| 1 | Boiler repairing of VCT Boiler No: WBL-6035 at Madhaipur Colliery under Pandaveswar area.. (Inclusive of EPF/CMPF) |
| 2 | Old damaged shell extension plate angle gas cutting and out dressing grinding(Material Cost) |
| 3 | Old damaged shell extension plate angle gas cutting and out dressing grinding (labour cost) |
| 4 | Shell extension plate materials few late angle + 10% allowance = 310 kg (Size 6' dia & 1' height) thick 12 mm |
| 5 | New Shell extension plate & angle rolling, bending, fabrication & same position fitting welding, grinding, dressing smoothly (Material Cost) |
| 6 | New Shell extension plate & angle rolling, bending, fabrication & same position fitting welding, grinding, dressing smoothly (Labour Cost) |
| 7 | New Shell extension plate & angle rolling, bending, fabrication & same position fitting welding, grinding, dressing smoothly (Labour Cost) |
| 8 | Boiler cross tube gas cutting opening, dismantling out and dressing, grinding proper -V cutting(Material Cost) |
| 9 | Boiler cross tube gas cutting opening, dismantling out and dressing, grinding proper -V cutting(Labour Cost) |
| 10 | Boiler cross tube gas cutting opening, dismantling out and dressing, grinding proper -V cutting(Labour Cost) |
| 11 | Boiler cross tube same positioning erection, fitting BQ welding with side 350mmX1825mmX13mm of 360 Kg(material Cost) |
| 12 | Boiler cross tube same positioning erection, fitting BQ welding with side 350mmX1825mmX13mm of 360 Kg(Labour Cost) |
| 13 | Boiler cross tube same positioning erection, fitting BQ welding with side 350mmX1825mmX13mm of 360 Kg(Labour Cost) |
| 14 | Damaged fusible plug opening , boring and threading labour charges |
| 15 | New fusible plug fitting in same position with material IBR T.C.(Material Cost) |
| 16 | New Mud plug covered making machining drilling(Material Cost) |
| 17 | New Mud plug covered making machining drilling(Labour Cost) |
| 18 | New Mud plug covered making machining drilling(Labour Cost) |
| 19 | Hydraulic test arrangement by Boiler Inspector Director(material Cost) |
| 20 | Hydraulic test arrangement by Boiler Inspector Director(Labour Cost) |
| 21 | Boiler fitting purpose materials type joint, cotton tape, steam joint, hole tight, nut bolt, rubber joint, fiber bush, rubber cone gauge glass etc.(Material Cost) |
| 22 | Boiler fire bar & ring fabricated assembly fitting(material Cost) |
| 23 | Boiler fire bar & ring fabricated assembly fitting(Labour Cost) |
| 24 | Boiler fire bar & ring fabricated assembly fitting(Labour Cost) |
| 25 | Boiler fitting and commissioning steaming & running condition(labour Cost) |
| 26 | Profit @10% on Material Cost |
| 27 | Emergency Repairing of Boiler Injector & steam Pipeline 9,1, 5 & 6 Pit of Madhaipur colliery. (Inclusive of EPF/CMPF) |
| 28 | IBR 1\\" Pipe |
| 29 | IBR 1\\" Flange Table-H |
| 30 | IBR 1\\" L/R Bend |
| 31 | IBR 1\\" Valve |
| 32 | Require materials oxygen,DA welding Rod,High pressure joint,Nuts- Bolts ,Washer,Pubber cone etc with Labour charges |
| 33 | Horizontal 2\\" steam stop valve(CS) |
| 34 | Flange 2\\"(IBR) |
| 35 | Pipe 2\\" |
| 36 | Band 2\\" |
| 37 | Labour cost for Injector pipeline |
| 38 | Profit @10% |
| 39 | EPF @12.72% |
| 40 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |