Name of Work:- Extension Work of existing 400kV GIS Bay for installation of 3rd ICT (500MVA, 400/220kV) at BTPS
Sl. No.
Item Description
1
Item Rate BoQ BoQ_Ver3.0 Item Rate Normal INR Only INR Select, Excess (+), Less (-) Less (-) Tender Inviting Authority: Sr. GM, C&M Dept., DVC Name of Work: Extension Work of existing 400kV GIS Bay for installation of 3rd ICT (500MVA, 400/220kV) at BTPS NIT No: DVC/Tender/Head Quarter/SPE/CMM/Works and Service/SAP/ 2600001652 Name of the Bidder/ Bidding Firm / Company : PRICE SCHEDULE(This BOQ template must not be modified/replaced by the bidder and the same should be uploaded after filling the relevent columns, else the bidder is liable to be rejected for this tender. Bidders are allowed to enter the Bidder Name and Values only ) NUMBER # TEXT # TEXT # NUMBER # TEXT # NUMBER NUMBER TEXT TEXT # NUMBER # TEXT# TEXT # NUMBER # NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER NUMBER TEXT TEXT NUMBER NUMBER NUMBER # NUMBER # TEXT TEXT NUMBER # NUMBER # DATE NUMBER # NUMBER # TEXT # Sl.No. Item/Work Description Item Code / Make Quantity Units Estimated RateinRs. P Addition / Deduction Addition / Deduction Values Currency Convertion against each Item Quoted Currency in INR / Other Currency BASIC RATE In Figures To be entered by the Bidder inRs. P GST in % VAT Freight Charges ( Unloading & Stacking) Any Other Taxes/Duties/Levies Other Taxes 2 IIIrd Party i.e DGS&D / RITES etc Inspection Charges @0.34%+Service Tax Less for Cenvat Credit,if any respect of Supplies Under full Excise Duty Category TOTAL AMOUNT Without TaxesinRs. P TOTAL AMOUNT Without TaxesinRs. P TOTAL AMOUNT Without TaxesIn Words
2
BTPS 400kV GIS Extn Work (ICT#3)
3
Supply_Substation
4
Erection other than Civil_Substation Total in Figures 0.0 0.0 Zero Only 4.0 Construction of chamber for 100mm sluice plates item5 10.0 Nos Quoted Rate in Figures Select 0.0 0.0 Zero Only Quoted Rate in Words INR Zero Only Note:1. Supply part includes entire supply of all the materials & spares, related to the project, as per the Scope of Work, Technical Specification & BOQ 2. Supply Part Includes F&I upto site, loading, unloading, storing, with all insurnaces for all items under Supply-Schedule3. Erection part includes entire erection work as per the Scope of Work, Technical Specification & BOQ4. Bidder have to quote for all of the above line items under BOQ SHEET#1 & the summation of the rates of all the line items will be considered for evaluation of the L1 bidder. 6. All the quoted rates should be exclusive of the GST. However, GST percentage will be quoted seperately under the designated colume of the BOQ SHEET#1. Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.