| 1 | Labour charges for removing grass, thorney shrubs, Jungli shrub, Kubabul and alike grass along roadside making the ground clean by showel and phavaras etc. complete. |
| 2 | Excavation for catch / side water gutter in all sorts of soils to the specified section including stacking the excavated stuff in a regular bund and disposing of unsuitable or excess stuff as directed all sorts of soils. |
| 3 | Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 450mm diameter in proper line, level and slope including providing and fixing collars in cement mortar 1:2 and curing etc. complete.BDG 1/11.08 |
| 4 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting with vibratory roller to the required density. By Mechanical Means -Grading I (Using Screening Type B (11.2 mm) Aggregate) |
| 5 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting with vibratory roller to the required density. By Mechanical Means -Grading Il (Using Screening Type B (11.2 mm) Aggregate) |
| 6 | Providing and constructing 50 mm. thick Modified Penetration Macadam (MPM) road surface including all materials, preparing the existing road surface, spreading 40mm. stone layers metal 30% crusher broken metal + 70% Hand broken metal (By breaking Rubble obtained by blasting) , heating and spraying the bitumen of VG-30 @ 1.75 kg / sqm, spreading 12mm.size chips compacting with Static roller having weight 8 to 10 MT. to achive the desired degree of compaction as per Technical Specification Clause 506 etc.complete, including applying tack coat at the rate of 0.30 Kg Sqm.( for repair works only) |
| 7 | Open Graded Premix Surfacing- Providing and Laying OGC 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates premixed with bituminous binder transported to site with VTS , laid over a previously prepared surface, finished to the required grade, level, alignment, and rolling to achieve the desired compaction but excluding prime / tack and Seal coat. For Bitumen of specified grade--USING drum mix type hot mix plant with SCADA, Paver and Vibratory roller ( Over MPM Surface) (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 8 | Providing bituminous Type A liquid seal coat on bituminous surface including supplying all materials and bitumen of specified grade preparing existing road surface, heating and applying bitumen @ 0.98 KgSqm. by mechanical means, spreading chips and rolling, by static roller having weight 8 to 10 MT. etc. complete. (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 9 | Supplying hard murum/ kankar at the quarry site, including conveying and stacking complete. |
| 10 | Spreading hard murum for side width complete spec. no 2.30 MORTH 408 |
| 11 | Compacting the hard murum side widths including laying in layers on each side with vibratory roller including artificial watering etc. complete. |
| 12 | Providing and fixing information sign board of size 1.20 x 0.90m 3913.05 No prepared on 18 guage M. S. Sheet with Horizontal bracing of single frame of size 25x25x5 mm including painting with one coat of zink cromae preimer and wo coats of oil painting including two angle ion post of size50x50x5 mm of 270 m long including all taxes, conveying fixing in ground with cement concrete 1:4:8 block of 45cmx45cmx45cm size as directed by Engineee-in charge etc complete. sec. No. S directed by Engineer-in-Charge etc complete |
| 13 | Basic Test of Aggregates - Sieve Analysis |
| 14 | Basic Test of Hard Murum - Sieve Analysis |
| 15 | BITUMEN - Penetration, Softening Point, Flash & Fire Point, Specific Gravity |
| 16 | BITUMEN - Extraction Test |
| 17 | Add Extra royalty Charges |
| 18 | Add 18% GST Please Enable Macros to View BoQ information |