| 1 | Excavation in trenches in soft/lose soil n.exc. 1.5M wide & n exc 1.5M deep for laying of GI/CI pipe line & getting out including forming bottom surface complete all as specified and directed. |
| 2 | Returning, filling in, trenches including spreading, levelling, watering and well ramming in layer n.exc. 250 mm in any type of soil after the pipe laid & tested complete all as specified and directed. |
| 3 | Removing excavated surplus soil to a distance n.exc. 50mtr and depositing where directed at a level n.exc. 1.5 m above the starting point complete all as specified and directed. |
| 4 | Disconnecting and Taking out old existing CI pipe including all fitting with spigot and socket ends and lead jointed any description / grade and in any position of trenches or under floors by breaking of PCC / tiles of any grade complete all as specified and directed for the following sizes :- |
| 5 | 200mm dia bore |
| 6 | 150mm dia bore |
| 7 | 100mm dia bore |
| 8 | Disconnecting and Taking out old existing GI pipe and connecting of any description / grade and any position of trenches including connecting fitting / accessoriese and fixtures complete all as specified and directed for the following size of pipe :- |
| 9 | 80mm dia bore |
| 10 | 50 mm dia bore |
| 11 | 40 mm dia bore |
| 12 | 25 mm dia bore |
| 13 | 20mm dia bore |
| 14 | 15mm dia bore |
| 15 | Material and labour for cast iron fitting upto size 150 mm dia bore such as bends ( any type radius and angle ) tapers any type , ( straight , bend , increasing , decreasing or double socket etc) Tee pieces single branch , \\"Y' junction , double branch, cross ( all sockets or socket and spigot ) collars, caps and plugs complete all as specified and directed. |
| 16 | Material and labour for replacement of rubber gasket joint for socket and spigot pipe complete all as required at site of following sizes :- |
| 17 | 200mm dia bore |
| 18 | 150mm dia bore |
| 19 | 100mm dia bore |
| 20 | 80mm dia bore |
| 21 | Taking down old existing sluice valve, Supply and fixing sluice valve PN-1.6 with stainless steel spindle conforming to IS-14846-2000 both end flanged including necessary nuts, bolts, washer and rubber gasket of the following sizes :- |
| 22 | 200mm dia bore |
| 23 | 150mm dia bore |
| 24 | 100mm dia bore |
| 25 | 80mm dia bore |
| 26 | Taking down old existing cast iron non return valve and supply and fixing cast iron non return valve, both ends flanged jointed, ISI marked of approved quality including necessary nuts, bolts, washer and rubber gasket of the following sizes :- |
| 27 | 200mm dia bore |
| 28 | 150mm dia bore |
| 29 | 100mm dia bore |
| 30 | Supply and fixing in replacement of Gun metal gate valve with iron wheel head screwed both ends for iron pipe including tasting of following :- |
| 31 | 50mm dia bore |
| 32 | 40mm dia bore |
| 33 | 25mm dia bore |
| 34 | 20mm dia bore |
| 35 | Supply and fixing in replacement of Bib taps 15 mm dia, PTMT any colour, high pressure screwed for iron pipes and fixed to pipe (minimum weight not less than 90 gms) complete all as specified & directed. |
| 36 | Material and labour for replacement of stainless steel spindle with check nut of suitable size of existing sluice valve complete complete all as specified and directed. for the following sizes :- |
| 37 | 200mm dia bore |
| 38 | 150mm dia bore |
| 39 | 100mm dia bore |
| 40 | 80mm dia bore |
| 41 | Supply and laying galvanised Iron tubes, medium grade, ISI marked complete with all fittings, laid in trenches complete all as specified and directed for the following sizes:- |
| 42 | 80mm dia bore |
| 43 | 50 mm dia bore |
| 44 | 40 mm dia bore |
| 45 | 25 mm dia bore |
| 46 | Supply and laying galvanised Iron tubes, medium grade, ISI marked complete with all fittings,fixing on walls including provision of suitable size of MS clamps for support to wall complete all as specified and directed. for the following sizes:- |
| 47 | 20 mm dia bore |
| 48 | 15mm dia bore |
| 49 | Material and labour for Ductile iron pipes with spigot and socket ends, centrifugally cast (spun) class K7, in any length, externally coated with metallic Zinc Coating finished with bituminous paint complete all as specified and directed of the following bore:- Note :- Excavation, earthwork and DI Joint shall be measured and paid separately. |
| 50 | 200mm dia bore |
| 51 | 150mm dia bore |
| 52 | 100mm dia bore Please Enable Macros to View BoQ information |
| 53 | 100mm dia bore Please Enable Macros to View BoQ information |