. |
| 48 | 150mm.dia size M.S. bail plug. |
| 49 | 150mm Center guide. |
| 50 | 200mm dia half thread socket |
| 51 | 1.60mm to 4.80mm. size pea gravel of Lalkuwan quarry duly screened, washed and proper stacking at site. |
| 52 | Installation of air compressor and T & P etc complete in all respect at site. |
| 53 | Development of tubewell by 250 PSI air compressors including necessary welding works, with supply of fuel and lubricants, labour etc as required for running the air compressor during development of tube well, testing of the yield of finally developed tube well. |
| 54 | Sodium Hexametaphasphate |
| 55 | Dismantling of air compressor and its associated accessories, T&P etc complete in all respect after development of tubewell. |
| 56 | Installation of O.P. unit including leveling & dressing of site and proper stacking of camp equipage. |
| 57 | Development of tube well by O.P. unit. |
| 58 | Dismantling of O.P. unit after completion of work. |
| 59 | Chemical and bacteriological test. |
| 60 | Yield and verticality test of tube well. |
| 61 | Logging of tube well. |
| 62 | Rental charges of rig machine air compressor and O.P. unit |
| 63 | Supply and installation of Electro Mechanical type Chlorinating Plant of suitable capacity working pressure 0-4 Kg/Cm2 complete with panel and 100 liter capacity syntax make tank suitable for 500 L.P.M. to 3000 L.P.M. discharge of pumping plant. |
| 64 | LT power connection of mini tubewell including processing fee, security fee and connection charges complete in all respect. |
| 65 | GST amount Please Enable Macros to View BoQ information |