| 1 | Item Rate BoQ BoQ_Ver3.0 Item Rate Normal INR Only INR Select, Excess (+), Less (-) Less (-) Tender Inviting Authority: GE Utilities Udhampur Name of Work: Repair/Maint to solar power plants and lightening arrestors under GE (Utilities) Udhampur. Contract No: GE/U-75/2026-27 Bidder Name : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # Ser.No. Item Description Item Code / Make Quantity Units Estimated Rate Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder Rs. P Excise Duty VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category TOTAL AMOUNT Without Taxes TOTAL AMOUNT TOTAL AMOUNT In Words |
| 2 | Taking down old U/S Solar Modules, Supply, installation, testing, and commissioning of a solar photovoltaic (PV) system of cumulative capacity in KWp (AC output), as per site-specific requirements. The system shall comprise high-efficiency PV modules (ranging from 300W to 600W) associated cabling, safety systems and other balance-of-system (BoS) components.The installation shall be carried out in accordance with best industry practices and under the supervision of the Engineer-in-Charge, ensuring full compliance with relevant national and international standards. |
| 3 | Taking down old U/S DC Cable and Supply,fixing,Testing and commisioning Solar DC Copper Cable 4mm² single core XLPE UV Resistant complete & LSZH sheathed 1100V AC/1800V DC complete all as specified in Particular Specification and directed by Engineer-in-Charge. |
| 4 | Taking Down old U/S HDPE Pipe and M&L Protection Pipe for 4 sqmm copper cable High density polyethylene pipes (HDPE) of min 16 sqmm cross section area and pressure rating 6 kgf/cm2 for protection of copper cable laid in fixed on wall with GI support, Clamp included complete all as specifed and directed by Engineer-in-Charge. |
| 5 | Complete Repair and Maintenance of existing ACDB/DCDB boxes, including safe electrical isolation, systematic disconnection, and serviceability audit of all internal components. Scope includes the thorough decarbonization of the panel (internal and external)to remove all carbon deposits and oxidation; cleaning with cotton waste; and replacement of damaged/faulty spare parts with brand-new, original-spec components only upon prior approval from the Engineer-in-Charge. Work concludes with professional re-termination of all connections, cable dressing, and testing for electrical integrity as per Particular Specifications and to the complete satisfaction of the Engineer-in-Charge. |
| 6 | (a) Fuse (b) Surge Protection Device ( SPD) Board(c) DC SPD with board(d) AC SPD with board (e) AC Socket with cable(f) Mounting Structure(g) SPN(h)TP MCB (j) Din RailNote: All item replaced will be measured and Paid separately. |
| 7 | S&F in repair Type 2 DC SPD System Voltage: 1000V DC Uc: 1100V DC In: 20 kA Imax: 40 kA Up: ≤ 3.5 kV, 3P Standard: IEC 61643-31 Mounting: DIN Rail of complete all as specifed and directed by Engineer-in-Charge. |
| 8 | S&F in repair Type 2 AC SPD System Voltage: 415V AC Uc: 385V AC In: 20 kA Imax: 40 kA Up: ≤ 1.8 kV, 4P Standard: IEC 61643-11 Mounting: DIN Rail complete all as specifed and directed by Engineer-in-Charge. |
| 9 | S & F of DIN Rail suitable for Mounting MCCB, Relays, SPDs within the Panel Enclosure complete all as specifed and directed by Engineer-in-Charge. |
| 10 | Taking down old U/S Earth lekage relay, Supply and fix Earth relay , with digital microprocessor / Microcontroller based, test and reset facility, CBCT/ZCT connection monitoring facility, true RMS complete all as specifed and directed by Engineer-in-Charge. |
| 11 | Repair,and Maint of U/S 50 kW Solar On-Grid String Inverter, including fault identification, dismantling, repair/replacement of defective parts, and reassembly. Scope includes supply and replacement of components such as M1 Controller Boards (10 & 12 string), P Board, W Boards (10 & 12 string), M3 (L) Board, C1 (S) Board, Fuse Board (12 string), DC power cords, cooling fans, AC plug & socket, and other associated parts as required. Work also includes internal cleaning, checking/tightening of connections, testing of DC/AC performance, ensuring proper grid synchronization.Note: Rate shall include all materials, labour, testing, and to & fro transportation from site to workshop, complete all as specifed and directed by Engineer-in-Charge. |
| 12 | Description all as per Item Ser No 9.00 here-in-before, but for capacity 20 kW |
| 13 | Description all as per Item Ser No 9.00 here-in-before, but for capacity 15 kW |
| 14 | Comprehensive checking and functional assessment of all existing MC4 connectors within the solar PV array. Scope includes visual inspection for thermal degradation, UV damage, or ingress of moisture; electrical testing for continuity and contact resistance; and verification of secure \\"click-lock\\" engagement. All work to be executed in strict compliance with safety protocols complete all as specifed and directed by Engineer-in-Charge. |
| 15 | Periodic checking and technical tightening of all fasteners, nuts, bolts, and clamps (including mid-clamps and end-clamps) of the solar module mounting structure. Scope includes verifying the structural integrity of all members, ensuring uniform tension to prevent vibration or loosening due to wind loads, and applying anti-rust/cold galvanizing spray where necessary. All work to be performed using calibrated torque wrenches to specified Newton-meter (Nm) values as per the manufacturer's design, strictly adhering to the Particular Specifications , complete all as specifed and directed by Engineer-in-Charge. |
| 16 | M&L for Mild Steel angle channel Hot Dip Galvanized Module Mounting Structure for 525 Wp, 310 Wp, 325wp, 250 Wp rated solar module over RCC Roof comprising of angle iron, channel, GI pipe of medium grade , MS plate 5mm thick & SS 304 Fasteners to sustain wind speed of 150 km/hr as per IS 875 part 3 , tilt angle as per OEM ( MNRE approved solar consultant) Complete all as specified in Particular Specification , complete all as specifed and directed by Engineer-in-Charge. |
| 17 | Periodic checking and measurement of Earth Pit resistance values using a calibrated Earth Tester (Digital/Analog) for all lightning and power earthing systems. Scope includes the inspection of electrode-to-soil contact, cleaning of terminals, and technical verification of low-impedance paths. All measured values shall be documented and formally reported to the JE-in-Charge in the prescribed MES (Military Engineer Services) format. Work must be carried out as per specified standards and strictly as directed by the Engineer-in-Charge. |
| 18 | Taking down old U/S down conductor,Supply and Fix of 1.1 kV grade, 70 single core PVC/FRLS insulated flexible copper conductor cable (down conductor) suitable for lightning discharge complete all as specifed and directed by Engineer-in-Charge. |
| 19 | Periodic inspection and performance evaluation of Solar PV panels at defined intervals to ensure optimal system efficiency. The work shall include visual inspection for physical damage, dirt accumulation, shading, hotspots, and loose connections. Performance assessment shall be carried out using I-V curve tracing, string current and voltage measurement, and comparison with standard expected output under prevailing irradiance conditions using a solar irradiance meter. Cleaning status and mounting structure integrity shall also be verified. Any deviation from standard performance shall be recorded and reported with corrective recommendations to the Engineer-in-Charge. |
| 20 | Cleaning of Solar PV modules of sizes range from 300-600 Wp by washing, sprays, brushes, tools and plants, with mild soap based solution & as per laid down norms for solar power plant complete all as specifed and directed by Engineer-in-Charge including providing arrangements for taking water from tapping point to modules. Note:1) Each Panel cleaned completly will be considered as one job. 2) Any damage to existing strucure/Plant while cleaning will be fix/replace by contractor at no Extra Cost. |
| 21 | Excavation in trenches n. exc. 1.5 mtr in wide and n. exc. 1.5 mtr in depth for laying of underground cable and getting out in soft/loose soil complete all as specifed and directed by Engineer-in-Charge. |
| 22 | Returning, filling in excavated soil in trenches including spreading, leveling, watering and well ramming in layers n. exc. 25 cm thick complete all as specifed and directed by Engineer-in-Charge. |
| 23 | Removing of excavted soil to a distance n. exc. 50 mtr and deposited where directed at a level not exceeding 1.5 mtr above the starting point complete all as specifed and directed by Engineer-in-Charge. |
| 24 | Taking down old U/S Flexible Cable and Supply,fixing,Testing and commisioning Aluminium PVC Flexible Cable 1.1KV, 3.5 core, 35 sqmm heavy duty in DWC Pipe of suitable size and fixing of pipe with clamps on wall/floor/underground complete all as specifed and directed by Engineer-in-Charge. |
| 25 | Taking down old U/S Flexible Cable and Supply,fixing,Testing and commisioning Aluminium PVC Flexible Cable 1.1KV, 3.5 core, 70 sqmm heavy duty in DWC Pipe of suitable size and fixing of pipe with clamps on wall/floor/underground complete all as specifed and directed by Engineer-in-Charge. |
| 26 | Supply, and fixing of Current Transformer (CT) of ratio 200/5A, accuracy Class 1, burden 5 VA, suitable for metering applications, complete with resin-cast insulation, primary and secondary terminals, mounting accessories, and conforming to relevant IS/IEC standards. The CT shall be suitable for indoor/outdoor use as required and capable of reliable performance under specified operating conditions, complete all as specifed and directed by Engineer-in-Charge. |
| 27 | Taking down old US Pipe protection and Supply and lay DWC (Double wall corruguated) pipe 40x32 mm conforming to IS: 14930/ IS 16205 for protection of earth strip including necessary snap-fit coupler required for fixing complete all as specifed and directed by Engineer-in-Charge. |
| 28 | Supply and fixing of 30- 50 Wp IEC-certified mono/poly crystalline solar PV module with anodized aluminum frame, suitable for outdoor installation with high efficiency and 25-year performance warrantyfrom panal manufacturer complete all as specifed and directed by Engineer-in-Charge. |
| 29 | Supply and fixing of hot dip galvanized GI module mounting structure with ≥80 micron coating, designed for site-specific tilt angle and wind resistance up to 150 km/h for solar street light complete all as specified and directed by Engr-in-Charge. |
| 30 | Supply and fixing of 30 W LED street light fixture with luminous efficacy ≥130 lm/W, IP65/66 protection, CRI ≥70 and minimum 50,000 hours life complete with heat sink complete all as specifed and directed by Engineer-in-Charge. |
| 31 | Supply and fixing of constant current LED driver with power factor ≥0.95, efficiency ≥85% and inbuilt protections like short circuit and surge protection, complete all as specifed and directed by Engineer-in-Charge. |
| 32 | Supply of 12.8V 60 Ah LiFePO₄/Lithium battery with minimum 2 days backup and cycle life ≥2000 cycles suitable for solar street light complete all as specified and directed by Engineer-in-Charge. |
| 33 | Supply and fix of IP 65 weather proof battery box made of Metal with anti-theft and corrosion-resistant features complete all as specified and directed by Engineer-in-Charge. |
| 34 | Supply and fix of MPPT/PWM solar charge controller with dusk-to-dawn operation and protections against overcharge, deep discharge and reverse polarity complete all as specified and directed by Engineer-in-Charge. |
| 35 | Supply of IP65 weatherproof junction box with terminal connectors for safe electrical connections complete all as specified and directed by Engineer-in-Charge. |
| 36 | Taking down old U/S MCB, Supply and fixing 240V, 10 KA 'B' curve SP miniature circuit breaker (MCB) of single poles and current carrying capacity 6 to 32 AMP, in the MCB DB/ Solar ACDB Complete with connection testing and commissioning complete all as specified and directed by Engineer-in-Charge. |
| 37 | Taking down old U/S MCCB, Supply and fix MCCB 4 pole , Ics=100%Icu- 16 KA, 415 Volts, 63 Amps , with thermal adjustable and fixed magnetic setting with extended terminals complete all as specified and directed by Engineer-in-Charge. |
| 38 | Taking down old U/S MCCB, Supply and fix MCCB 4 pole , Ics=100%Icu- 30 KA, 415 Volts, 100 Amps ,with thermal adjustable and fixed magnetic setting with extended terminals complete all as specified and directed by Engineer-in-Charge.. |
| 39 | Taking down old U/S MCCB,Supply and fix MCCB 4 pole , Ics=100%Icu- 36 KA, 415 Volts, 125 Amps ,with thermal adjustable and fixed magnetic setting with extended terminals complete all as specified and directed by Engineer-in-Charge. |
| 40 | Taking down old U/S MCCB, Supply and fix MCCB 4 pole , Ics=100%Icu- 36 KA, 415 Volts, 200 Amps ,with thermal adjustable and fixed magnetic setting with extended terminals complete all as specified and directed by Engineer-in-Charge. |
| 41 | Taking down of U/S Pointed Rod and Supply and install Air termination rod, Single pointed Aluminium Rod 12 mm dia and 300 mm long complete all as specified and directed by Engineer-in-Charge. Note : (a) Necessary PCC foundation for termination rod fixing is inclusive of rate quoted by contractor.(b) Site clearance after fixing shall be done by contractor. |
| 42 | Taking down of U/S Pointed Rod and Supply and install Air termination rod, Single Pointed Copper rod 12 mm dia and 300 mm long complete all as specified and directed by Engineer-in-Charge. Note : a) Necessary PCC foundation for termination rod fixing is inclusive of rate quoted by contractor.b) Site clearance after fixing shall be done by contractor. |
| 43 | Supply and fix Aluminium Strip 25x3.15 mm with saddles and fixing screws etc. for roof conductors and down conductors above ground complete all as specified and directed by Engineer-in-Charge.Note : a) Necessary T&P required for fixing of Aluminium strip is inclusive of rate quoted by contractor.b) Site clearance after fixing shall be done by contractor. |
| 44 | Supply and fix Galvanised iron strip 32 x 6 mm buried in ground complete all as specified and directed by Engineer-in-Charge.Note : a) Necessary T&P required for fixing of GI strip is inclusive of rate quoted by contractor.(b) Site clearance after fixing shall be done by contractor. |
| 45 | M&L for colour coding of earthing pit cover and indication plate with rod with the following colour:-Red for chemical earth pit.Yellow for conventional earth pit. The numbering / Marking of earth pit will be in capital black colour and is to be done complete all as specified and directed by Engineer-in-Charge. |
| 46 | M & L for industrial salt for earthing pit recharging complete all as specified and directed by Engineer-in-Charge. |
| 47 | M & L for technical grade Magnisium Sulphate for earthing pit recharging complete all as specified and directed by Engineer-in-Charge. |
| 48 | M& L Char Coal for earthing pit recharging complete all as specified and directed by Engineer-in-Charge. |
| 49 | M&L for Earthing complete with galvanised steel earth plate electrode 60×60cm.× 6mm thick, buried directly in ground (earth pit not less than 2.25 metres deep below ground level) with top edge of the plate not less'than 1.5 metres below normal ground level, connected to galvanised earth lead wire 4.0mm dia by means of bolts, nuts, check nuts and washers , of GI or steel, including PCC (concrete chamber) shall be PCC 1:3:6 type C-1 using 20mm graded stone aggregate, with fair finish internal surface of concrete chamber shall be given 15mm thick plaster in CM 1:4, funnel with wire gauge mesh, 80 mm thick RCC pit cover 320 mm x 320 mm of RCC 1:2:4 type B-1 using 20 mm graded stone aggregate reinforced with XPM, JALLI and charcoal dust and common salt all as shown in electrical plate No 3 of MES SSR Part-I (2009) and specified including provision of GI strip protected by 40 mm dia medium grade pipe and watering pipe shall be 20mm bore medium grade, and including all excavation and earth work & connecting the earthing to an earthing test point complete all as specified & directed by Engr-in-Charge. |
| 50 | M & L for chemical earthing complete with copper plate earth electrode 90cm x 60cm x 5 mm thick buried directly in ground (earth pit not less than 4.00 mtr below ground level with top edge of plate not less than 3.25 mtr below ground level) brazed with copper strip 50x6 mm size 7.5 mtr long and connected to copper strip of any size by means of copper bolts, nuts, check nuts and washers complete all as specified and directed by Engineer-in-Charge.Note:- The rated quoted is deemed to the inclusive of the followings:-(a) The excavation and earth work (filling in, ramming in layers, watering etc as directed) in any type of soil for earth pit (pit size 1.20x 1.20x4.0mtr).(b) Perforated GI tubing (ISI marked) light grade 80mm bore 7.0 mtr long for strip protection and watering.(c) Common salt charcoal dust in alternative layers of 15cm, up to 90cm above the top of copper plate and one layers of 15cm Magnesium sulphate (MgSo4) all as directed (Salt - 500Kg, Charcoal dust - 1000 Kg & MgSo4 - 150 Kg). |
| 51 | (d) Earth chamber of internal size 600mm x 600mm x 600mm, built in PCC (1:3:6) type C2 bed 15cm thick at bottom, brick work in CM 1:6 upto 45cm over PCC bed and PCC (1:3:6) type C1 coping 15cm above, embedded with MS angle 50mmx50mmx3mm frame work duly painted with anti corrosive bituminous paint, with and including RCC slab 50mm thick in cement concrete (1:2:4) type B1, reinforced with XPM (weight not less than 4 kg per Sqm) having lifting arrangement duly painted in green and making earth pit as directed.(e) On testing, after completion, if the earth resistance <2 ohms is not obtained, earthing will be regenerated at no extra cost till the desired earth resistance is obtained.(f) GI tubing, bib tap etc for provisioning of continuous water supply at earthing pit will be measured and paid seperately under respective schedule of the contract. |
| 52 | M & L in replacement of earhing pit GI funnel as per sample complete all as specified and directed by Engineer-in-Charge. |
| 53 | Supply and fix of the Earth Pit Chamber Board of 3.15 mm thick mild steel sheet of size min 45 cm X 30 cm fixed with 12 mm thick MS rod two nos up to 90 cm Height by nut/bolts including spray painting with two coats of synthetic Enamel Black Paint complete MS Sheet both side including writing letters min 6 cm height i.e. Earth Pit No. , Location, Earthing test value and date and other letters complete all as specified and directed by Engineer-in-Charge. |
| 54 | Taking down of U/S LA Set Supply , installation testing & commissioning of Lightning Protection (LA) SET with following specifications:-a) Radius of Protection = 42mtrb) Current capacity= 200KAc) Additional protection= SFCHd) Weight= 3.5kge) Length= 505mmf) Accessories box with following 8 Nos M8 allen bolt with washer , 2 Nos M16 Expansion bolt G. I , 4 Nos of cable Tie nylong) Coupler and Mast with following:-Cemented flat surface installation with circular base plate haviong main pipe out diameteras 48mm & thickness 3.2mm circular bottom plate of diameter 220mm and having thickness as 10mm is welded directly ewith the pipe to from a single piece of without nay joint for stability at bottom. The bottom plate is furnished with 04 Nos of 16mm holes for securing the mast on the Cemented flat surface made of G.I, At top of the mast insullation is provided from lightening arrestor via derlyn mast coupler(MC), The total height of mast is 4500mm. |
| 55 | Taking down old U/S solar street Light, supply & fixing of solar street Light ALL IN TWO STANDARD of capacity 30 Watt and Luminance Efficacy >150 Lm/W, PIR Motion Dimming and Monocrysralline Solar Panel capacity of 60 Wp with MPPT charge controller and 12.8V, 30Ah Li-Po4 Battery ,IP65,IP66 rated enclosure 4500-5000 Lumen aluminium body on pole 7m above the ground all as specified and directed by Engr-in-Charge. Total in Figures 0.0 0.0 INR Zero Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 Zero Only Quoted Rate in Words INR Zero Only Please Enable Macros to View BoQ information |