| 1 | Excavation in Foundation including in ordinary soil (Loam clay, or sand) wtering lift upto 1.5meter and lead upto 30m. including filling. the sides and of foundation ramming of excavated earth into the trenches or into disposal trenches or into the plinth and removal and of surplus earth as directed by the Engineer-in-charge upto a distance of 30M. (100fts) from the foundation trenches. |
| 2 | Concrete with 4cm gauge stone ballast, coarse sand & cement in poroportion of 8:4:1 (8 graded stone aggregate: 4 coarse sand : 1cement :) including supply of all material, labour and T&P etc. required for proper completion of the work as per direction of Engineer-in-Charge. |
| 3 | R.C.C. work with cement, approved coarse sand & 2cm gauge approved stone grit in proportion of 1:1.5:3 in RCC Raft foundation footing and RCC column excluding supply of reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. binding wire and including necessary centering and shuttering etc and also including supply of all material, labour and T&P etc. required for proper completion of the work as per direction of Engineer-in-Charge. |
| 4 | M.S. (tor Steel or plain) in Plain work such as R.C.C. workincluding beding for proper shape as necessary including bendingfor proper complition of the work and including supply of allmaterial and wastage, bend hooks, and authorised overlappingshall be measured labour and T&P etc. required for propercompletion of the work as per direction of Engineer-in-Charge.Work Including cost of binding wire |
| 5 | Taking out existing kerb stones of all types from footpath/ centralverge, including removal of mortar etc., disposal of unserviceablematerial to the dumping ground, for which payment shall be madeseparately and stacking of serviceable material within 50 metrelead as per direction of Engineer-in-Charge. |
| 6 | Laying at or near ground level old kerb stones of all types inposition to the required line, level and curvature, jointed withcement mortar 1:3 (1 cement: 3 coarse sand), including makingjoints with or without grooves (thickness of joints, except at sharpcurve, shall not be more than 5 mm), including making drainageopening wherever required etc. complete as per direction ofEngineer-in-charge. (Length of finished kerb edging shall bemeasured for payment). (Old kerb stones shall be supplied by thedepartment free of cost) |
| 7 | Concrete with 2cm gauge stone grit, coarse and cement inproportion of 4:2:1 including supply of all material, labour and T&Petc. required for proper completion of the work as per direction ofEngineer-in-Charge. |
| 8 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including qutting, hoisting, fixing in position and applying a priming coat of approved stèel primer, including welding and bolted with special shaped washers etc. 10.16.1 Hot finished welded type tu |
| 9 | Painting priming and roofs or othe iron work in large areas with one coat two coat of approved (above or equivlent) including supply of all materials, labour Tools & plants etc. required for proper completionof the work. |
| 10 | Providing wall putty on new surface with approved quality material of Berger/J.K./Birla or similar make 2 coats. |
| 11 | Fioviding wall putty on old surface with apaproved quality material of berger/J.K./Birla or similar make 2 coats. Please Enable Macros to View BoQ information |