| 1 | Dismantling pucca brick or lime concrete work includind stacking serveable materials in countablr stacks with in 15 M lead and disposal of unserviceable materials with all leads all complete as per direction of E/I. |
| 2 | Dismantling plain cement or lime concrete work includind stacking serveable materials in countablr stacks with in 15 M lead and disposal of unserviceable materials with all leads all complete as per direction of E/I. |
| 3 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. |
| 4 | Providing clean coarse sand in filling foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm think with all leads and lifts including cost of all materials, labour, royalty and taxes all complete as per specification and direction of E/I. (Mode of measurement compacted volume) |
| 5 | Providing designation 75B one brick flat soiling joints filled with local sand including cost of watering taxes, royalty all complete as per building specification and direction of E/I. |
| 6 | Reinforced cement concrete work in wall (any thickness),Including attached pilaster ,buttresses,plinth and string course,fillets,columns,pillers ,piers etc all complete as per specification and direction of E/I. |
| 7 | Reinforcement cement concrete work in beams, suspended floors,roof having slope upto 15 landing, balcony ,shelves,chajja,lintel,bands etc all complete as per specification and direction of E/I. |
| 8 | Providing Tor steel reinforcement of 8mm dia bars cutting bending and binding with annealed wire with cost of wire, removal of roots, placing the rods in position as per approved disign and drawing all complete as per specification and direction of E/I. |
| 9 | Providing Tor steel reinforcement of 10mm dia bars cutting bending and binding with annealed wire with cost of wire, removal of roots, placing the rods in position as per approved disign and drawing all complete as per specification and direction of E/I. |
| 10 | Providing centring and shuttering including strutting, propping etc. and removal of formwork for foundations, footings, bases of column etc all complete as per specification and direction of E/I. |
| 11 | Filling in foundation trenches and plinth in layers not exceeding 150mm thick well watered rammed, fully compacted and fine dressed with earth obtained from excavation of foundation treanches within a lead of 50M and lifts of 1.5M all complete as per specification and direction of E/I. |
| 12 | CARRIAGE CEMENT & STEEL ( LEAD 2K.M ) |
| 13 | SAND ( LEAD 20 K.M ) |
| 14 | STONE CHIPS ( LEAD 18 K.M) |
| 15 | BRICKS( LEAD 30 K.M) |
| 16 | ADD 18% GST |
| 17 | ADD 1% Labour Cess |
| 18 | Photography and Sign board Please Enable Macros to View BoQ information |