| 1 | Dismantling brick work or stone work in lime or cement mortar and including stacking of materials as directed be the Engineer-in-charge within a distance of 60 meter (200 feet).SI No.692 |
| 2 | E/W cutting with cartage upto 10km including all complete of work. |
| 3 | Excavation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 M. and lead upto 30 M. and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in charge upto a distance of 30 M. from the foundation trenches.SI No.251a |
| 4 | Concrete with 4 cm. gauge brick ballast, Fine sand of 1.25 F.M. and cement, in proportion of 12:6:1 in foundations and under floors, including supply of all materials, labour, Tools & plants etc. required for proper completion of the work.(S.I No-273) |
| 5 | M-150 Brick Work in 1:4 cement & c/sand 2.20 F.M mortar in foundation and plinth including supply of all materials, Labour and T&P etc. Required for proper completion of the work. (S.I-305) |
| 6 | 12mm thick plaster with cement and c/sand in 1:4 over brick work minimum thickness not to be less than 1cm. Including supply of all materials, labour, tools & Plants etc. required for proper completion of the work. (S.I-584) |
| 7 | Cement Concrete with 20mm gauge approved stone grit, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work. (S.I-279a) |
| 8 | Two coat Painting work etc with all complte work. |
| 9 | Providing wall putty one water proof cement paint of approved make and quality on new work with two coat to give an even shade including supply of all material,labour,tools&plantetc. |
| 10 | S/L of GSB 53-9.5mm thick S/B upto 10cm loose layer including etc including all complete of work. |
| 11 | Consolidation of GSB upto 10cm thick loose layer by road roller including etc.including all complete of work.S.I No.753 |
| 12 | P/L OF Hexagonal tile |
| 13 | S/F of m.s. angle frame with febrication T&P with all complte work |
| 14 | sign board |
| 15 | Cleaning of site with labour etc with all comp. of work |
| 16 | Supply and fixing of Leg press as per attached detail and specifications. |
| 17 | Supply and fixing of rowing as per attached detail and specifications. |
| 18 | Supply and fixing of Cross walker as per attached detail and specifications. |
| 19 | Supply and fixing of Arm as per attached detail and specifications. |
| 20 | Supply and fixing of chest Press as per attached detail and specifications. |
| 21 | Supply and fixing of Air walker as per attached detail and specifications. |
| 22 | Supply and fixing of Cycle/arm as per attached detail and specifications. |
| 23 | Supply and fixing of Abdominal as per attached detail and specifications. |
| 24 | Supply and fixing of Waist Twister Triple as per attached detail and specifications. |
| 25 | Supply and fixing of chin up as per attached detail and specifications. |
| 26 | Supply and fixing of zeem rubber as per attached detail and specifications. |
| 27 | S/f of R.C.C Bench |
| 28 | Deduction cost of dismental materials - Old brick Please Enable Macros to View BoQ information |