| 1 | Pipes Works |
| 2 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m inwidth) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed:All kinds of soil |
| 3 | Refilling of Excavated soil back into trunches |
| 4 | Providing and Laying / Fititng of G.I Pipes 50mm Dia (M) |
| 5 | Carriage of G.I Pipes for average 200 Mtr by HL |
| 6 | Welding of Joints bt Electric arc Welding including testing and commissioning of joints includes carriage if set and all other accessories including making arrangement for electric supply /arrangement for generator etc. Complete job |
| 7 | Making interconnection of G.I distribution branch with G.I main by providing and fixing tee, Union including cutting and threading of pipes etc, Complete 50 mm to 80 mm Dia |
| 8 | CI CHECK VALVE 50MM |
| 9 | Civil Work |
| 10 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m inwidth) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed:All kinds of soil |
| 11 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering – All work up to plinth level 1:3:6 (1 cement: 3 Coarse sand: 6 graded stone Agg. 40 mm nominal size) Crushed |
| 12 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting , hoisting , fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. Hot finished welded type tubes |
| 13 | Structural steel work in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete.Welded for Door and Window |
| 14 | Providing and laying Steel Bar Square for Grill . |
| 15 | Providing and laying MS patti .20x6mm |
| 16 | Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle iron and 3mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer.Using M.S. angles 40x40x6mm for diagonal braces |
| 17 | Providing corrugated G. S. sheet roofing including vertical/curved surface fixed with polymer coated J or L hooks, bolts and nuts 8mm diameter with bitumen and G.I limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (upto any pitch in orizontal/vertical or curved surface)excluding the cost of purlins, raftersand trusses and including cutting to size and shape wherever required. 0.50 mm thick with zinc coating not less than 275 gram/m2 |
| 18 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc.complete.40mm thick with 20 mm nominal size stone aggregate. |
| 19 | Dumping of stone 20 % boulder |
| 20 | Mechanical Work |
| 21 | HC PumpProviding of Horizontal Centrifugal pump set 2000 GPH X 350 MH (02No.) along with suitable Induction motor & base frame at Pumping Station Dharati KG Mandir under Distt,Capex. Carriage/ shifting of pumping machinery by M/T up to stacking place road side with loading/unloading charges, then H/L from stacking place up-to pump room by dragging/ tying with wooden logs/ropes and manual labour. Laying of RCC foundation block for HCP set by way of excavation of trench in the pump room as per the size of HCP set and disposal of exuviated waste material outside premises with the help of manual labour. The job includes fabrication, welding, laying of steel mesh made from tar steel placed horizontally, vertically, and diagonally at equal distance including form work. Placing/ leveling he base frame with the help of leveling tool. Fabrication/fixing of foundation/anchor bolts. Llaying of foundation block of RCC in the ratio (1:1.5:3) cement, sand, bajri mix sufficiently elevated with respect to floor level. The entire block to be laid in such a way that it can dump all types of mechanical vibrations created by dynamic load of HCP set. Fastening the foundation bolts and curing properly. The job includes cost of cement, Bajri, steel, carriage of material & labour charges.Mechanical Installation of HCP set by way placing pump & motor on base frame Coupling with coupling pulley set, proper leveling with steel shims, tools/ tackles etc. Fabrication/Laying of Suction line from outlet of sump tank to suction flange/head of HCP by way of providing Gl pipe 50 mm Ø (Medium), cutting of pipe of required length, providing,/ fitting of M.S. flanges as per suction size of pump. Providing/ fitting of heavy duty Sluice valve 50 mm ( 01 No.) with flanges as per size of valve at appropriate place in the suction line. Providing, Fabrication/laying of delivery line by way of providing/fitting of G.l pipe 50mm@ (Medium), cutting of pipe of required length from delivery head/flange of HCP set to rising main with P/F of M.S flanges as per delivery size of pump. P/F of heavy duty Sluice valve 50 mm Ø- ( 01 no.), Reflux Valve 500J mm ( 01 no.) with flanges as per size of valves at appropriate place in the delivery line. The job includes P/F of M.$ bends, flanges, nut-bolts, washers etc. Both suction & delivery pipes and accessories should be independently supported near the pump, so that when the flanges, bolts are tightened no strains will be transmitted to the pump casing. Ccomplete wvelding of suction/delivery lines with good quality electrodes to make leak proof joints. Painting of Suction and delivery pipeline of HCP set with recommended colours with single coat of premier and double coat of superior quality of paint.The complete job includes cost of material carriage/ shifting charges of material, welding charges, skilled/semi-skilled labour charges and hire charges of tools / tackles..Electrical InstallationDesign, fabrication, installation, testing and commissioning of air break star-delta auto starter-cum-fault analyzer-cum-automation & FASD protection panels suitable to run an induction motor. The job involves fabrication of starter with Power Contractors and MCCB as per given scheme.Typ eDescriptio nContractor 1Contract or 2Contractor 3MCCB170 Amp. LT Control PanelMNX -70MNX -70MNX-50100 AmpContactors Make:-ISl Reputed Make,MCCB:-ISI Reputed MakeFASD starter are to be provided with following configuration: .systemn is to be providedwith solid state fault analyzer-Thecum-controller (CB-45A). The complete System is to be enclosed in wall/ floor mounted MS steel enclosure box of suitabledimensions. The ahas been finished with powder coatedpainting enclosurefrom outer surfaceofapproved inside aswellasfromcolor.Theenclosure should have frontshuttermountedwith key locking system having glass window, digital electronic volitmeter, ampere mete, have been provided alongwiththe requiredcurrenttranstormer and selectorswitches Theinternal wiring should be done with flexible PVC LT cable with properthimbling at each end,FEATURESANDSPECIFICATIONS:1.Automation :- Thesystemtripsthe motoronpower failureandonappearance of any electricalfaultmentioned belowwhichmay otherwisedamagethemotor field coils and restart the motor automatically onresumption of the power and also onrectificationoftheappearedfault, thus providing automationtothesystemandprotection tothe motor. 2.The system/star Delta starter should not fall into delta if it doesn't fall into star mode first and should remain de-energized to avoiddamage to the motor/ machinery and also to the power source/transformer3.The system/star delta auto starter should trip off if it does not fall intodelta & remains in star mode for more than ` 10-20 seconds.4.Overload Relay to be provided as per amperage if required Thesystem shouldprovideprotection against:-1.LOW voltage (below350V)2.High voltage(above 450 V)3.Singlephasing4.Reversephasing5.Un -balancedphasing(a difference of 35 to 45V between anytwophases)6.Dry Running7.Overloading (on althe 3 phases)INFORMATION SECTIONIn additionthesystem shouldhave:1.Separate LED fault/status indictorsLED phase indicators 2.LED phase indicatorsAn isolation by pass system, fault analysis system, with a blinking 3.-indicator.3 LED, contractor \\"COIL OK\\", indicators, one for each the 4.contractors/coils, LED star& delta indicators to access the star to delta timing.A tamper proof starting system to avoid manipulations by the motor 5.operator to keep the system in a permanently ON position.Electrical Installation by way of fabrication, providing & fitting of panel board of size 6'x4' to be fabricated out of 40 mm x 40 mm x 6 mm MS angle Iron having a rectangular frame with a provision for grouting in wall/floor, fitted with 12 mm thicksided mica ply board of size as oneper site requirement with nuts-bolts and washers and proper fixing of the panel board. P/F of 01 No. Voltmeter (0-500 V) range, P/F of 01 No, ammeter (0-200 A) range with CT's having suitablereductionratio, P/F of single phase preventer (01 No.), P/F of 03 nos. phase indicators & 02 Nos. selector switches, 200 amps bus bar system on the panel board and making necessary electrical connections of voltmeter,ammeter, single phase_ preventer, selector switches with suitable rating copper cable. Drilling of holes for fitting on iron frame. P/F of 400 amp. 451 volt , 3 phase Change Over/Main Switch and P/F star delta starter 80 HP on panel board by way of drilling holes providing of nuts , bolts washers etc. P/f of approximately 60 mtrs aluminum cable 300 mm² single core (Armoured) in three leads for three phases to be laid for making connections from L.T pole to main switch and then to voltage stabilizer and 185 mm² (Approx 20mtrs.) for neutral phase P/Fitting of-50mm PVC Copper cable(Approx. 40 mtrs) voltage stabilizer and from voltage stabilizer to FASD panel/ Starter in three leads and 35mm' PVC Coppercable(Approx. 30 mtrs) from starter to motor with proper thimbling using copper thimbles duly crimpled by using crimpling tool. Labour charges ofskilled/ unskilled and carrage charges.Testing and commissioning of HCP set after checking of alignment of pump & motor, and voltage stabilizer checking all the electrical connections, tightening of loose connections if any, plugging of leakage ofjoints by welding & tightening of nuts & bolts etc,Painting of HCP sets along with suction and delivery with recommended colors with single coat of primer & double coat of superior quality paint.Complete job includes material, labour charges, transportation/shifting charges up tO site of work, including installation testing and commissioning. |
| 22 | Design, Manufacturing, Installation, testing & commissioning of63 KVA voltage stabilizerDesign Manufacture, installation, testing and commissioning ofcopper wound manually operated oil cooled 3- phase stepup/down voltage stabilizer 63KVA conforming to relevant IS codesuitable for operation on unbalanced voltage input from 160V480V to deliver an output voltage of 415V + 5% frequency 50 Hz t3% AC supply. Material of construction shall be of followingspecifications:Core should be of first quality CRGO silicon steel core.Conductor should be 99.95% electrolyte copper.MS Sheet thickness of container: 14/16 SWGTransformer oil to be used shall be of best quality conforming toIS 335 with latest amendments.The voltage stabilizer shall be mounted on two pairs of M.SWheels of adequate strength to make shifting and fixing easyThe stabilizer shall be fitted with Voltmeter: 0-500v-02 Nos.,Ammeter- (0-100Amps)-01 No. Toggle switch 3 Nos. for input andout reading of each phase, MCCB (250 Amp), Bypass/Change OverSwitch (250 Amp)Rotary switches of suitable Amp each with eight stepsHeavy duty terminal block for input and output connections Thejob includes carriage of voltage stabilizer along with transformeroil then unloading near the approachable site and manualcarragefrom there to pumping station.(vi)Main Switch & Cables The job also includes P/F of 200 AmpereMain switch Heavy Duty confirming to ISI Standard to be mountedon the walls of the pump room with suitable angle iron frarnegrouted on wall. Providing & fitting of 200 mm²', singlecorearmored aluminum cable from pole /transformer up to mainswitch toVoltage stabilizer. Providing & fitting of PVC coppercable of suitable rating from Voltage stabilizer to bus bar torespective Panels to motors with proper thimbling and insulationmaterialandconduiting.vii)Earthing of electromechanical machinery/equipment's ofpumping station premises.(Any other accessory/job which has not been mentioned here butis mandatory and is inevitable for accomplishment of work andproper functioning of the equipment's shall also be provided andexecuted at no extra cost. Please Enable Macros to View BoQ information |