| 1 | Dismantiling cement concrete or brick or granolithic floors including stacking of dismantled materials as directed by E/IC with in a distance of 60meters (17-Chapter SI.No.697). |
| 2 | Dismentling Existing damage Plaster Including disposal of refuse as directed by E/IC with in a distance of 60 meters etc. all complete. {Chapter No. 17 S.I. No.16 (706)} |
| 3 | Dismantling stone slab flooring laid in cement mortar including stacking of serviceable material and disposal of unserviceable material within 50 metres lead. (17-Chapter SI.No.16) |
| 4 | Cleaning of the site for warkable etc. All complete. (Non Scheduled) |
| 5 | Excavation in foundation in ordinary soil (loam, clay or sand) including, lift up to 1.50 m and lead up to 30m and including filling watering and ramming of oxcavated the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the engineer-in-charge up to a distance of 30m form the foundation trenches. (Rate including Royalty of earth also) (4-Chapter S.I.NO.- 251) |
| 6 | Earth work in Cutting or in embankment in rodinary soil excavation to be in the form of a regular pits not exceeding 0.50m in depth and earth work in embankment to be in 20cm layers including ramming and dressing the surface to required lavels and slops and also including 1.5 m lift and 30 m lead. The earth in form of cutting (b) to be used as spoil banks within 50m distance as directed by the Engineer-in-Charge etc. all complete. (20-Chapter PWD.SCH.No.253(a))PWD Sheduled 2015 |
| 7 | Providing and laying cement concrete in 1:5:10 (1 cement :6 fine sand 12 stone ballast 40 mm gauges) and curing complete, including cost of form work in foundation and floors. (5-Chapter S.I. No. 01) |
| 8 | Providing and laying D.P.C. 40cm. Thick with cement concrete consisting of one part cement 1.5 part of coarse sand and three part of approved 10mm grade stone grit and including water proofing material as directed by the engineer-in-charge in the proportion as specified by the manufacturer. {Chapter No.07 Si.No.1} |
| 9 | Class-150 Brick Work in 1:4 Cement and Coarse Sand, mortar in foundation and plinth including supply of all materials, labor and tools and plants, etc. Required for proper completion of the work. ( Chapter No. 06 S.I. No. 305) |
| 10 | RCC work Providing and laying in position specified grade of reinforced cement concrete , including the cost of centering, shuttering, finishing and excluding reinforcement - All work up to plinth leuel:1:2:4 (1 cement: 2 coarse sand :4 graded stone aggregate 20 mm nominal size) (5-Chapter S.I. No.-8) |
| 11 | Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not included in and an overall rates) brought for proper completion of the work and including supply of steel, its wastage bend hooks and authorized over lapping shall be measured up to floor two level. (b) 10mm to 12mm tor.(Chapter No. 10 S.I. No. 504(B)) |
| 12 | 12mm cement plaster in single coat on rough site of single of half brick wall for interior plastering up to floor to level including internal rounded angles not excluding 80mm in girth and finished even and smooth. (b) 1cement : 6 Coarse sand. (Chapter No.13 Si.No. 1) |
| 13 | Mild steel of iron in heavy size such as trusses built up gates record reck, roof work gates etc. brought to required form including drilling holes revitting are welding where neccesary, and also including supply of steel bolts , nuts wastage etc. and there fixing required for completion of the work. |
| 14 | Cartage of Ballast, Kankar, Coal, Grit or Sand etc, including loading and unloading but excluding stackings on pucca roads. (Chapter No.3Si.No.8)8km. |
| 15 | Sub Total |
| 16 | Add/Deduction Rs. For Estimate Figure Amount Match |
| 17 | Grand Total Please Enable Macros to View BoQ information |