| 1 | Fitting and erecting one HT A type Single Pole in position, including fitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 2 | Additionalrateforprovidingonediscset,PGclampetc.complete,onany type of HT pole for making cut point. |
| 3 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 4 | Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 5 | FittingoneAdditional2.4m/3mChannelcrossarm(100x50x6mm),in existing 11kV DP including conveyance of materials. |
| 6 | Transferring LT single phase 2/3 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 7 | Transferring LT three phase 4/5 wire OH line to newly erected HT/LT pole including dismantling existing cross arm and insulators, refitting the same on the new pole, binding etc. complete. |
| 8 | Dismantling(withoutdamage)oneLTPSC/RCCpoleafterdisconnecting stays, strut etc. attached thereon and stacking the same. |
| 9 | Dismantling(withoutdamage)LTstayincludingdiggingpitinallclasses of soil and backfilling. |
| 10 | Conveyance of one km 11kV line materials from section store/stackingplace to the work site (excluding poles). |
| 11 | Providingconcretemuffingofsize0.45x0.45x1.5m(0.5maboveGLand 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 12 | FittinganderectingoneHTPSCSinglePoleinposition,includingfitting cross arm, digging and back filling pit in ordinary soil (as per standards), drawing sufficient length of GI earthing leads from F clamp through V cross arm to the ground for earthing (excluding provision of earthing). |
| 13 | FittingoneAdditional75x40mm,1.8mChannelcrossarminexisting single pole including conveyance of materials. |
| 14 | LabourchargesforloadingHTPSCpolefromthestackingplaceand unloading the same at work site (transportation by any vehicle). |
| 15 | Fitting one set AB switch on existing DP, giving connection and drawing sufficientlengthofGIearthingleadstothegroundforearthing,excluding provision of earthing. |
| 16 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 17 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 18 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 19 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon or equivalant (3 conductors) after fitting insulators, binding conductors to pin insulators using suitable tie and anchoring with wedge type anchoring clamps including cutting and removing tree branches wherever necessary excluding cut point works. |
| 20 | FittingandprovidingoneStrutusingHTPSCpoleincludingdiggingand back filling pit in ordinary soil. |
| 21 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 22 | ProvidingoneCoilEarthusingNo.8GI-earthwire(50mmdia,115turns) including digging separate pit (0.45x0.45x1.5m) at standard distance away from the pole/structure in ordinary soil & backfilling. |
| 23 | FittingoneAdditionalVcrossarminexistingsinglepoleincluding conveyance of materials. |
| 24 | Dismantling (without damage) one km 11kV line (three conductors) including dismantling cross arm, insulators, disc, disconnecting jumper connection, rolling the conductor and stacking the materials. |
| 25 | Dismantling (without damage) one HT stay including digging pit in allclasses of soil and backfilling, and bringing back to section store. |
| 26 | Dismantlingonedamaged11kVPSC/RCCpoleafterdisconnectingstays, strut etc. attached thereon and stacking the same. |