| 1 | Installation of Pre-insulated lugs for 50sqmm |
| 2 | Installation of Pre-insulated lugs for 16sqmm |
| 3 | Providing End Caps |
| 4 | Providing Cable Tie |
| 5 | Additional rate for excavation of one Pit for Coil Earthing in Laterite |
| 6 | Additional rate for excavation of one Pit for Coil Earthing in Hard Laterite. |
| 7 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 8 | Labour charges for loading LT PSC pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 9 | Dismantling (without damage) one km LT single phase 2 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. |
| 10 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. |
| 11 | Renewal of existing damaged/old LT stay with new stay in place including excavation of stay pit, erection of new stay, backfilling pit and refitting of all items and conveyance of all materials. |
| 12 | Renewal of existing damaged/broken old LT stay in existing stay rod. |
| 13 | Providing Fly stay for LT pole using LT PSC pole including digging and back filling pit in ordinary soil. |
| 14 | Additional rate for excavation of one Pit for LT Pole/LT Stay in Laterite. |
| 15 | Additional rate for excavation of one Pit for LT Pole/LT Stay in Hard Laterite. |
| 16 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 17 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 18 | Erection of suspension clamp for LT ABC of any size |
| 19 | Installation of Insulation piercing connector for main to service line main :16-95 sqmm, Tap : 4-35 sqmm |
| 20 | Installation of Insulation piercing connector for main to service line main :16-95 sqmm, Tap 16-95 sqmm |
| 21 | Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size |
| 22 | Installation of Pre-insulated lugs for 70sqmm |
| 23 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt & nut etc. |
| 24 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 25 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. |
| 26 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. |
| 27 | Straightening one slanted LT pole after unbinding the line and binding the line after work. |
| 28 | Straightening one slanted LT Cut Pole after lowering down the existing line and stringing the line after work. |
| 29 | Renewal of existing damaged/old LT PSC/RCC (single phase line) pole with new PSC pole in place including excavation of pole pit, erection of new pole, backfilling pit and refitting of all items except street light fitting etc. and conveyance of all materials except pole. |
| 30 | Insertion of one LT PSC pole in existing single phase OH line including digging & back filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation of poles. |
| 31 | Insertion of one LT PSC pole in existing three phase OH line including digging & back filling pit in ordinary soil, fitting cross arm, insulator, binding etc. excluding transportation of poles. |
| 32 | Providing one Coil Earth using No.8 GI-earth wire (50mm dia, 115 turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 33 | Providing WP support with PSC pole including digging & back filling pit in ordinary soil. excluding transportation of poles. |
| 34 | Providing Strut using LT PSC pole including digging and back filling pit in ordinary soil. |
| 35 | Fitting one LT 2 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 36 | Fitting one LT 4 line cross arm on HT or LT existing poles including fitting insulators and binding the same with LT Line. |
| 37 | Additional rate for refitting/redoing one Shackle Set, including reshacling one span, while renewing any type of LT pole. |
| 38 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. Please Enable Macros to View BoQ information |