Tender For Construction / Upgradation Of Rural Roads Under Pradhan Mantri Gram Sadak Yojna Including Maintenance For Five Year After Construction.
Tender Value
3.45 Crore
Estimated cost
Bid Submission
13 Jul 2026
0 days left
EMD
3.45 Lakhs
Bank guarantee accepted
Document Fee
17700
Non-refundable
Tender Type
Online
Tender Overview
Organization
Tender ID
Competition Type
NCB
Bidding Type
Tender
Location / State
Umaria → Madhya Pradesh
EMD Exemption
Not Available
Quantity
Not Available
Website
Contact Person
Address
Project Description
Tender for Construction / Upgradation Of Rural Roads Under Pradhan Mantri Gram Sadak Yojna Including Maintenance For Five Year After Construction.
BOQ
| Sl. No. | Item Description |
| 1 | Road/Bridge Work |
| 2 | Construction/Upgradation of Rural Road and CDs under Package No. MP44901 (Offer Based on SSR issued by MPRRDA Effective from 01/01/2024) as per detailed BOQ attached in Annex-II A. Please Enable Macros to View BoQ information MPRRDA, PIU Umaria Annex-II A Bill of Quantity Details for the Percentage (%) Rate Tender Based on SSR 01/01/2024 District :- Umaria PIU :- Umaria Package No. :- MP44901 Sl. No. Block Name of the Road Length in Km |
| 3 | Karkeli |
| 4 | Karkeli |
| 5 | Karkeli Total Total Road Length 6.5 Amount of Construction Cost 33171000.0 Amount of Maintenance Cost 1420000.0 Total Amount of PAC 34591000.0 S.No. SOR No. DESCRIPTION OF ITEMS UNIT QUANTITY Pavement Work |
| 6 | 1.6 B. Reference piller (As per drawing annex-I) Per no 62.0 |
| 7 | 3.3(B) |
| 8 | 5.1(I) |
| 9 | 5.2(II) |
| 10 | 11.4(i) |
| 11 | 9.8 (E ) (A) NP3 Pipes 600 mm dia RM 140.0 ( E ) NP2 Pipes 300 mm dia RM 40.0 |
| 12 | 10.12 |
| 13 | 10.12 |
| 14 | 10.13 |
| 15 | 10.2 A . 900 mm equilateral & triangle Each 3.0 Stop sgn board Each 6.0 B 600 mm Circular Each 3.0 C 800 mm x 600 mm rectangular Each 3.0 D 600 mm x 450 mm rectangular Each 0.0 E 600 mm equilateral & triangle Each 12.0 F 900 mm High Octagon Each 0.0 |
| 16 | 10.6 (A) ii) Ordinary Kilometer Stone (Precast) Each 11.0 iii) 200 m stone (precast) Each 25.0 |
| 17 | 14.10 |
| 18 | 10.14 |
| 19 | 11.1 (II) Ordinary rock (not requiring blasting)i. Upto 3 m depth Cum 0.0 i)in rock Upto 3 m depth Cum 44.18 iv)hard rock (not requiring blasting) Cum 29.46 |
| 20 | 11.4(i) |
| 21 | 10.16 |
| 22 | 13.16(iii) |
| 23 | 11.4 (I) Foundation Concrete cum 19.98 |
| 24 | 12.5 (II-i) Face wall Pipe In Casing Number Pillers Deduction of opening of pipe cum 310.45 |
| 25 | 12.6 For number of Pillers 8 mm Dia Ring 8 mm Dia @ 0.394 kg/m = 5.122 kg T 0.0 |
| 26 | 9.3 Providing and laying ISI mark reinforced cement concrete hume pipe NP3 for culverts on first class bedding of granular material in single row including jointing with cement mortar 1:2 but excluding excavation, protection works, backfilling, bedding, concrete and masonry works in head walls and parapets Clause 1101.6 (B) 1000 mm dia RM 15.0 |
| 27 | 12.16 For number of Pillers 8 mm Dia Ring 8 mm Dia @ 0.394 kg/m = 5.122 kg T 0.0 9.3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design |
| 28 | 12.1 Below Face wall Granular material cum 292.87 |
| 29 | 7.5 Construction of un-reinforced and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and construction joints, applying debonding strips, primer, sealant, approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days, cum 16.1 |
| 30 | 12.9 Nos. 94.0 |
| 31 | 12.16 Sqm 48.0 General Manager MPRRDA PIU Umaria (M.P.) |
AI Tender Summary
Tender Timeline
Jun 19, 2026
11:30 IST
Tender Published
Tender notice published.
CompletedJul 13, 2026
17:00 IST
Bid Submission Deadline
Online submission via eProcurement portal.
TodayJul 15, 2026
Bid Opening Date
Technical bids will be opened and evaluated.
Upcoming · 2 daysTender Documents
Download All (ZIP) ↓
Disclaimer
We takes all possible care for accurate & authentic tender information. However users are requested to refer Original source of Tender Notice / Tender Document published by Tender Issuing Agency before taking any call regarding this tender