| 1 | Dismantling brick work tile, masonry or tile lining In cement |
| 2 | Dismantling stone pitching or soling grouted with natural silt and clay |
| 3 | Dismantling concrete Cement concrete plain 1:4:8 |
| 4 | Site clearance Excavation in dumped stone or malba including stacking of unserviceable material separately and disposal of unserviceable material. Lead up to 50 m and lift up to 1.5 m, disposed material to be neatly dressed in all kinds of soils. |
| 5 | Excavation in Soil (any type) using Hydraulic Excavator CK 90 with hydraulic excavator of 0.9 cum bucket capacity including cutting, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, including all lifts and combined lead upto 30m. |
| 6 | Cement concrete 1:4:8 with stone Aggregate of 40mm gauge |
| 7 | Construction of granular sub-base by providing material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per MORD technical specifications |
| 8 | Providing, laying, spreading and compacting stone aggregates of Grading II to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheeled roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical specifications |
| 9 | Reinforced cement concrete M-25 mechanically batch mixed using batch type concrete mixer as per IS:1791 and vibrated by needle vibrator but excluding steel reinforcement centring and shuttering in superstructure. |
| 10 | Centering and shuttering for faces of walls, partitions, retaining walls and the like (vertical or battering including attached pilasters buttresses etc. |
| 11 | Cement concrete 1:2:4 mixing by mechanical means using concrete mixer volumetric type With stone aggregates 40mm gauge |
| 12 | Cold twisted detormed (Ribbed/ Tor steel) Bars (Fe 550 grade as per IS 1786-2008) , for R.C.C works, where not including in the complete rate of RCC including binding, bending and placing in position complete |
| 13 | Providing, lowering in trenches to correct gradient and allignments, jointing with tytone rubber joint and cutting of RCC S/S pipes having inside HDPE. lining ISI marekd as per ISI code IS:458-2003 into trenches for all depths and laying out the same to correct alignment, gradients, levels etc.,cutting of concrete beds and joints holes, supporting the pipes and specials in correct position in a suitable rigid manner while the same are being jointed and until the surrounding benchings, haunches and envelopes are completed. The pipes shall rest on the beds at all joints through their lengths and to ensure this, testing the pipes for leakage and making good the same leakage and all defects to the entire satisfaction of the Engineer incharge including all cartage etccopmplete in all respects. R.C.C. pipe with inside H.D.P.E. liningclass- NP-3 400mm i/d pipe with inside H.D.P.E.lining |
| 14 | Extra for providing 1:2 cement sand mortar on tytone rubber joint of RCC pipes having sockets extended out of barrel, in trenches including facing trowelling and finishing the joints at the angle of 45 degree with faces of socket keeping joints wet till cured, testing the pipe joints for leakproof and making good all leakage and defects as per specifications. NP-3 & NP4 Pipes S/S joints having internal dia meter of pipe:- 400mm i/d pipe |
| 15 | Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint for fixed ends of simply supported spans not exceeding 10 m to cater for a horizontal movement upto 20 mm, covered with sealant complete as per drawing and technical specifications. |
| 16 | Providing and laying of boulder apron laid in wire crates made with 4mm dia GI wire confoming to IS: 280 & IS:4826 in 150mm x 150mm mesh (weaved diagonally) including 10 per cent extra for laps and joints laid with stone boulders weighing not less than 18 kg, Including excavation for trimming. |
| 17 | Add credit of 400mm RCC Pipe NP-3 Same Qty as above items No.8 |
| 18 | Add credit of Brickwork dismantled Same Qty as above items No.1 |
| 19 | Add Culture Cess @ 1 % Please Enable Macros to View BoQ information |