| 1 | Earth work in excavation of foundation in all kinds of soil within the initial lead and lift including dressing and levelling the bed and depositing the excavated materials away from the work site etc. all complete as directed by the Engineer-in-charge. |
| 2 | Shoring & shuttering for the excavated trench up to a depth of 1.5m. from G.L |
| 3 | Filling foundation and plinth with Sand well watered and rammed including cost,conveyance and royality of sand etc complete. |
| 4 | Supplying all labour,materials,T&P for Cement Concrete (1:3:6) in foundation using 4 cm size hard granite Hand Broken metal including cost of materials,royalty & conveyance charges with watering,curing all complete as per direction of Engineer-in-charge. |
| 5 | Supplying all labour,materials,T&P for ReinforcedCement Concrete M0-20 for reinforced cement concrete works in using 12mm to 20 mm size hard granite Crusher Broken chips including cost of materials,royalty & conveyance charges with watering,curing all complete as per direction of Engineer-in-charge.a) Raft |
| 6 | Straightening, cutting, bending and binding, welding and jointing (if necessary) coiled/bent up M.S. rods/Tor Steel/deformed rods etc. including hoisting, placing in position, tying the grills binding with 18 to 20 gauge binding wire required for R.C.C. work including cost, conveyance, taxes of all materials, cost of all labour, T&P etc. as required for the work complete (weight of binding wires will not be considered) as directed by Engineer-in-charge. |
| 7 | Rigid smmooth centring & shuttering in R.C.C. Foundation, Plinth Band, Footings, Bases of Columns, Mass Concrete & Precast Slabs etc. in Ground Floor. |
| 8 | For Wall |
| 9 | Supplying , transporting, fitting&fixing M.S. Fabricated Grill Window as per approved specification and direction of Engineer in Charge.Supply of aggregate |
| 10 | 40mm Metal |
| 11 | 20mm Chips |
| 12 | 12mm thick cement plaster (1:4) over brick work with cement punning for skirting |
| 13 | Finishing walls with water proofing weather coat over a coat of prmer of approved shade including cost conveyabce taxes of all materials etc complete. |
| 14 | Painting two coats with approved synthetic Enamel Paint on one coat of Primer including all cost of Paint Primer etc. Complete. |
| 15 | Supplying all materials,labour, T&P for fitting & fixing U PVC S.W.R pipes(4kg/cm2) and fittings of the following outside diameter including jointing with approved solvent cement by non-heat application method testing as per specification with lead of all materials to site.(i)110mm dia SWR Pipe |
| 16 | Supplying all materials, labour and T&P for fitting fixing of following types of P.H. Fittings etc. all complete. Please Enable Macros to View BoQ information |