| 1 | Labour charges for removing grass, thorney shurbs, Jungli shurb, Kubabhul and alike grass along roadside making the ground clean by showel and phavaras, excetra complete. |
| 2 | Excavation for catch / side water gutter in all sorts of soils to the specified section including stacking the excavated stuff in a regular bund and disposing off unsuitable or excess stuff as directed all sorts of soils. |
| 3 | Providing pick and roll surface by picking the old water bound macadam surface to the required standard, adding 30 percent of 40 milimetre size metal and required quantity of murum including laying sectioning, watering, compacting with static roller with thin layer of murum blindage on carrageway, watering and compacting by static roller, including cost of all materials, loading, unloading, stacking and labour, excetra complete. |
| 4 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification inciuding spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening / binding material to fill the interstices of coarse aggregate, watering and compacting with Vibratory roller to the required density. |
| 5 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening / binding material to fill the interstices of coarse aggregate, watering and compacting with Vibratory roller to the required density. - By Mechanical Means - Grading II Using Screening type-B |
| 6 | Providing and constructing 75 milimetre thick modified penetration macadam road surface including all materials, preparing the existing road surface, spreading 40 milimetre stone metal layers 30 percent crusher broken metal plus 70 percent hand broken (by breaking rubble obtained by blasting), heating and spraying the bitumen of of specified grade at the rate of 2 kilogram per square metre, spreading 12 milimetre size chips, compacting with three wheel static roller having weight 8 to 10 metric tonnes to achive the desired degree of compaction as per technical specification Clause 506, excetra complete. Including picking of existing water bound macadam surface. |
| 7 | Providing and applying tack coat on the prepared surface, heating by flames in boiler and spraying bitumen set footed in bitumen boller on black topped surface 2.5 killogram per 10 square metre. (Using VG-30 bulk bitumen) |
| 8 | Providing and Laying open graded premix surfacing of 20 milimetre thickness composed of 13.2 milimetre to 5.6 milimetre aggregates premixed with bituminous binder, transported to site with vehicle tracking system, laid over a previously prepared surface, finished to the required grade, level, alignment, and rolling to achieve the desired compaction, excluding prime / tack coat and seal coat. For Bitumen VG-30 bulk (Grade 60/70) - Using drum mix type hot mix plant with Supervisory Control and Data Acquisition, Paver and vibratory roller. |
| 9 | Providing bituminous type-A liquid seal coat on bituminous surface including supplying all materials and bitumen of VG-30 grade, preparing existing road surface, heating and applying bitumen at the rate of 0.98 kilogram per square metre by mechanical means, spreading chips and rolling by static roller having weight 8 to 10 metric tonne, excetra complete. |
| 10 | Supplying hard murum / kankar at the road site, including conveying and stacking, excetra complete. |
| 11 | Spreading hard murum / soft murrum / gravel or kankar for side width, excetra complete. |
| 12 | Compacting the hard murum side widths including laying in layers on each side with vibratory roller including artificial watering, excetra complete. |
| 13 | Providing & fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion & liability period etc', having rectangular shape of 1.20m X 0.90m size made out 18 gauge (1.25mm) thick M.S. sheet painted with one coat of Zinc chromate stoving primer & two coats of enamel paint on front side & grey stove enamel on back side & border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 X 35 X 3 mm frame with properly cross |
| 14 | Royalty charges for various building construction bonafied materials which are used for government bonafied works and for which Royalty charges are to be paid by the contractor. |
| 15 | Laboratory testing charges for various materials required for items of work, on the basis of testing frequency and charges fixed by Vigilence and Quality Control Circle, Pune. |
| 16 | Flekiness Index / Elongation Index Test for Metal below 40 milimetre |
| 17 | Sieve Analysis Test for Hard Murrm |
| 18 | Penetration, Softening Point, Flash and Fire Point, Specific Gravity for Asphalt VG-30 (Grade 60/70) |
| 19 | Ductility / Elastic Recovery for Asphalt VG-30 (Grade 60/70) |
| 20 | Sieve Analysis Test for Metal 40 milimetre and above (Hand Broken) |
| 21 | Extraction Test for Mix Material (OGC) |
| 22 | Goods and Services Tax Please Enable Macros to View BoQ information |