| 1 | Brick work in following Cement Mortar using best quality Burnt Clay Brick of size 8¾“x4¼”x2¼” with class designation of 10 conforming to IS 1077-1992 for foundation and basement including Cost of Mortar Plasticizer curing, etc., complete complying with standard specification and as directed by the departmental officers. Brickwork shall be done as per IS 2212-1991 adopting English Bond generally other type of bond shall be done as directed by the Executive Engineer in charge. |
| 2 | Plastering the surface of walls with Cement Mortar 1:4 (One cement and Four plastering sand), 12mm thick in all floors including mortar plasticizer at 200ml per 50Kg of cement used, curing etc., complete complying with standard specification and as directed by the departmental officers. |
| 3 | Plain Cement Concrete 1:2:4 (one cement, two crushed stone sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing etc., complete as per standard specifications and as directed by the departmental officers. - Mixing by mechanical means |
| 4 | Paving floor with colour ceramic tiles of size 200 x 200 x 6 mm in all floors over the base layer of cement mortar 1:3 (one part of cement three part of sand) 20 mm thick pointed with white cement at 0.40 kg/m2 including finishing the joints etc complete, as directed by the departmental officers (The rate should be exclusive of cost of flooring concrete 1:5) special |
| 5 | Dadooing the walls with plain glazed tiles of 150 x 150 x 6 mm set in cement mortar 1:2 (one part of cement two part of sand) 12 mm and pointing white cement used 4kg/m2 neatly etc complete as directed. |
| 6 | Supply and fixing of RCC Precast slab in cement concrete 1:1½:3 mix (one part of cement one and a half part of sand and three part of aggregates) of thick 0.075 m using 20 mm ISS HBG metal including cost of molding charges mixing laying and curing cost and conveyance of all materials to site and all labour charges etc. complete as per standard specification but excluding cost of reinforcement. |
| 7 | Thorough Scrapping of old plasted surface. |
| 8 | Painting two coats with ready mixed plastic emulsion paints of first class quality and of approved colour over existing coat including through scraping clean removal of dirt etc, complete and including cost of necessary plaster of paris, putty, brushes, wherever required and all labour charges, scaffolding charges etc., complete as per standard specification. |
| 9 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc with two coats of best approved first quality and colour of synthetic enamel paint over the existing coat in all floors excluding cost of priming coat etc complete complying with standard specification. (The make, quality and colour of paint should be got approved by the departmental officers before use on works.) |
| 10 | Painting the new wood work or plastered surface two coats in all floors with best synthetic enamel paint of approved quality, colour and brand to be approved by departmental officer before use on works including ordinary scrapping, sand papering and preparation of surface including coat of brushes, high scaffolding charges neat finishing complying with standard specification and as directed by the departmental officers. |
| 11 | Supplying and fixing of steel door with suitable design including cost of materials, welding and conveyance of all materials to site locking arrangements and painting one coat of primer etc complete as per standard specification including fixing charges etc complete. |
| 12 | Plastering in cement mortar 1:3 mix (one part of cement and three part of sand) 20 mm thick finishing including cost and conveyance of all materials and labour charges for curing and all other incidental charges etc., complete complying with standard specification. |
| 13 | Supply and delivery of fixing of HDPE tank 1000 litres capacity as per IS 12701/1996 including loading, unloading, transportation and labour charges for fixing of GI pipes and specials for pipe connection works including cutting, threading and fixing chargers as directed by officers. |
| 14 | Supplying, delivery and fixing in position of following PVC / GI pipes and specials of approved quality and good variety excluding fixing charges etc complete. |
| 15 | 32 mm PVC pipe |
| 16 | 32 mm PVC bend |
| 17 | 25 mm PVC pipe |
| 18 | 25 mm PVC bend |
| 19 | 20 mm PVC tap |
| 20 | Supply and fixing in position best quality of approved make Wash hand basin of size 550 x 440 mm with all accessories such as cast iron brackets, including cost of 15 mm Ø brass nipple, 15 mm nylon connection etc including fixing the wash basin in the wall in position with a pair of CI brackets with TW plug and screws and giving necessary water supply connection and painting the brackets with two coats of paint over priming coat of anticorrosive paint including testing leakages etc, complete complying with standard specifications. |
| 21 | Dismantling the existing damaged machine pressed tiles with weathering course portion clearing away and carefully taking material useful for reuse for any thickness of concrete including all cost etc as per standard specification. |
| 22 | Supplying, fabricating and placing in position Mild Steel/Ribbed T or Steel reinforcement grills of all variety like HYSD/CTD/TMT and all grade like Fe500, Fe550D, Fe500D etc for all RCC works as per design given including cost of steel reinforcement and GI binding wire, wastage etc complete complying with standard specification and as directed by the departmental officers. (Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) |
| 23 | Reinforced Cement Concrete 1:1½:3 (One Cement, One and half crushed stone sand and three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including Super Plasticiser, mixing charges for machine mix,laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification. |
| 24 | Supplying, fabricating, erecting structural steel trusses work for roofing welded or bolted type using necessary mild steel rectangle and square box sections etc each according to given design conforming to IS specification. It includes cutting, welding, conveyance of all materials to work site, primer coating and enamel painting and approved by the departmental officers etc complete as per standard specification. |
| 25 | Supplying and fixing of roofing with galvaline Sheet 0.47 mm thick of approved quality by drilling hole (and not by punching) with necessary J/U bold and nut of 8 mm Ø of suitable length providing one set of bitumen washer at 25 mm Ø and 1.60 mm thick for each bold and nut including protruding portion of bold and nut shall be covered with bitumen compound etc complete complying with standard specification and as directed by Engineer incharge. Please Enable Macros to View BoQ information |