| 1 | Material of DP with AB Switch for Termination of UG CableWPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP |
| 2 | Top Channel(GI) 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 3 mtr., 2 no's Channel(GI) required =( 2x9.56x3) |
| 3 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 4 | AB switch Mounting Channel(GI) 75X40X4.8mm, 7.14KG/Mtr, each Channel(GI) length 3 Mtr., 2 no's Channel(GI) required =( 7.14x3x2) |
| 5 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 6 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 7 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 3.0 Mtr., 4 no's Channel(GI) required =( 7.14x3x4) |
| 8 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.512 mtr., 4 nos Angle(GI) required = (4.5x3.512x4) |
| 9 | Danger Plate, 2 no's. |
| 10 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 11 | H.T. Stay clamp, 50x8 mm. Flat(GI), 3.14Kg/Mtr., 0.551 Mtr. Length, 2 no's qty. required ( 1 Pair) |
| 12 | H.T. Stay set (Complete ) |
| 13 | H.T. Stay Insulator Type-C |
| 14 | 7/10 SWG Stay Wire 15kg /stay |
| 15 | Gi Pipe Earthing 40mm. 3 Mtr. Long |
| 16 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (12.5 Mtr. For L.A, 3 Mtr for AB Switch Body, 2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 20.5x2.36 |
| 17 | GI barbed wire anticlimbing device 3 Kg. Per support, 2 no's qty. required =(2x3kg) |
| 18 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 19 | Lightning Arrester(12KV,10KA) (Station Class,class-2) |
| 20 | AB Switch (11KV,400A.3pole,50Hz) |
| 21 | 11 KV pin insulator polymer |
| 22 | H W fitting(B&S) 70KN, 3Bolt |
| 23 | Disc insulator (B&S) 70 KN polymer |
| 24 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 25 | POLYCARBONATE BIRD GUARD |
| 26 | GI Nut , Bolt & Washer of different sizes (13.718 Kg each DP with AB Switch) |
| 27 | Black Paint(GIS Numbering & Zebra Stripping) |
| 28 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 29 | Civil & ServicesFixing of complete 11KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire.5)Stay clamps with Nuts & bolts BA will do the excvation including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size ( 500mmx500mmx800mm) using 20mm BHG metal with all labour and material as per TPCODL Drawing & Standard. |
| 30 | Concreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.45Cu.mtr(Per Pole) |
| 31 | Couping ratio 1:1.5:3(M-20 Grade) with dimension ( 500X500X450)= 0.1125 Cu mtr(Per Pole) |
| 32 | Provide necessary civil material for construction of Earthing chamber, excavation & installation of incuding earthingpipe dia up to 100mm dia for length of 3Mtr.Scope also includes necessary nutbolt, 25 Kg Bentonide Power , connection & welding with incoming earth Flat(GI). The work to be executed as per TPCODL drawing & design |
| 33 | MATERIALS FOR 11 KV Cut Point with 180 Degree AngleStraight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 1.2 mtr., 2 no's Channel(GI) required =( 2x9.56x1.2) |
| 34 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 8 no's required = (8x2.36x0.280) |
| 35 | Straight Cross Arm 100X50X6mm, 9.56 KG/Mtr., each Channel(GI) length 0.306 mtr., 2 no's Channel(GI) required =(2x9.56x0.306) |
| 36 | 11 KV pin insulator polymer |
| 37 | H W fitting(B&S) 70KN, 3Bolt |
| 38 | Disc insulator (B&S) 70 KN polymer |
| 39 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 40 | POLYCARBONATE BIRD GUARD |
| 41 | GI Nut , Bolt & Washer of different sizes (3.55 Kg each Cut Pole) |
| 42 | Materials for 11 KV Pin Points with WPB55 sqmm AAA conductor |
| 43 | 11Kv 3c,95 Sqmm UG Cable with HDD methodSupply of 11kV, 3Core, 95sqmm, XLPE insulation armoured UG cable (SC rating of cable in kA- 9kA and SC rating of Armour in kA- 9kA) |
| 44 | Supply of Outdoor termination kits Heat Shrinkable type suitable for 11kV, 3Core, 95sqmm, HT UG Cable kits |
| 45 | Erection PortionErection of Straight through jointing Kits/Outdoor termination kits/Indoor termination Kits Heat Shrinkable type suitable for 11kV, 3Core, 95sqmm, aluminium UG cable kits |
| 46 | Installation, Laying, Commissioning & Testing of 11kV, 3Core, 95sqmm, XLPE U/G cable by HDD method with HDPE pipe (160mm dia, PN8 PE80) including suply of HDPE Pipe. |
| 47 | Supply and erection of GI Pipe of dia. 150mm, Class-B (8Mtr.) |
| 48 | Supply and Erection of Cable Route Marker along the cable route at an interval of 30mtrs with civil works |
| 49 | SUPPLY OF FOLLOWING EQUIPMENT & MATERIALS WPB (GI) Pole 160x152 (11Mtr. Long, 30.44KG/Mtr.)-DP |
| 50 | Top Channel(GI) GI 100 X 50 X 6 MM (3000 mm long) (9.56Kg./Mtr, 2 No's.) (Each 2x3.000x9.56= 57.36 Kg) |
| 51 | Fish Plate(GI) 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280) |
| 52 | AB Switch Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 53 | AB Switch Side Support Channel(GI) 100X50X6mm,9.56 KG/Mtr., each Channel(GI) length 0.35 mtr., 2 no's Channel(GI) required =( 9.56x2x0.35) |
| 54 | Channel(GI) Support for down Pipe 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 0.8 Mtr., 1 no's Channel(GI) required =( 7.14x0.8x1) |
| 55 | HG/ DO Fuse Mounting Channel(GI) 75x40x4.8 mm GI Channel(GI) (3000 mm long)(7.14Kg./Mtr., 2 No's.) (Each 2x3.000x7.14= 42.84 Kg) |
| 56 | Cantilever Support Channel(GI) 75x40x4.8 mm GI Channel(GI) (810 mm long,2 No's.) (7.14Kg./Mtr., 2 No's.) (Each 2x0.810x7.14= 11.57 Kg) |
| 57 | Cantilever Support Angle(GI) 50 X 50 X 6MM GI (1282 mm long) (4.5Kg./Mtr, 2 No's.) (Each 2x1.282x4.5= 11.54Kg) |
| 58 | Double Pole Belting Channel(GI) 75X40X 4.8mm., 7.14KG/Mtr., each Channel(GI) length 3.0 Mtr., 2 no's Channel(GI) required =( 7.14x3x2) |
| 59 | 50x50x6mm.GI Bracing Angle(GI), 4.5Kg./mtr., each Angle(GI) length 3.512 mtr., 2 nos Angle(GI) required = (4.5x3.512x2) |
| 60 | 50x6mm Flat(GI) for earthing, 2.36kg/mtr., (2.5x7 mtr. For mesh formation, 12 Mtr. For LA and 2.5 mtr. For raising, 11 mtr for AB switch, 2.8 mtr for HG Fuse, 5x2 mtr. for DTR Nutral, (1.3+4.5) mtr. For DTR Body, 0.500 mtr for LTDB & AB Switch operating handle, 3 mtr. for Fencing) ( Each 65.6x 2.36= 154.81 Kg) |
| 61 | 100 KVA , 11/ 0.4 KV (AL) Transformer BIS Energy level II |
| 62 | LT Distribution Box with MCCB, Aluminium Busbar of 2 Bay with kit kat fuse for 100 KVA S/S |
| 63 | 55mm2 ACSR - PVC Insulated (50 Mtr. Each Dtr.) |
| 64 | 4 Cx 150 mm2 LT XLPE Cable(Armoured) - FOR 100 KVA Trf. |
| 65 | AB Switch(11KV,200A.3pole,50Hz) |
| 66 | H.G.Fuse( 11KV.200A.3Pole) |
| 67 | WEDGE CONNECTOR FOR 55 SQMM.CONDUCTOR |
| 68 | POLYCARBONATE BIRD GUARD |
| 69 | Disc insulator (B&S)70 KN polymer |
| 70 | H W fitting (B&S)70KN(3bolted) |
| 71 | Lightning Arrester(12KV,10KA) Station Class 2 |
| 72 | 11KV pin insulator polymer |
| 73 | HT stay set complete |
| 74 | HT stay Clamp (1.9Kg/pair) |
| 75 | HT stay insulator TYPE-C |
| 76 | 7/10 SWG GI stay wire, Grade -2 (15Kg./ Set) |
| 77 | 40 mm Nominal bore GI pipe (medium gauge) earthing device with 3 mtr .Long |
| 78 | GI Nuts & Bolts of Assorted size (25 Kg/ DSS DP) |
| 79 | GI Barbed wire/Anticlimbing device (3Kg /Pole) |
| 80 | Back Clamp for anticlimbing device 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 8 no's = (8x0.59x0.510) |
| 81 | Danger plate 11kv |
| 82 | Back Clamp for danger Plate 25X3 mm. Flat(GI), 0.59Kg/Mtr. Flat(GI) of 0.510mtr length 2 no's = (2x0.59x0.510) |
| 83 | Name plate |
| 84 | Yellow Colour Paint(GIS Numbering & Zebra Stripping) for Background |
| 85 | Black Colour Paint(GIS Numbering & Zebra Stripping) for numbering |
| 86 | Civil and Services WorksConcreting ratio 1:1.5:3(M-20 Grade) (500mmX500mmX1800mm) = 0.450Cu.mtr(Per Pole) (For WPB Pole) |
| 87 | Couping ratio 1:1.5:3(M-20 Grade) (500mmX500mmX450mm) = 0.113Cu.mtr(Per Pole) |
| 88 | PCC ratio 1:3:6(M-10 Grade) For DSS Area (5X3X0.1)= 1.5 Cu. mtr. |
| 89 | Fixing of stay set with 0.5Cum cement concrete foundation 1:3:6(M-10 Grade) size ( 900mmx600mmx900mm) using 40mm BHG metal with all labor and material except stay set , stay wire , stay insulator . |
| 90 | Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earthresistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of Flat(GI)around pipe . |
| 91 | DTR Plinth |
| 92 | Laying of 4 Cx 150 mm2 LT XLPE Cable |
| 93 | SITC and Erection of GI Fencing with Gate |
| 94 | Supply of AL Lugs suitable for 150 sq mm cable/conductor, Crimping with cable and Fixing/connecting include supply and erection of PVC Tape as per voltage requirement. |
| 95 | Supply and erection of double Compression Flameproof Type Glanding for armored Cable 3.5/4C 120-185sqmm including making hole in Base plate and dressing of cable along with vermin proofing properly .Supply to be done as per TPCODL Spec and approved make dowells. |
| 96 | Materials for Service Connection4C X 150 sqmm Armoured Aluminium Cable-XLPE Insulated |
| 97 | Insulated piercing connector bType-A main 50 to 150 Sqmm & Tap -50 to 150 Sqmm - for LT AB Cable |
| 98 | GI Nut, Bolt & Washer of different sizes Please Enable Macros to View BoQ information |