| 1 | Earth work Open excavation by Mechanical Means for Open Earthwork in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard specification and as directed by the departmental officers. |
| 2 | Cement Concrete 1:5:10 (One cement, Five crushed stone sand and Ten hard broken stone jelly) using 40mm gauge hard broken jelly for flooring including laying, consolidating, finishing, rendering the top surface rough to receive the floor, curing, etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers - Mixing by mechanical means |
| 3 | Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 2.10M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton and as directed by the departmental Officers (Payment for centering shall be given after the concrete is laid) |
| 4 | Plain Cement Concrete 1:2:4 (one cement, two crushed stone sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. - Mixing by mechanical means |
| 5 | Plastering the surface of walls with Cement Mortar 1:4 (One cement and Four plastering sand), 20mm thick in all floors including mortar plasticizer at 200ml per 50Kg of cement used , curing etc., complete complying with standard specification and as directed by the departmental officers. |
| 6 | Supplying and erecting centering for plane surfaces such as RCC Floor Slab, Roof Slab, Loft, Landing Slabs, etc with necessary supports and strutting above 3.60m upto 4.90m height in all floors with all cross bracings using MS Sheets made of 10 gauge thick welded with MS angle of Size 25mm x 25mm x 3mm for boarding laid over steel adjustable span of size 2m x 2m (expandable upto 3.60m) and supported by Steel Adjustable Telescopic Props of Size 2.40m x 3.00m (expandable upto 4.90m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick) with Cross bracings provided at two levels at a spacing of 1.80m ,etc complete complying with standard specifications. Steel adjustable span and Steel Adjustable telescopic props shall be provided as directed by the departmental Officers (Payment for centering shall be given after the concrete is laid). |
| 7 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steel reinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) |
| 8 | Reinforced Cement Concrete 1:1½:3 (One Cement, One and a half crushed stone sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including Super Plasticiser, mixing charges for machine mix,laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers - machine mix |
| 9 | RCC non pressure spun pipe with socket and spigot ends as per IS 458/2003 manufacturedwith sulphate resistant cement with 12 mm HI -alumina lining with rubber ring joints. |
| 10 | Lowering RCC pipes and specials into the trenches and laying to proper grade and alignment |
| 11 | Jointing RCC pipes with cement using necessary collars including the cost of jointing materials. |
| 12 | Supply and run of 4 of 4 sq.mm. PVC insulated SC unsheathed FRLS copper conductor of 1100V grade insuitable heavy gauge MS conduit pipe concealed in wall and ceiling with continuous earth wire connection of 4sq.mm copper wire and making good of the concealed portion with suitable colour. |
| 13 | Supply and fixing of TNEB meter board suitable for 32A three phase service connection with 3 Nos.32A fuse unit (500V) 32A neutra llink and earth link (1\\"x1/8\\"copper flat) on TW plank of size 600mmx450mmx19mm with supporting TW reepers of 1\\"thick an either side with painting with suitable bolt and nuts for fixing the TW plank on wall with earth connection and inter connection with 7/20 PVCinsulated copper wire from EB meter to fuse unit with 1No 40Amp 30MA Four Pole RCD / RCCB (Lower End) with suitable necessary connection. |
| 14 | Earthing as per PWD standard with an earth electrode of 2 metre Class'B'GI pipe of dia not less than 32 mm complete with necessary masonry work. |
| 15 | Add G.S.T. @ 18% Please Enable Macros to View BoQ information |