| 1 | Safe carriage of 8.5 M Long PCC | Safe carriage of 8.5 mtr. Long PCC pole from store center Etah 33/11 KV S/S to direct pit site in distance range 0 to 10 Km including loading & unloading at both ends. |
| 2 | Safe carriage of 11 M Long PCC | Safe carriage of 11 mtr. Long PCC pole from store center Etah 33/11 KV S/S to direct pit site in distance range 0 to 10 Km including loading & unloading at both ends. |
| 3 | Safe carriage of 9 M Long STP | Safe carriage of 9 mtr. long STP pole from store center Etah/nearest 33/11 KV S/S to direct pit site in distance range 0 to 10 Km. including loading & unloading at both ends. |
| 4 | Safe carriage of 11 and 13 M Long STP | Safe carriage of 11/13 mtr. long STP pole from store center Etah/nearest 33/11 KV S/S to direct pit site in distance range 0 to 10 Km. including loading & unloading at both ends. |
| 5 | Safe carriage of Line Material | Safe carriage of line material from store center Etah to pit site in distance range 0 to 10 km including loading & unloading at both ends. |
| 6 | Safe carriage of XLPE Cable | Safe carriage of XLPE Cable 3x70/3x120 sq mm from store center Etah to pit site in distance range 0 to 10 km including loading & unloading at both ends. |
| 7 | Safe carriage of 11 KV CT PT Pole Mounting | Safe carriage of 11 KV CT/PT Pole mounting unit/11 KV Metering Cubical from store center Etah to pit site in distance range 0 to 10 km including loading & unloading at both ends. |
| 8 | Safe carriage of 10 and 16 KVA TF | Safe carriage of 10/16 KVA form store center, Etah JE store to different pit site in distance range 0 to 10 Km including loading & unloading at both ends. |
| 9 | Safe carriage of 25 and 63 KVA TF | Safe carriage of 25/63 KVA form store center, Etah JE store to different pit site in distance range 0 to 10 Km including loading & unloading at both ends. |
| 10 | Safe carriage of 100 KVA TF | Safe carriage of 100 KVA form store center, Etah JE store to different pit site in distance range 0 to 10 Km including loading & unloading at both ends. |
| 11 | Etection of 8.5 M Long PCC Single Support | Erection of 8.5 mtr long PCC Pole as single support including fixing of HT/LT accessories etc complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 12 | Etection of 9 M Long STP Single Support | Erection of 9 mtr long ST Pole as single support including fixing of HT/LT accessories etc complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 13 | Etection of 11 and 13 M Long STP Single Support | Erection of 11/13 mtr long ST Pole as single support including fixing of HT/LT accessories etc complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 14 | Etection of 11 M Long PCC Single Support | Erection of 11 mtr long PCC Pole as single support including fixing of HT/LT accessories etc complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 15 | Etection of 8.5 M Long PCC Double Pole Section Pole | Erection of 8.5 mtr. long PCC poles as D/P or section pole including fixing of HT/LT accessories with TPMO etc. complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 16 | Etection of 11 M Long PCC Double Pole Section Pole | Erection of 11 mtr. long PCC poles as D/P or section pole including fixing of HT/LT accessories with TPMO etc. complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 17 | Etection of 11 and 13 M Long STP Double Pole with TPMO etc | Erection of 11/13 mtr. long ST poles as D/P including fixing of HT/LT accessories with TPMO etc. complete, pole should be gruted properly as per DVVNL/Respo norms. |
| 18 | Laying sagging of Dog Conductor | Laying sagging, stringing, binding and jumpering etc of Dog Conductor as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 19 | Laying sagging of ACSR Weasel Conductor | Laying sagging, stringing, binding and jumpering etc of ACSR weasel Conductor as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 20 | Laying sagging of LT XLPE Cable | Laying sagging, stringing, binding and jumpering etc of LT XLPE Cable 3.5x70/3.5x150 sq mm as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 21 | Laying sagging of 11 KV XLPE Cable | Laying sagging, stringing, binding and jumpering etc of 11 KV XLPE Cable size 3x70 sq mm as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 22 | Laying sagging of 11 KV XLPE Cable | Laying sagging, stringing, binding and jumpering etc of 11 KV XLPE Cable size 3x120 sq mm as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 23 | Laying sagging of AB Cable | Laying sagging, stringing, binding and jumpering etc of AB Cable of size 3X50 sq mm as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 24 | Laying sagging of AB Cable | Laying sagging, stringing, binding and jumpering etc of AB Cable of size 1x25+1x16 sq mm as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc required for proper completion of work. |
| 25 | Fixing of stay rod | Fixing of stay rod with nozzling etc complete. |
| 26 | Fixing of 3 Phase Distribution Box | Fixing of 3 Phase Distribution Box with clamp |
| 27 | Erection of 11 KV CT PT Pole Mounting Unit | Erection of 11 KV CT/PT Pole mounting unit with connection |
| 28 | Installation of 11 KV Pilfer Metering Cubical | Installation of 11 KV Pilfer Metering Cubical 5/5A |
| 29 | Providing and Fixing of Suspension Clamp | Providing and fixing of suspension clamp for PCC/ST pole |
| 30 | Providing and Fixing of Nut Bolts off size | Providing and fixing of Nut Bolts off size |
| 31 | Providing and Fixing of LT Shackle insulator | Providing and fixing of LT Shackle Insulator/LT Pin Clamp/Double Pole Clamp for PCC/ST pole |
| 32 | Providing and Fixing of Dead end clamp | Providing and fixing of Dead End Clamp/Piercing Connector for AB Cable |
| 33 | Providing and Fixing of Stone Pad | Providing and fixing of Stone Pad 300x300x75 mm |
| 34 | Providing and Fixing of Danger Board | Providing and fixing of Danger Board with Clamp |
| 35 | Providing and Fixing of Barbed wire | Providing and fixing of Barbed Wire as per norrms |
| 36 | Providing and Fixing of Number Plate | Providing and fixing of Number Plate as per norrms |
| 37 | Fixing of Joint kit outdoor | Fixing of Outdoor Jointing Kit suitable for 11 KV 3x120 sq mm XLPE Cable |
| 38 | Fixing of Joint kit indoor | Fixing of Indoor Jointing Kit suitable for 11 KV 3x120 sq mm XLPE Cable |
| 39 | Fixing of Joint kit outdoor | Fixing of Outdoor Jointing Kit suitable for 11 KV 3x70 sq mm XLPE Cable |
| 40 | Fixing of Joint kit indoor | Fixing of Indoor Jointing Kit suitable for 11 KV 3x70 sq mm XLPE Cable |
| 41 | Mounting of 10 and 16 KVA TF | Mounting of 10/16 KVA TF at double/Single pole of PCC/ST Pole supports including connections with LT line etc. complete. |
| 42 | Mounting of 25 and 63 KVA TF | Mounting of 25/63 KVA TF at double/Single pole of PCC/ST Pole supports including connections with LT line etc. complete. |
| 43 | Mounting of 100 KVA TF | Mounting of 100 KVA TF at double/Single pole of PCC/ST Pole supports including connections with LT line etc. complete. |
| 44 | Earthing of PCC Pole STP DT | Earthing of PCC Pole/STP/DT with MS earth rod as per RESPO norms/specification. |
| 45 | New guarding of HT lines with GI wire | New guarding of HT lines with GI wire as per RESPO norms/specification. |
| 46 | Carriage of ACSR Dog Weseal Conductor Scrap | Carriage of ACSR Dog/Weseal Conductor (Scrap) old material from pit site to JE store/store center Etah in distance range 0 to 10 km. including loading & unloading and proper stacking. |
| 47 | Carriage of Line Material Scrap | Carriage of Line Material (Scrap) old material from pit site to JE store/store center Etah in distance range 0 to 10 km. including loading & unloading and proper stacking. |
| 48 | Carriage of ST Pole Scrap | Carriage of ST Pole (Scrap) old material from pit site to JE store/store center Etah in distance range 0 to 10 km. including loading & unloading and proper stacking. |