| 1 | Boiler |
| 2 | Dismantling, fabrication, erection of leak proof Dampers at PA, SA,FD & ID fans |
| 3 | Dismantling, fabrication & erection of air heater outlet top plate. |
| 4 | Dismantling, Fabrication, Erection of RO water storage tanks canopy and railing. |
| 5 | Dismantling, fabrication & erection boiler furnace ash discharge hopper |
| 6 | Dismantling, fabrication & erection of air heater outlet Bottom plate. |
| 7 | Dismentling , Fabrication Erection of Rotory bagasse feeder Casing |
| 8 | Dismentling , Fabrication Erection of belt conveyor structure |
| 9 | Dismantling, Fabrication & Erection of S.A. Fan foundation |
| 10 | Dis, fabrication and erection work of expansion Bellows AT FD, ID, ESP, economizer, APH |
| 11 | Ducting work with structure |
| 12 | Strengthening of ducting of boiler. |
| 13 | Dismantling, Fabrication & Erection of F.D. Fan foundation |
| 14 | Dis, fabrication and erection of ID Fan upper & Lower Casing |
| 15 | Dis, fabrication and erection of F.D. Fan upper & Lower Casing |
| 16 | Dismantling, Fabrication & Erection of Drum type Rotary Bagasse feeder (with shaft) |
| 17 | Dismantling, Fabrication & Erection of Screw feeder |
| 18 | Dismantling, Fabrication & Erection of Screw feeder Casing. |
| 19 | Fabrication & Erection of Man hole 24”X24” |
| 20 | Dis., Fab & Erecting of APH tubes (Replacement) |
| 21 | Dis, fab & Erection of R.O plant pressure vessel stand |
| 22 | Fab & Erection of fire fighting pipe line including Valves, bends, flange & support ( using new pipeline & old drum to drum tubes) |
| 23 | Travelling grate front side ash discharge plate Dis, fab & erection with structure |
| 24 | Fab & Erection of travelling grate rear plate flange (Flange type ) |
| 25 | Fabrication & erection of pneumatic spreader assembly from 10 mm thk. S.S. plate with fabrication & erection of deflector plate from 20mm thk. S.S. Plate with top & bottom flange |
| 26 | Dismantling of old pneumatic spreader assembly & Internal deflector plate |
| 27 | Dismantling & fitting/ Replacement of ID fan Impeller |
| 28 | Fabrication & erection of ID fan Suction bend |
| 29 | Fabrication & erection of ID fan suction cone |
| 30 | Fabrication & erection of plate & spindle type damper with flanges |
| 31 | Dismantling, fabrication & erection of rotary soot blower |
| 32 | Dismantling, fabrication & erection of Long retractable Soot blower |
| 33 | Dismantling, Fabrication & erection of economizer L.H.S. & R.H.S from 6 mm thk. M.S. plate with strengthening from 65 x 65 angles |
| 34 | Fabrication & erection of 1.5 kg/cm2 PRDS, exhaust & vapour pipeline from 10mm thk. M. S. Plate |
| 35 | Fabrication & erection of 1.5 kg/cm2 PRDS, exhaust & vapour pipeline drains |
| 36 | Dismantling, overhauling and fitting 1.5 kg/cm2 new PRDS(25 TPH) 400 N.B valve |
| 37 | Dismantling, fabrication & erection of new bagasse discharge chute at return bagasse carrier with gate arrangement complete set in all respect |
| 38 | Fabrication and erection of Boiler outlet/economizer hopper |
| 39 | Fabrication and erection of water monitor on fire fighting line |
| 40 | Fabrication and erection of FD fan suction cone |
| 41 | Replacement of travelling grate skid rail |
| 42 | BOILING HOUSE |
| 43 | Platform work at various stations such as Mill house, Boiler, Turbine, cranes, Boiling house, C/F house etc. if required anywhere with structure strengthening |
| 44 | Dismantling , fabrication & Erection of foundation of pump & Motor |
| 45 | Fitting of motor |
| 46 | Repairing of exhaust valve |
| 47 | Fab & Erection of double filtration system for quad & water inlet pipe in pan condenser. |
| 48 | Arrangement for lifting of vaccum filtered drums-3 nos |
| 49 | Replacement of exhaust and vapour valves in the boiling House. Dis |
| 50 | Replacement of exhaust and vapour valves in the boiling House Erec- |
| 51 | Fabrication of electric motor cover. |
| 52 | Strengthening of vapour pipe inside & outside with angle iron rings/ M.S.plate. |
| 53 | Manhole work in Vapour pipes/Headers |
| 54 | Modification in Bagacillo chimney |
| 55 | Replacement of vapour pipe. A) Dis |
| 56 | Replacement of vapour pipe. B) FAB |
| 57 | Replacement of vapour pipe. C) ERE |
| 58 | Exhaust and injection Pipeline a) Dis |
| 59 | Exhaust and injection Pipeline b) Fab |
| 60 | Exhaust and injection Pipeline c ) Ere |
| 61 | Replacement of V.pipe bends Dis |
| 62 | Exhaust & Injection bends Fab- |
| 63 | Exhaust & Injection bends Erec. |
| 64 | Dis,Fab & Ere of Final Molasses pipeline |
| 65 | Dis,Fab & Ere of suction pipe for injection, CT pump |
| 66 | Fab & Erection of M.S. vessels, square & rectangular tank |
| 67 | Increase of shell height with all the fitting and accessories Work. |
| 68 | Dis, Fab & Erection of M.S.plate work |
| 69 | Dis,Cleaning & Ere of pipeline (Juice, Massecuite, Srrup, Molasses etc) |
| 70 | Dis,Fab & Ere of Coil(water,juice,ammonia,so2etc) |
| 71 | Fab and erection of Motor bed |
| 72 | Dis,Fab & Ere of NRV for injection, turbine, spray etc |
| 73 | Saveall of Pan,Quad DIS |
| 74 | Saveall of Pan,Quad FAB |
| 75 | Saveall of Pan,Quad ERE |
| 76 | Unloading of Material from Truck (MS, SS, CI, ACC etc) |
| 77 | Dis, Fab & Ere of Jay pipe |
| 78 | Fitting of Baffle plates |
| 79 | Dismantling, Fabrication & Erection of belt conveyor structure |
| 80 | Clarifier coil work a) Dismantling |
| 81 | Clarifier coil work (b) Fabrication |
| 82 | Clarifier coil work ( c) Erection |
| 83 | Dismantling, fabrication & erection of Perforated M.S plates Of Direct contact juice heaters. |
| 84 | Dismantling , fabrication & erection of strainers of Injection, spray , C.T pumps. |
| 85 | Dismantling, erection (with alignment) of planetary gear box of crystallizers. |
| 86 | Nozzles of spray pond, condenser. |
| 87 | Dismantling (each nozzle) |
| 88 | Fitting (each nozzle) |
| 89 | Replacement of Double beat valve |
| 90 | Dismantling , fabrication & erection of exhaust valve casing |
| 91 | Opening & Fitting of Juice Heater Covers |
| 92 | Dismantling & fitting of S.S Tubes in Juice Heater & Evaporator Body |
| 93 | Dismantling, Fabrication & Erection of Mud Mixture Conveyor |
| 94 | Dismantling, Fabrication & Erection of Mud Mixture Casing |
| 95 | Dismantling, fabrication & erection of down take umbrella of Pan |
| 96 | Replacement of 3’’ coil of vertical crystallizer |
| 97 | Gutter Work (bigger side will be treated as dia.) |
| 98 | Gutter Work Dismantling |
| 99 | Gutter Work Fabrication |
| 100 | Gutter Work Erection |
| 101 | Jammed tube falling film Evaporator |
| 102 | Replacement of sluice valve |
| 103 | Fabrication / strenghting of beam, vessel, pipe, channel, angle etc. |
| 104 | Dis, Fabrication & erection of 7 kg/cm2 PRDS pipeline |
| 105 | Dis, Fabrication & erection of 7 kg/cm2 PRDS pipeline drains |
| 106 | Replacement of readymade bend |
| 107 | Replacement of ammonia pipe of pan & Quad |
| 108 | Replacing of worn out brass zig zags & S.S screens of Vacuum Filter |
| 109 | Dismantling, Fabrication & Erection of M.S plate ( As Required) |
| 110 | Dismantling of Existing syrup sulphitor & shifting to scrap yard |
| 111 | Dis., Fab & Erection of Save all cone of evaporator And pans |
| 112 | Dismantling, installation and alignment of reduction Gear box. |
| 113 | Dismantling, Fab & erection of agitator |
| 114 | Fitting & replacement of batch type machine |
| 115 | Fitting & replacement of continuous type machine |
| 116 | Replacement of exhaust balloon |
| 117 | Replacement of Savall of quad and pan |
| 118 | Replacement of screw type arm of crystallizer |
| 119 | Replacement of drive of vertical crystallizer |
| 120 | Replacement of tube of quad and juice heater |
| 121 | Dis, Fab. & Erection of foundation for clarifier drive |
| 122 | Dismantling, fabrication & Erection of cover of S400 semi-kestner |
| 123 | Replacement of S.S. pipelines including pipe fittings |
| 124 | Replacement of seamless pipeline including pipe fitting |
| 125 | Replacement of Magma mixer with arm, bracket & gear |
| 126 | Dismantling, fabrication & erection of underground S.S. pipeline for condensate water |
| 127 | Dismantling, fabrication & erection of cone as per requirement |
| 128 | Modification of bagasscillo cyclone |
| 129 | Dismantling, fabrication, assembly and trial of mechanical Circulator |
| 130 | Modification in exhaust & vapour valve |
| 131 | Dismantling, fabrication & erection of spray pond header |
| 132 | Dismantling, fabricaton & erection of basket housing Cover & bottom discharge chute of centrifugal machine |
| 133 | Dismantling, fabrication & erection of arms of clarifier |
| 134 | Dismantling, fabrication & erection of down tape of evaporator bodies |
| 135 | Fabrication & erection of molasses jacket for batch type C/F M/C |
| 136 | Hydraulic testing of vertical crystallizers complete in all respects |
| 137 | Dismantling, fabrication & erection of various stations for entrainment catcher |
| 138 | Dismantling & installation of super heater in boiling house |
| 139 | Dismantling & installation of oil cooler at turbine |
| 140 | Dismantling, fabrication & erection of all high pressure line drains at turbine |
| 141 | Replacement of cut over valve for Pan |
| 142 | Modification work in juice line below quad station |
| 143 | Dis., Fabrication & erection of grit conveyor |
| 144 | Dis., Fabrication & erection of sugar hopper |
| 145 | Dis., Fabrication & erection of M.S. Tank/Vessel |
| 146 | M.S. Pipeline replacement |
| 147 | Dis., Fabrication & erection of vapour/ exhaust line from quad to pan station |
| 148 | Dismantling and fitting vapour/exhaust valve |
| 149 | Dismantling, fabrication & erection of bagassecillo line |
| 150 | Dismantling, fabrication & erection of underground & outside pipeline of all sizes |
| 151 | BOILER/TURBINE, COOLING TOWER SUGAR GODOWN/WORKSHOP/STORE/CANE UNLOADER & FACTORY |
| 152 | Fab & Erection of gate |
| 153 | Strengthning of tress beams,vessel,pipe with channel,angle,pipe etc any where |
| 154 | Fab & Erection of M.S.stair/Ladder single story |
| 155 | Fab & Erection of M.S.stair/Ladder Double story |
| 156 | Dismantling, fabrication & erection of underground and Outside pipeline of all sizes |
| 157 | Fabrication & erection of NRV of CT Pump |
| 158 | Dismantling, fabrication & erection of turbine silencer |
| 159 | Dismantling, fabrication & erection of cooling tower pipeline from cooling tower of turbine |
| 160 | MISC .ITEMS. |
| 161 | M.S Pipeline per inch dia//ft/length (a ) Dismentling of pipe line. |
| 162 | Upto 1” dia to 12’ dia. |
| 163 | Above 12” |
| 164 | Fabrication of pipe line from M.S.plate or ready-made pipe any dia. |
| 165 | Erection of pipe line per inch dia/ft/length (i) Upto 1’ dia to |
| 166 | Erection of pipe line per inch dia/ft/length (ii. Above 12” dia |
| 167 | M.S.Pipe accessories work, dismantling of bends, Tee, reducder, cross, elbow, nipple, nozzle, flanged, and bends. (per inch dia/ft/length ) (a) Upto 1”dia to 12” dia |
| 168 | M.S.Pipe accessories work, dismantling of bends, Tee, reducder, cross, elbow, nipple, nozzle, flanged, and bends. (Per inch dia/ft/length (ii.) Above 12” dia. |
| 169 | Fabrication of bends, tee, reducer etc.-(p.inch dia/ft) (i) upto 1”diato 12” dia |
| 170 | Fabrication of bends, tee, reducer etc.-(p.inch dia/ft) ( ii) above 12\\" dia.. |
| 171 | Erection of bends, tee etc.(per inch dia/ft/length) (i) upto 1” dia to 12” dia |
| 172 | Erection of bends, tee etc.(per inch dia/ft/length) ii) Above 12” dia |
| 173 | VALVE WORK |
| 174 | Dismantling of valves, (per inch dia/pc) Upto 1” dia to 12” dia |
| 175 | Dismantling of valves, (per inch dia/pc) Above 12” dia |
| 176 | ERECTION OF VALVE |
| 177 | Dismantling of valves ,(per inch dia/ft/length) (i) Upto 1” dia to 12” dia |
| 178 | Dismantling of valves ,(per inch dia/ft/length( ii) Above 12” dia |
| 179 | PLATEFORM WORK (Per SFT) |
| 180 | I) Dismantling |
| 181 | II) Fabrication and erection |
| 182 | a) Patch work with old material. |
| 183 | b) patch with new material . |
| 184 | Purling in work.(per RFT) (i) Dismantling |
| 185 | Fabrication & Erection |
| 186 | Cutting of old flange repairing for reuse & fitting |
| 187 | Dis, fabrication and erection of distance piece |
| 188 | Mill House |
| 189 | Replacement of MS plate work, weak portion of cane carrier, chopper, leveller, fibrizer, Bagasse elevator, MBC,RBC,BC etc a) Dismantling |
| 190 | Replacement of MS plate work, weak portion of cane carrier, chopper, leveller, fibrizer, Bagasse elevator, MBC,RBC,BC etc b) Fabrication |
| 191 | Replacement of MS plate work, weak portion of cane carrier, chopper, leveller, fibrizer, Bagasse elevator, MBC,RBC,BC etc c) Erection |
| 192 | HC Flat replacement angle, beam & channel. |
| 193 | Dismantling, Fitting & alignment of C-Channel & Teflon Runner of Rake Carriers . |
| 194 | Fabrication & Erection of TRPF Cover |
| 195 | Dismantling, Fabrication & Erection of Guide(Salami) |
| 196 | Dismantling, Fabrication & Erection of trough of Bagasse Carriers |
| 197 | Dismantling, Fabrication & Erection of Bagaescillo pipe |
| 198 | Fabrication & Erection of Discharge Chute |
| 199 | Dismantling, Fabrication & Erection of BE,MBC & RBC trough |
| 200 | Dismantling, Fabrication & Erection of BE,MBC & RBC Side plate |
| 201 | Dismantling, Fabrication & Erection of Discharge chute of MBC Belt Conveyor |
| 202 | Dismantling, Fabrication & Erection of Foundation bed of Pump, Motor, Gear boxes |
| 203 | Fabrication & Erection of Weak portion of Cane Unloader Bridge, Trolley etc |
| 204 | Dismantling,Fabrication & erection of Square bar of Cane Unloader |
| 205 | Dismantling of Old Rotary screen between Mill 1 & Mill 2. |
| 206 | Modification in the MBC chain as per new RBC belt system. |
| 207 | Dismantling of Complete RBC structure. Please Enable Macros to View BoQ information |