| 1 | Desilting the existing drain complete direction as per the departmental officers |
| 2 | Dismantling of Plain cement concrete complete direction as per the departmental officers |
| 3 | Dismantling of reinforced cement concrete complete direction as per the departmental officers |
| 4 | Earthwork excavation for foundation in Hard stiff clay,stiff black cotton, hardred earth,shalesmurram,gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand,silt or other loose soil,wet sand,or silt not underwater, light black cotton soil,sandy loam ordinary soil and to full depth as may be directed except in hard rock requiring blasting inclusiveof shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum |
| 5 | Conveyance the excess earth or earth not suitable for refilling, dumping and spreading, levelling of the same at places of dump approved by departmental officers and as directed including lorry hire charges, labour for loading, unloading, spreading, leveling, making approaches for areas of dumps etc., complete. |
| 6 | Flooring with bed of cement concrete 1:4:8 (One part of cement, four parts of sand and eight parts of stone jelly by volume) using 40 mm thick granite hard broken stones, all machine mixed, laid to uniform thickness of 100mm and top left rought to receive floor finish including all labour charges for concreting, ramming, curing etc, and providing expansion joints, slopes & grades if any etc., complete complying with relevant standard specifications at all leads & lifts inside the building. |
| 7 | Supplying and erecting centering for sides and soffits including supports and strutting for plain surfaces such as Plain cement concrete walls etc., with all cross bracing etc., including decentering after curing period,complete complying with standard specifications, at all leads inside the building, at all heights. |
| 8 | Drain walls with of cement concrete 1:3:6 (One part of cement, three parts of sand and six parts of stone jelly by volume) using 20 mm thick granite hard broken stones, all machine mixed, laid to the specified thickness including all labour charges for concreting, ramming, curing etc, complete complying with relevant standard specifications |
| 9 | Flooring with bed of cement concrete 1:2:4 (One part of cement, two parts of sand and four parts of stone jelly by volume) using 20 mm thick granite hard broken stones, all machine mixed, laid to uniform thickness of 100mm and top left rought to receive floor finish including all labour charges for concreting, ramming, curing etc, and providing expansion joints, slopes & grades if any etc., complete complying with relevant standard specifications at all leads & lifts inside the building. |
| 10 | Plastering with C.M.1:5 mix with 12mm thick etc., complete as per the direction of departmental officers. |
| 11 | Supplying and erecting Centering for sides and soffits including supports and strutting upto 3.29m high for plane surfaces such as RCC Slabs, Rectangular beams, TEE or ELL beams, Lintels, Bed blocks, Staircase waist, Landing slab, Landing beam and Canopy etc., in all floors to centre etc., complete and as directed. |
| 12 | Reinforced Cement concrete 1:1.5:3 (one cement, one and a half sand and three aggregate) using 20mm hard broken granite stone jelly for all RCC items of work excluding centering, shuttering and cost of reinforcement grill but including curing finishing, vibrator charges etc., complete and also including fixing fan clamps and fixtures in RCC works wherever necessary as directed by departmental officer etc., complete |
| 13 | Supplying, fabricating and placing in position RTS rods for all RCC works including cost of steel and binding wire also in all floors complete complying with standard specification |
| 14 | Supply & Fixing of 600mm dia SFRC man hole cover of heavy duty with frame as per the standard specification and instruction of departmental officers |
| 15 | Providing and fixing Bitumen Pad for Expansion joint in between pavement slabs to 12mm thick and fixed as shown in the drawing including cost and conveyence of expansion joints including shalimarpad and joint sealent etc,complete as per standard specification |
| 16 | Supply of PVC pipes and specials |
| 17 | 110 mm pvc pipe |
| 18 | 110 mm pvc coupling |
| 19 | 110 mm pvc elbow |
| 20 | 90 mm pvc pipe |
| 21 | 90 mm pvc coupling |
| 22 | 90 mm pvc elbow |
| 23 | Add :- GST @ 18% Please Enable Macros to View BoQ information |