| 1 | Dismanteling/ Installation of 100/ 63 kVA distribution transformer |
| 2 | Dismanteling/ Installation of 250/ 200 kVA distribution transformer |
| 3 | Dismanteling/ Installation of 400/ 630 kVA distribution transformer |
| 4 | Supply Installation testing and commissioning of 11 KV LA (9KV,10KA,station type) |
| 5 | Supply Installation testing and commissioning of 11 KV GO AB switch 3 pole 200 Amp |
| 6 | Supply Installation testing and commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 7 | Providing and laying of 70mm² single core Cable,1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type |
| 8 | Providing and laying of 120mm² ,240mm² (2Ckt for 250kVA) single core Cable,1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type |
| 9 | Providing and laying of 240mm² single core Cable,1.1kV Grade, XLPE Insulated Stranded Conductor FRLS type (44mtr for 1 Ckt) |
| 10 | Providing and laying of 300 mm², Single Phase Cable,1.1K V Grade, XLPE Insulated Stranded Conductor FRLS type |
| 11 | Providing and laying of 400mm² (3Ckt) for 630kVA , Single Phase Cable,1.1K V Grade, XLPE Insulated Stranded Conductor FRLS type |
| 12 | Supply Installation testing and commissioning of 9 Mtr. Long Pole(ST-410 SP33) along with earthing and cement bottoming as per standard |
| 13 | Providing and fixing of GI Channel / Angle/ Flat of sizes including clamps |
| 14 | Providing and fixing Galvanized Nuts & Bolts of sizes |
| 15 | Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover. |
| 16 | 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm |
| 17 | Galvanised Stay Set with 50x8mm stay clamp, guy insulator(2Nos.), anchor plate (200x 200 x 6 )mm, nut-bolts, 2 Nos turn-buckles, 1.8m long, 16 mm diameter solid GS stay rod & 7/3.15 mm dia GI stranded wire complete |
| 18 | Providing and fixing Wedge connectors/ PG clamps |
| 19 | Providing and fixing Danger plates with clamps |
| 20 | Providing and fixing GI barbed wire for Anti Climbing |
| 21 | Painting of poles Al Paint |
| 22 | Painting of poles Red Oxide Primer |
| 23 | LT Distribution Box for:- 63 kVA DTR with 100 Amp MCCB 3P 16 kA for incomer & 100 Amp MCCB 3P 16 kA 1 No. and 63 Amp MCCB 3P 16 kA 1 No.s for Outgoing Circuits. . |
| 24 | LT Distribution Box for 100 kVA DTR with 160 Amp MCCB 3P 16 kA for incomer & 100 Amp MCCB 3P 16 kA 2 No.s for Outgoing Circuits. |
| 25 | LT Distribution Box for 200 kVA DTR with 315 Amp MCCB 3P 25 kA for incomer & 160 Amp MCCB 3P 16 kA 3 No.s for Outgoing Circuits. |
| 26 | LT Distribution Box for 250 kVA DTR with 400 Amp MCCB 3P 36 kA for incomer & 200 Amp MCCB 3P 16 kA 1 No. and 160 Amp MCCB 3P 16 kA 2 No.s for Outgoing Circuits |
| 27 | LT Distribution Box for 400 kVA DTR with 630 Amp MCCB 3P (36 KA) adjustable 1 No. for incomer & 200 Amp 3 P (16 KA) 4 No.s fixed for Outgoing Circuits. |
| 28 | LT Distribution Box for 630 kVA DTR with 1000 Amp MCCB 3P (36 KA) adjustable 1 No. for incomer & 250 Amp MCCB 3 P (25 KA) 2 No.s fixed & 200 Amp MCCB 3 P (25 KA) 3 No.s for Out going. |
| 29 | Sundry items like Aluminium lugs, Jumpers, Binding Tape, |
| 30 | Supply Installation testing and commissioning of 8 Mtr. Long ST pole SP-15 along with earthing and cement bottoming as per standard |
| 31 | 0.05 ACSR Conductor Please Enable Macros to View BoQ information |