| Sl. No. | Item Description |
| 1 | PART-A: Construction of 33KV line DP for road crossing 2nos. (Ref.: - SLD-12 at Karadibandha W.T.P Road). (To be executed by party and maintained by TPCODL under 6% supervision charges) 33 KV DP Without IsolatorWPB (GI) Pole 160x152 (13Mtr. Long, 30.44KG/Mtr.)-DP (Total Pole Weight with Base Plate & Stiffner=395.72 KG+10.74 KG= 406.46 KG) |
| 2 | Top Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 3.25 mtr., 2 no's Channel(GI) required =( 2x9.56x3.25) |
| 3 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 4 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 1.96 Mtr., 5 no's Channel(GI) required =( 5x7.14x1.96) |
| 5 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.432 mtr., 4 nos Angle(GI) required = (4*4.5*3.432) |
| 6 | Danger Plate, 2 no's. |
| 7 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 8 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 9 | H.T. Stay set (Complete ) |
| 10 | H.T. Stay Insulator Type-C (2 No's.) |
| 11 | 7/8 SWG Stay Wire 15kg /stay |
| 12 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 13 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 5x2.36 |
| 14 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 15 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 16 | 33KV pin insulator polymer |
| 17 | H W fitting(B&S) 90KN,4 Bolt |
| 18 | Disc insulator (B&S) 90 KN polymer |
| 19 | Wedge connector for 100 sq.mm AAA conductor |
| 20 | GI Nut , Bolt & Washer of different sizes (12.261 Kg each DP without Isolator) |
| 21 | POLYCARBONATE BIRD GUARD |
| 22 | Black Paint(GIS Numbering & Zebra Stripping) |
| 23 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 24 | Fixing of complete 33KV line Complete stay set includes1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard.Note:- Excavation of earth will be done of size 500X500X1500 mm. |
| 25 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2200mm) = 0.55Cu.mtr(Per Pole) |
| 26 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 27 | Provide necessary civil material for construction of Earthing chamber, excavation & installation of incuding earthingpipe dia up to 100mm dia for length of 3Mtr.Scope also includes necessary nutbolt, 25 Kg Bentonide Power , connection & welding with incoming earth Flat(GI). The work to be executed as per TPCODL drawing & design |
| 28 | PART-B: Guarding for road crossing 1no. (Ref.: - SLD-12 at Karadibandha W.T.P Road) for 33kV Line. (To be executed by party and maintained by TPCODL under 6% supervision charges)Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 4 mtr., 4 no's Channel(GI) required =( 4x7.14x4) ( For Single Pole) |
| 29 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 30 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 31 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 32 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 33 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (12.7 mtr For raising)= 12.7x2.36 |
| 34 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 35 | PART-C: Shifting of approximately 0.580Ckm of existing OH 11kV line, followed by construction of approximately 0.615Ckm. of new 11KV line with 55 SQ.MM. AAAC (Ref.: - SLD-2 at Padmanavapur Mangala Mandira 63KVA S/s to Khariamada Medical, SLD-8 at New Kesabareni 63KVA, SLD-12 at Karadibandha W.T.P Road & SLD-13 at Karadibandha Bridge to Ogalapur village water tank). (To be executed by party and maintained by TPCODL under 6% supervision charges) DP With AB SwitchWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 36 | Top Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 3 mtr., 2 no's Channel(GI) required =( 2x9.56x3) |
| 37 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 38 | AB switch Mounting Channel(GI) 75X40X4.8mm, 7.14KG/Mtr, each Channel(GI) length 3 Mtr., 2 no's Channel(GI) required =( 7.14x3x2) |
| 39 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 40 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 41 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 3.0 Mtr., 4 no's Channel(GI) required =( 7.14x3x4) |
| 42 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.512 mtr., 4 nos Angle(GI) required = (4.5x3.512x4) |
| 43 | Danger Plate, 2 no's. |
| 44 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 45 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 46 | H.T. Stay set (Complete ) |
| 47 | H.T. Stay Insulator Type-C |
| 48 | 7/10 SWG Stay Wire 15kg /stay |
| 49 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 50 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (12.5 Mtr. For L.A, 3 Mtr for AB Switch Body, 2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 20.5x2.36 |
| 51 | GI barbed wire anticlimbing device 3 Kg. Per support, 2 no's qty. required =(2x3kg) |
| 52 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 53 | Lightning Arrester(12KV,10KA) (Station Class,class-2) |
| 54 | AB Switch (11KV,400A.3pole,50Hz) |
| 55 | 11 KV pin insulator polymer |
| 56 | H W fitting(B&S) 70KN, 3Bolt |
| 57 | Disc insulator (B&S) 70 KN polymer |
| 58 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 59 | POLYCARBONATE BIRD GUARD |
| 60 | GI Nut , Bolt & Washer of different sizes (13.718 Kg each DP with AB Switch) |
| 61 | Black Paint(GIS Numbering & Zebra Stripping) |
| 62 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 63 | Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 64 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 65 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 66 | Provide necessary civil material for construction of Earthing chamber, excavation & installation of incuding earthingpipe dia up to 100mm dia for length of 3Mtr.Scope also includes necessary nutbolt, 25 Kg Bentonide Power , connection & welding with incoming earth Flat(GI). The work to be executed as per TPCODL drawing & design |
| 67 | 11 KV Cut Point with 180 Degree AngleWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 68 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 2 no's Channel(GI) required =( 2x9.56x1.2) |
| 69 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 8 no's required = (8x2.36x0.280) |
| 70 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 2 no's Channel(GI) required =(2x9.56x0.306) |
| 71 | Danger Plate, 1 no's. |
| 72 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 73 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 74 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 75 | 11 KV pin insulator polymer |
| 76 | H W fitting(B&S) 70KN, 3Bolt |
| 77 | Disc insulator (B&S) 70 KN polymer |
| 78 | Earthing of Support ( Coil Type ) |
| 79 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 80 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 81 | POLYCARBONATE BIRD GUARD |
| 82 | GI Nut , Bolt & Washer of different sizes (3.55 Kg each Cut Pole) |
| 83 | Black Paint(GIS Numbering & Zebra Stripping) |
| 84 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 85 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 86 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 87 | 11 KV Cut Point with 90 Degree AngleWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 88 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 4 no's Channel(GI) required =( 4x9.56x1.2) |
| 89 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 90 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 4 no's Channel(GI) required =( 4x9.56x0.306) |
| 91 | Danger Plate, 1 no's. |
| 92 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 93 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 94 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 95 | 11 KV pin insulator polymer |
| 96 | H W fitting(B&S) 70KN, 3Bolt |
| 97 | Disc insulator (B&S) 70 KN polymer |
| 98 | Earthing of Support ( Coil Type ) |
| 99 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 100 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 101 | POLYCARBONATE BIRD GUARD |
| 102 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 103 | H.T. Stay set (Complete ) |
| 104 | H.T. Stay Insulator Type-C |
| 105 | 7/10 SWG Stay Wire 15kg /stay |
| 106 | GI Nut , Bolt & Washer of different sizes (7.433 Kg each Cut Pole) |
| 107 | Black Paint(GIS Numbering & Zebra Stripping) |
| 108 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 109 | Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 110 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 111 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 112 | 11 KV Pin Points With WPBWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 113 | 11 KV V cross Arm(GI) (10.2 K.g. each ) |
| 114 | Top bracket 100x50X6 mm GI Channel(GI) (2kg each) |
| 115 | Danger Plate, 1 no's. for each pole |
| 116 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 117 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 118 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 119 | 11 KV pin insulator polymer, 3 Nos. required for each support |
| 120 | Earthing of Support ( Coil Type ) |
| 121 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 122 | GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point) |
| 123 | 55 sq.mm AAA conductor |
| 124 | Black Paint(GIS Numbering & Zebra Stripping) |
| 125 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 126 | POLYCARBONATE BIRD GUARD |
| 127 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 128 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 129 | PART D: Supply & Installation of 0.04 CKM 11 kV 3CX400 Sq.mm. XLPE U/G cable with one run spare in open trench method (Refer SLD 12)(To be executed by party and maintained by TPCODL under 6% supervision charges) Supply of materials for 11kV, 3Core, 400sqmm Aluminium, XLPE insulation UG Cable with accessoriesSupply of 11kV, 3Core, 400sqmm, XLPE insulation armoured UG cable (SC rating of cable in kA- 37.7kA and SC rating of Armour in kA- 15kA) |
| 130 | Supply of Outdoor termination kits Heat Shrinkable type suitable for 11kV, 3Core, 400sqmm, HT UG Cable kits |
| 131 | Supply of materials for High Density Polyethelene (HDPE) pipe 200mm diameter, PE 80- PN8 for laying of 11kV UG cable |
| 132 | Erection, Commissioning & Testing of 11kV new line by 3Core, 400sqmm, XLPE UG cable Laying, Commissioning & Testing of 11kV, 3Core, 400sqmm, XLPE insulation (extruted type) UG cable by open trench method. |
| 133 | Erection of Straight through jointing Kits/Outdoor termination kits/Indoor termination Kits Heat Shrinkable type suitable for 11kV, 3Core, 400sqmm, aluminium UG cable kits |
| 134 | Laying of 200mm dia PE 80-PN8, HDPE pipe inside open trench. |
| 135 | Civil works with supply of all materials like cement, MS tor rod, brick, coarse & fine aggregates and labour, T&P, etc for UG Cable TrenchEarth work excavation of soil (1mtr. width X 1mtr. depth)-Route LengthEarth work excavation of soil |
| 136 | Earth work excavation of hard rock |
| 137 | Back filling with excavated soil outside and above the trench |
| 138 | Supply and Erection of Cable Route Marker along the cable route at an interval of 30mtrs with civil works |
| 139 | PART E: Construction of 9 Nos 11 kV Guarding having span 25 Mtr. each (Refer PSLD) (To be executed by party and maintained by TPCODL under 6% supervision charges) Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 2.2 mtr., 4 no's Channel(GI) required =( 4x7.14x2.2) ( For Single Pole) |
| 140 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 141 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 142 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 143 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 144 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 145 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 146 | PART F: Construction of 02 Nos 11 kV Guarding having span 25 Mtr. & 50 Mtr. (Refer PSLD-3) (To be executed by party and maintained by TPCODL under 6% supervision charges) Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 3.5 mtr., 4 no's Channel(GI) required =( 4x7.14x3.5) ( For Double Pole) |
| 147 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 148 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 149 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 150 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 151 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 152 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 153 | PART-G : Shifting of approximately 0.250Ckm of existing OH 11kV line, followed by construction of approximately 0.270Ckm. of new 11KV line with 100 SQ.MM. AAAC (Ref.: - SLD-15 at 500KVA S/s DP Sasanga to Bhattarika 100KVA S/s DP). (To be executed by party and maintained by TPCODL under 6% supervision charges) 11 KV Cut Point with 180 Degree AngleWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 154 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 2 no's Channel(GI) required =( 2x9.56x1.2) |
| 155 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 8 no's required = (8x2.36x0.280) |
| 156 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 2 no's Channel(GI) required =(2x9.56x0.306) |
| 157 | Danger Plate, 1 no's. |
| 158 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 159 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 160 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 161 | 11 KV pin insulator polymer |
| 162 | H W fitting(B&S) 70KN, 3Bolt |
| 163 | Disc insulator (B&S) 70 KN polymer |
| 164 | Earthing of Support ( Coil Type ) |
| 165 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 166 | WEDGE CONNECTOR FOR 100 SQMM.CONDUCTOR |
| 167 | POLYCARBONATE BIRD GUARD |
| 168 | GI Nut , Bolt & Washer of different sizes (3.55 Kg each Cut Pole) |
| 169 | Black Paint(GIS Numbering & Zebra Stripping) |
| 170 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 171 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 172 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 173 | 11 KV Cut Point with 90 Degree AngleWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 174 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 4 no's Channel(GI) required =( 4x9.56x1.2) |
| 175 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 176 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 4 no's Channel(GI) required =( 4x9.56x0.306) |
| 177 | Danger Plate, 1 no's. |
| 178 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 179 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 180 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 181 | 11 KV pin insulator polymer |
| 182 | H W fitting(B&S) 70KN, 3Bolt |
| 183 | Disc insulator (B&S) 70 KN polymer |
| 184 | Earthing of Support ( Coil Type ) |
| 185 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 186 | WEDGE CONNECTOR FOR 100 SQMM.CONDUCTOR |
| 187 | POLYCARBONATE BIRD GUARD |
| 188 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 189 | H.T. Stay set (Complete ) |
| 190 | H.T. Stay Insulator Type-C |
| 191 | 7/10 SWG Stay Wire 15kg /stay |
| 192 | GI Nut , Bolt & Washer of different sizes (7.433 Kg each Cut Pole) |
| 193 | Black Paint(GIS Numbering & Zebra Stripping) |
| 194 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 195 | Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 196 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 197 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 198 | 11 KV Pin Points With WPBWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 199 | 11 KV V cross Arm(GI) (10.2 K.g. each ) |
| 200 | Top bracket 100x50X6 mm GI Channel(GI) (2kg each) |
| 201 | Danger Plate, 1 no's. for each pole |
| 202 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 203 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 204 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 205 | 11 KV pin insulator polymer, 3 Nos. required for each support |
| 206 | Earthing of Support ( Coil Type ) |
| 207 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 208 | GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point) |
| 209 | 100 sq.mm AAA conductor |
| 210 | Black Paint(GIS Numbering & Zebra Stripping) |
| 211 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 212 | POLYCARBONATE BIRD GUARD |
| 213 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 214 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 215 | PART- H: Construction of Cutpoint with H-Pole 1no (Ref.: - SLD-15 at 500KVA S/s DP Sasanga to Bhattarika 100KVA S/s DP). (To be executed by party and maintained by TPCODL under 6% supervision charges) 11 KV Cut Point with 90 Degree Angle11 Mtr. Long H-Pole(GI) (Total weight with Base Plate & Stiffner- 638.696 KG) |
| 216 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 4 no's Channel(GI) required =( 4x9.56x1.2) |
| 217 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 218 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 4 no's Channel(GI) required =( 4x9.56x0.306) |
| 219 | Danger Plate, 1 no's. |
| 220 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 221 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 222 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 223 | 11 KV pin insulator polymer |
| 224 | H W fitting(B&S) 70KN, 3Bolt |
| 225 | Disc insulator (B&S) 70 KN polymer |
| 226 | Earthing of Support ( Coil Type ) |
| 227 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 228 | WEDGE CONNECTOR FOR 100 SQMM.CONDUCTOR |
| 229 | POLYCARBONATE BIRD GUARD |
| 230 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 231 | H.T. Stay set (Complete ) |
| 232 | H.T. Stay Insulator Type-C |
| 233 | 7/10 SWG Stay Wire 15kg /stay |
| 234 | GI Nut , Bolt & Washer of different sizes (7.433 Kg each Cut Pole) |
| 235 | Black Paint(GIS Numbering & Zebra Stripping) |
| 236 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 237 | Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 238 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 239 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 240 | PART I: Construction of 15 Nos LT Guarding having span 25 Mtr. each (Refer PSLD) (To be executed by party and maintained by TPCODL under 6% supervision charges) Guarding Channel(GI) 75x40x4.8 mm, 7.14 KG/Mtr., each Channel(GI) length 2.2 mtr., 4 no's Channel(GI) required =( 4x7.14x2.2) ( For Single Pole) |
| 241 | No-6 GI wire (0.192 kg/mtr.) for Main String |
| 242 | No-8 GI wire (0.131 kg/mtr.) for lacing |
| 243 | Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.) |
| 244 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 245 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (10.7 mtr For raising)= 10.7x2.36 |
| 246 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 247 | PART-J: - Shifting of approximately 0.260Ckm of existing OH 11kV line, followed by construction of approximately 0.270Ckm. of new 11KV line with 80 SQ.MM. Grade insulated conductor (Ref.: - SLD-5 at Khariamada village to Banamalipur Bazar end). (To be executed by party and maintained by TPCODL under 6% supervision charges) WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.) 1no for Stud Stay (Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 248 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 4 no's Channel(GI) required =( 4x9.56x1.2) |
| 249 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280) |
| 250 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 4 no's Channel(GI) required =( 4x9.56x0.306) |
| 251 | Danger Plate, 1 no's. |
| 252 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 253 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 254 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 255 | 11 KV pin insulator polymer |
| 256 | H W fitting(B&S) 70KN, 3Bolt |
| 257 | Disc insulator (B&S) 70 KN polymer |
| 258 | Earthing of Support ( Coil Type ) |
| 259 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 260 | NON METALLIC TIES -11KV 80SQMM CVRD AAAC |
| 261 | IPC for 80 sq.mm AAA conductor (For covered conductor)-11kV |
| 262 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 263 | H.T. Stay set (Complete ) |
| 264 | H.T. Stay Insulator Type-C |
| 265 | 7/10 SWG Stay Wire 15kg /stay |
| 266 | GI Nut , Bolt & Washer of different sizes (7.433 Kg each Cut Pole) |
| 267 | Black Paint(GIS Numbering & Zebra Stripping) |
| 268 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 269 | Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 270 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 271 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 272 | 11 KV Pin Points With WPBWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 273 | 11 KV V cross Arm(GI) (10.2 K.g. each ) |
| 274 | Top bracket 100x50X6 mm GI Channel(GI) (2kg each) |
| 275 | Danger Plate, 1 no's. for each pole |
| 276 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 277 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 278 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 279 | 11 KV pin insulator polymer, 3 Nos. required for each support |
| 280 | Earthing of Support ( Coil Type ) |
| 281 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 282 | GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point) |
| 283 | 80 sq.mm XLPE AAA conductor |
| 284 | Black Paint(GIS Numbering & Zebra Stripping) |
| 285 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 286 | NON METALLIC TIES -11KV 80SQMM CVRD AAAC |
| 287 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 288 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 289 | PART-K: - Installation of 11KV Line DP without AB switch 2nos & 01 No 11 kV Pin point using 13 Mtr. WPB Pole (Ref.: - SLD-3 at Khariamada medical front). (To be executed by party and maintained by TPCODL under 6% supervision charges) DP Without AB SwitchWPB (GI) Pole 160x152 (13Mtr. Long, 30.44KG/Mtr.)-DP (Total Pole Weight with Base Plate & Stiffner=395.72 KG+10.74 KG= 406.46 KG) |
| 290 | Top Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 2.3 mtr., 2 no's Channel(GI) required =( 2x9.56x2.3) |
| 291 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 292 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 1.66 Mtr., 4 no's Channel(GI) required =( 7.14x1.66x4) |
| 293 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 2.671 mtr., 4 nos Angle(GI) required = (4.5x2.671x4) |
| 294 | Danger Plate, 2 no's. |
| 295 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 296 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 297 | H.T. Stay set (Complete ) |
| 298 | H.T. Stay Insulator Type-C |
| 299 | 7/10 SWG Stay Wire 15kg /stay |
| 300 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 301 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 5x2.36 |
| 302 | GI barbed wire anticlimbing device 3 Kg. Per support, 2 no's qty. required =(2x3kg) |
| 303 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 304 | 11 KV pin insulator polymer |
| 305 | H W fitting(B&S) 70KN, 3Bolt |
| 306 | Disc insulator (B&S) 70 KN polymer |
| 307 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 308 | POLYCARBONATE BIRD GUARD |
| 309 | GI Nut , Bolt & Washer of different sizes (12.261 Kg each DP without AB Switch) |
| 310 | Black Paint(GIS Numbering & Zebra Stripping) |
| 311 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 312 | Fixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 313 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2200mm) = 0.55Cu.mtr(Per Pole) |
| 314 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 315 | Provide necessary civil material for construction of Earthing chamber, excavation & installation of incuding earthingpipe dia up to 100mm dia for length of 3Mtr.Scope also includes necessary nutbolt, 25 Kg Bentonide Power , connection & welding with incoming earth Flat(GI). The work to be executed as per TPCODL drawing & design |
| 316 | 11 KV Pin Points With WPBWPB (GI) Pole 160x152 (13Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=395.72 KG+10.74 KG= 406.46 KG) |
| 317 | 11 KV V cross Arm(GI) (10.2 K.g. each ) |
| 318 | Top bracket 100x50X6 mm GI Channel(GI) (2kg each) |
| 319 | Danger Plate, 1 no's. for each pole |
| 320 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 321 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 322 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 323 | 11 KV pin insulator polymer, 3 Nos. required for each support |
| 324 | Earthing of Support ( Coil Type ) |
| 325 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 326 | GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point) |
| 327 | Black Paint(GIS Numbering & Zebra Stripping) |
| 328 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 329 | POLYCARBONATE BIRD GUARD |
| 330 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX2200mm) = 0.55Cu.mtr(Per Pole) |
| 331 | Couping ratio 1:1.5:3(M-20 Grade) with dimension (500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 332 | Part-L : Installation of 01 No of existing 11/0.433 KV, 100 KVA DTR on Proposed DP (Refer PSLD) (Cost of DTR not considered, existing DTR will be used) (Refer PSLD)(To be executed by Party and maintained by TPCODL under 6% deposit work scheme)WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 333 | 9 Mtr. long 300 Kg. PSC Pole |
| 334 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 335 | EYE hook for XLPE Aerial bunched Cable |
| 336 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 337 | LT Cable raising Channel(GI) 75x40x4.8 mm GI Channel(GI) (1000 mm long)(7.14Kg./Mtr., 3 No's.) (Each 3x1.000x7.14= 21.42 Kg) |
| 338 | Top Channel(GI) GI 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 339 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 340 | AB Switch Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 341 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 342 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 343 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 344 | Cantilever Support Channel(GI) 75x40x4.8 mm GI Channel(GI) (810 mm long,2 No's.) (7.14Kg./Mtr., 2 No's.) (Each 2x0.810x7.14= 11.57 Kg) |
| 345 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 346 | Transformer Base GI Channel(GI) 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 347 | Transformer Base Support GI Channel(GI) 100 X 50 X 6 MM (515 mm long) (9.56Kg./Mtr, 2 No's) (Each 2x0.515x9.56= 9.85Kg) |
| 348 | Transformer Belting Angle(GI) 50 X 50 X 6MM GI (3000 mm long)(4.5Kg./Mtr, 2 No's) (Each 2x3.0x4.5 Kg) |
| 349 | Transformer Belting Support Angle(GI) 50 X 50 X 6MM GI (580 mm long)(4.5Kg./Mtr,2 No's) (Each 2x0.580x4.5= Kg) |
| 350 | LTDB Mounting Angle(GI) 50 X 50 X 6MM GI (1000 mm long)(4.5Kg./Mtr, 2 No's) (Each 2x1x4.5 Kg) |
| 351 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle, 3 mtr. for Fencing) ( Each 65.6x 2.36= 154.81 Kg) |
| 352 | LT Distribution Box with MCCB, Aluminium Busbar of 2 Bay with kit kat fuse for 100 KVA S/S |
| 353 | 55 SQ.MM. AAAC XLPE Covered Conductor |
| 354 | 4 Cx 150 mm2 LT XLPE Cable(Armoured) - FOR 100 KVA Trf. |
| 355 | 1.1kV, 4Core, 150 sqmm, XLPE insulation armoured -Aluminium UG cable from LTDB to Pole |
| 356 | AB Switch(11KV,200A.3pole,50Hz) |
| 357 | DO.Fuse( 11KV.200A.3Pole) |
| 358 | 10 AMP Fuse Link |
| 359 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 360 | POLYCARBONATE BIRD GUARD |
| 361 | Disc insulator (B&S)70 KN polymer |
| 362 | H W fitting (B&S)70KN(3bolted) |
| 363 | Lightning Arrester(12KV,10KA) Station Class 2 |
| 364 | 11KV pin insulator polymer |
| 365 | HT stay set complete |
| 366 | HT stay Clamp (1.9Kg/pair) |
| 367 | HT stay insulator TYPE-C |
| 368 | 7/10 SWG GI stay wire, Grade -2 (15Kg./ Set) |
| 369 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 370 | GI Nuts & Bolts of Assorted size (25 Kg/ DSS DP) |
| 371 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 372 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 373 | Danger plate 11kv |
| 374 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 375 | Name plate |
| 376 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 377 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 378 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) (For WPB Pole) |
| 379 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 380 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (5X3X0.1)= 1.5 Cu. mtr. |
| 381 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 382 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 383 | Laying of 4 Cx 150 mm2 LT XLPE Cable |
| 384 | SITC and Erection of GI Fencing with Gate |
| 385 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) (For PSC Pole) |
| 386 | Supply of AL Lugs suitable for 150 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 387 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 3.5/4C 120-185sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 388 | PART-M: - Construction of 63 KVA 11/0.4KV DP mounted S/s (without transformer) - 1no (Ref.: - SLD-8 at New Kesabareni 63KVA) (To be executed by party and maintained by TPCODL under 6% supervision charges) WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 389 | 9 Mtr. long 300 Kg. PSC Pole |
| 390 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 391 | EYE hook for XLPE Aerial bunched Cable |
| 392 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 393 | LT Cable raising Channel(GI) 75x40x4.8 mm GI Channel(GI) (1000 mm long)(7.14Kg./Mtr., 3 No's.) (Each 3x1.000x7.14= 21.42 Kg) |
| 394 | Top Channel(GI) GI 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 395 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 396 | AB Switch Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 397 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 398 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 399 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 400 | Cantilever Support Channel(GI) 75x40x4.8 mm GI Channel(GI) (810 mm long,2 No's.) (7.14Kg./Mtr., 2 No's.) (Each 2x0.810x7.14= 11.57 Kg) |
| 401 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 402 | Transformer Base GI Channel(GI) 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 403 | Transformer Base Support GI Channel(GI) 100 X 50 X 6 MM (515 mm long) (9.56Kg./Mtr, 2 No's) (Each 2x0.515x9.56= 9.85Kg) |
| 404 | Transformer Belting Angle(GI) 50 X 50 X 6MM GI (3000 mm long)(4.5Kg./Mtr, 2 No's) (Each 2x3.0x4.5 Kg) |
| 405 | Transformer Belting Support Angle(GI) 50 X 50 X 6MM GI (580 mm long)(4.5Kg./Mtr,2 No's) (Each 2x0.580x4.5= Kg) |
| 406 | LTDB Mounting Angle(GI) 50 X 50 X 6MM GI (1000 mm long)(4.5Kg./Mtr, 2 No's) (Each 2x1x4.5 Kg) |
| 407 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle, 3 mtr. for Fencing) ( Each 65.6x 2.36= 154.81 Kg) |
| 408 | LT Distribution Box with MCCB, Aluminium Busbar of single Bay with kit kat fuse for 63 KVA S/S |
| 409 | 55 SQ.MM. AAAC XLPE Covered Conductor |
| 410 | 4 Cx 95 mm2 LT XLPE Cable(Armoured) - FOR 63 KVA Trf. |
| 411 | 4 Cx 95 mm2 LT XLPE Cable(Armoured) - From LTDB to Pole |
| 412 | AB Switch(11KV,200A.3pole,50Hz) |
| 413 | DO.Fuse( 11KV.200A.3Pole) |
| 414 | 5 AMP Fuse Link |
| 415 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 416 | POLYCARBONATE BIRD GUARD |
| 417 | Disc insulator (B&S)70 KN polymer |
| 418 | H W fitting (B&S)70KN(3bolted) |
| 419 | Lightning Arrester(12KV,10KA) Station Class 2 |
| 420 | 11KV pin insulator polymer |
| 421 | HT stay set complete |
| 422 | HT stay Clamp (1.9Kg/pair) |
| 423 | HT stay insulator TYPE-C |
| 424 | 7/10 SWG GI stay wire, Grade -2 (15Kg./ Set) |
| 425 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 426 | GI Nuts & Bolts of Assorted size (25 Kg/ DSS DP) |
| 427 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 428 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 429 | Danger plate 11kv |
| 430 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 431 | Name plate |
| 432 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 433 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 434 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) (For WPB Pole) |
| 435 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 436 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (5X3X0.1)= 1.5 Cu. mtr. |
| 437 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 438 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 439 | Laying of 4 Cx 95 mm2 LT XLPE Cable |
| 440 | SITC and Erection of GI Fencing with Gate |
| 441 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) (For PSC Pole) |
| 442 | Supply of AL Lugs suitable for 95 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 443 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 3.5/4C 50-95sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 444 | PART-N: - Construction of 63 KVA 11/0.4KV Plinth mounted S/s (without transformer) - 2nos (Ref.: - SLD-6 at Khairamada Medical front 63KVA S/s and Banamalipur 1X100+1X63KVA S/s DP) (To be executed by party and maintained by TPCODL under 6% supervision charges) WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 445 | 9 Mtr. long 300 Kg. PSC Pole |
| 446 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 447 | EYE hook for XLPE Aerial bunched Cable |
| 448 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 449 | LT Cable raising Channel(GI) 75x40x4.8 mm GI Channel(GI) (1000 mm long)(7.14Kg./Mtr., 3 No's.) (Each 3x1.000x7.14= 21.42 Kg) |
| 450 | Top Channel(GI) GI 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 451 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 452 | AB Switch Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 453 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 454 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 455 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 456 | Cantilever Support Channel(GI) 75x40x4.8 mm GI Channel(GI) (810 mm long,2 No's.) (7.14Kg./Mtr., 2 No's.) (Each 2x0.810x7.14= 11.57 Kg) |
| 457 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 458 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 3.0 Mtr., 2 no's Channel(GI) required =( 7.14x3x2) |
| 459 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.512 mtr., 2 nos Angle(GI) required = (4.5x3.512x2) |
| 460 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle, 3 mtr. for Fencing) ( Each 65.6x 2.36= 154.81 Kg) |
| 461 | LT Distribution Box with MCCB, Aluminium Busbar of single Bay with kit kat fuse for 63 KVA S/S |
| 462 | 55 SQ.MM. AAAC XLPE Covered Conductor |
| 463 | 4 Cx 95 mm2 LT XLPE Cable(Armoured) - FOR 63 KVA Trf. |
| 464 | 4 Cx 95 mm2 LT XLPE Cable(Armoured) - From LTDB to Pole |
| 465 | AB Switch(11KV,200A.3pole,50Hz) |
| 466 | DO.Fuse( 11KV.200A.3Pole) |
| 467 | 5 AMP Fuse Link |
| 468 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 469 | POLYCARBONATE BIRD GUARD |
| 470 | Disc insulator (B&S)70 KN polymer |
| 471 | H W fitting (B&S)70KN(3bolted) |
| 472 | Lightning Arrester(12KV,10KA) Station Class 2 |
| 473 | 11KV pin insulator polymer |
| 474 | HT stay set complete |
| 475 | HT stay Clamp (1.9Kg/pair) |
| 476 | HT stay insulator TYPE-C |
| 477 | 7/10 SWG GI stay wire, Grade -2 (15Kg./ Set) |
| 478 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 479 | GI Nuts & Bolts of Assorted size (25 Kg/ DSS DP) |
| 480 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 481 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 482 | Danger plate 11kv |
| 483 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 484 | Name plate |
| 485 | Structure Numbering and MarkingYellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 486 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 487 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) (For WPB Pole) |
| 488 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 489 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (3.5X1.5X0.1)= 0.525 Cu. mtr. |
| 490 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 491 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 492 | DTR Plinth |
| 493 | Laying of 4 Cx 95 mm2 LT XLPE Cable |
| 494 | SITC and Erection of GI Fencing with Gate |
| 495 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) (For PSC Pole) |
| 496 | Supply of AL Lugs suitable for 95 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 497 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 3.5/4C 50-95sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 498 | Part-O: Installation of 02 Nos of existing 11/0.23 KV 16 KVA DTR on Proposed Single Pole (Refer PSLD) (Cost of DTR not considered, existing DTR will be used) (Refer PSLD)(To be executed by Party and maintained by TPCODL under 6% deposit work scheme)WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 499 | Top Channel(GI) GI 100 X 50 X 6 MM (1200 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x1.200x9.56= 22.94 Kg) |
| 500 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., Noch 0.280 mtr. length, 4 No's required = (4x2.36x0.280) |
| 501 | Transformer Mounting Bracket (65x65x6 GI Angle(GI)) suitable for 16/10KVA 11/0.23 KV Transformer |
| 502 | AB Switch Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (2000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x2.000x7.14= 28.56 Kg) |
| 503 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 504 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (2000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x2.000x7.14= 28.56 Kg) |
| 505 | 25x3mm Flat(GI) for earthing, 0.59kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle) ( Each 62.6x 0.59= 36.93 Kg) |
| 506 | LT Dist. Box with MCCB for 16KVA S/S. |
| 507 | 55 SQ.MM. AAAC XLPE Covered Conductor |
| 508 | 2Cx16 mm2 LT XLPE Cable(armoured) |
| 509 | AB Switch(11KV,200A.2pole,50Hz) |
| 510 | DO.Fuse( 11KV.200A.3Pole) |
| 511 | 2.5 AMP Fuse Link |
| 512 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 513 | POLYCARBONATE BIRD GUARD |
| 514 | Disc insulator (B&S)70 KN polymer |
| 515 | H W fitting (B&S)70KN(3bolted) |
| 516 | Lightning Arrester(12KV,10KA) Station Class 2 |
| 517 | 11KV pin insulator polymer |
| 518 | HT stay set complete |
| 519 | HT stay Clamp (1.9Kg/pair) |
| 520 | HT stay insulator TYPE-C |
| 521 | 7/10 SWG GI stay wire, Grade -2 (15Kg./ Set) |
| 522 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 523 | GI Nuts & Bolts of Assorted size (15 Kg/ DSS SP) |
| 524 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 525 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 No's = (4x0.59x0.510) |
| 526 | Danger plate 11kv |
| 527 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 No's (Noch 1x0.59x0.510) |
| 528 | Name plate |
| 529 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 530 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 531 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) |
| 532 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 533 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (3X2X0.1)= 0.6 Cu. mtr. |
| 534 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 535 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 536 | Laying of 2 Cx 16 mm2 LT PVC Cable |
| 537 | Supply of AL Lugs suitable for 16 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 538 | SITC and Erection of GI Fencing with Gate |
| 539 | PART-P: - Shifting of approximately 2.100kM of existing 1.1kV OH LT line, followed by construction of approximately 2.253kM of new 1.1kV OH LT line with 2X35+1X25 sqmm ABC (Ref.: - SLD-1 at Bhatarika Chhaka to Padmanavapur Managala Mandir 63KVA, SLD-2 at at Padmanavapur Mangala Mandira 63KVA S/s to Khariamada Medical, SLD-4 at Khariamada Medical to Khariamada village, SLD-7 at Kesabareni, SLD-8 at New Kesabareni 63KVA, SLD-10 at Karadibandha Pond to Bhagabata Ghara, SLD-11 at Karadibandha Bhagabata Ghara to GP Office, SLD-13 at Karadibandha Bridge to Ogalapur village water tank, SLD-14 at Ogalpur village water tank to Bhattarika Panthasala road, SLD-15 at 500KVA S/s DP Sasanga to Bhattarika 100KVA S/s DP & SLD-16 at Bhatarika Panthasala 100KVA S/s DP). (To be executed by party and maintained by TPCODL under 6% supervision charges) 9 Mtr. long 300 Kg. PSC Pole |
| 540 | LT Stay set Complete |
| 541 | 7/12 SWG GI stay wire, Grade -2 |
| 542 | LT stay Clamp ( 1.40Kg/pair) |
| 543 | LT Stay insulator |
| 544 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 545 | EYE hook for XLPE Aerial bunched Cable |
| 546 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 547 | Suspension Clamp with EYE hook for ABC |
| 548 | 2X35 + 1X25 (LT AB Cable) |
| 549 | 4 WAY SERVICE Distb. Box with kit kat fuse and Aluminium bus bar. |
| 550 | Insulated piercing connector.Type-B-main 25 to 150 sq.mm & Tap-6 to 35 sq.mm |
| 551 | GI Pipe Earthing (each 5th pole to earth) |
| 552 | Coil Earthing |
| 553 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 554 | Danger plate (LT) |
| 555 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 556 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 557 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 558 | GI Nut , Bolt & Washer of different sizes (0.5 Kg/ Pole) |
| 559 | Black Paint(GIS Numbering & Zebra Stripping) |
| 560 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 561 | Fixing of LT Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.) |
| 562 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) |
| 563 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 564 | PART-Q: - Shifting of approximately 3.200kM of existing 1.1kV OH LT line, followed by construction of approximately 3.555kM of new 1.1kV OH LT line with 4X35+1X35+1X16 sqmm ABC (Ref.: - SLD-5 at Khariamada village to Banamalipur Bazar end, SLD-8 at New Kesabareni 63KVA, SLD-9 at Karadibandha Budhabudhisahi 63KVA S/s, SLD-10 at Karadibandha Pond to Bhagabata Ghara, SLD-11 at Karadibandha Bhagabata Ghara to GP Office & SLD-16 at Bhatarika Panthasala 100KVA S/s DP). (To be executed by party and maintained by TPCODL under 6% supervision charges) 9 Mtr. long 300 Kg. PSC Pole |
| 565 | LT Stay set Complete |
| 566 | 7/12 SWG GI stay wire, Grade -2 |
| 567 | LT stay Clamp ( 1.40Kg/pair) |
| 568 | LT Stay insulator |
| 569 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 570 | EYE hook for XLPE Aerial bunched Cable |
| 571 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 572 | Suspension Clamp with EYE hook for ABC |
| 573 | 4C×35 mm² (P)+1C×35 mm²(M)+1CX16 mm²(Street Light) (LT AB Cable) |
| 574 | 4 WAY SERVICE Distb. Box with kit kat fuse and Aluminium bus bar. |
| 575 | Insulated piercing connector.Type-B-main 25 to 150 sq.mm & Tap-6 to 35 sq.mm |
| 576 | GI Pipe Earthing (each 5th pole to earth) |
| 577 | Coil Earthing |
| 578 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 579 | Danger plate (LT) |
| 580 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 581 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 582 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 583 | GI Nut , Bolt & Washer of different sizes (0.5 Kg/ Pole) |
| 584 | Black Paint(GIS Numbering & Zebra Stripping) |
| 585 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 586 | Fixing of LT Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.) |
| 587 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) |
| 588 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 589 | PART-R: - 1. Shifting of approximately 4.900kM of existing 1.1kV OH LT line, followed by construction of approximately 5.067kM of new 1.1kV OH LT line with 4X50+1X50+1X16 sqmm ABC (Ref.: - SLD-1 at Bhatarika Chhaka to Padmanavapur Managala Mandir 63KVA, SLD-2 at at Padmanavapur Mangala Mandira 63KVA S/s to Khariamada Medical, SLD-4 at Khariamada Medical to Khariamada village, SLD-5 at Khariamada village to Banamalipur Bazar end. SLD-7 at Kesabareni, SLD-10 at Karadibandha Pond to Bhagabata Ghara, SLD-11 at Karadibandha Bhagabata Ghara to GP Office, SLD-13 at Karadibandha Bridge to Ogalapur village water tank, SLD-14 at Ogalpur village water tank to Bhattarika Panthasala road & SLD-16 at Bhatarika Panthasala 100KVA S/s DP). 2. Installation of 30 Nos 11 Mtr. WPB Pole for LT AB Cable road Crossing (Refer PSLD) (To be executed by party and maintained by TPCODL under 6% supervision charges) WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)(Total Pole Weight with Base Plate & Stiffner=334.84 KG+10.74 KG= 345.58 KG) |
| 590 | 9 Mtr. long 300 Kg. PSC Pole |
| 591 | LT Stay set Complete |
| 592 | 7/12 SWG GI stay wire, Grade -2 |
| 593 | LT stay Clamp ( 1.40Kg/pair) |
| 594 | LT Stay insulator |
| 595 | Pole clamp for EYE hook for (XLPE Aerial bunched Cable) |
| 596 | EYE hook for XLPE Aerial bunched Cable |
| 597 | Dead End Clamp suitable for messenger XLPE Aerial bunched Cable |
| 598 | Suspension Clamp with EYE hook for ABC |
| 599 | 4C×50 mm² (P)+1C×50 mm²(M)+1CX16 mm²(Street Light) (LT AB Cable) |
| 600 | 4 WAY SERVICE Distb. Box with kit kat fuse and Aluminium bus bar. |
| 601 | Insulated piercing connector.Type-A-main 50 to 150 sq.mm & Tap-50 to 150 sq.mm |
| 602 | GI Pipe Earthing (each 5th pole to earth) |
| 603 | Coil Earthing |
| 604 | No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing |
| 605 | Danger plate (LT) |
| 606 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 1 no's = (1x0.59x0.510) |
| 607 | GI barbed wire anticlimbing device 3 Kg. Per support |
| 608 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 4 no's = (4x0.59x0.510) |
| 609 | GI Nut , Bolt & Washer of different sizes (0.5 Kg/ Pole) |
| 610 | Black Paint(GIS Numbering & Zebra Stripping) |
| 611 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 612 | Fixing of LT Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.) |
| 613 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 614 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 615 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1500mm) = 0.375Cu.mtr(Per Pole) |
| 616 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe . |
| 617 | PART-S : - Dismantling Materials against shifting (Ref. SLD-1 to SLD-16) (Dismantled material have to be returned to nearby TPCODL store)Dismantling of 11/13 Mtr.Joist/WPB Pole-150X150 mm/160X160mm |
| 618 | Dismantling of 09/11 Mtr. Joist/WPB Pole- 116X100mm |
| 619 | Dismantling of 9/8 Mtr. PCC/Joist Pole |
| 620 | Dismantling of existing 11/0.4kV, 33/0.4KV, Three Phase Distribution Transformer 16KVA including removal of HT/LT leads, earth connections and unloading by crane if required. |
| 621 | Dismantling of existing 11/0.4kV, 33/0.4KV, Three Phase Distribution Transformer 63KVA including removal of HT/LT leads, earth connections and unloading by crane if required. |
| 622 | Dismantling of existing 11/0.4kV, 33/0.4KV, Three Phase Distribution Transformer below 100KVA including removal of HT/LT leads, earth connections and unloading by crane if required. |
| 623 | Dismantling of ACSR/AAAC 34/ 55mm2 from overhead line |
| 624 | Dismantling of ACSR/AAAC 80/100 mm2 from overhead line |
| 625 | Dismantling of varous size of LT AB CableN:B;. Salvage Value @8% to be deducted from the contractor's bill. Please Enable Macros to View BoQ information |
| SR No | FileName | File Description |
| 1 | Click here to download tender document | Tender Documents |
| 2 | Click here to download tender document | Tender Documents |
| 3 | Click here to download tender document | Tender Documents |
| 4 | Click here to download tender document | Tender Documents |
Copyright © 2026 · All Rights Reserved. Terms of Usage | Privacy Policy
For Tender Information Services Visit : TenderDetail