| 1 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with Tractor Mount Grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MoRTH Specification Clause 401. For Grading III Material |
| 2 | Construction of dry lean cement concrete Sub-base over a prepared sub-grade with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate note xceeding 25mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to beas pertable 600-1, cement content not to be less than 150kg/cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10M paat 7days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing. |
| 3 | Construction of un-reinforced, plain cement concrete pavement, thickness as per design, over a prepared subbase, with 43 grade cement or anyother type as per Clause 602.2.2M30 (Grade), coarse and fine aggregates conforming toI S:383, maximum size of coarse aggregate not exceeding 31.5mm, mixed in a concrete mixer of not less than 0.5cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed Side Form work (steel channel, laying and fixing of 150micron thick polythene film, wedges, steel plates including levelling the form work as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant near approaches to bridge / culvert and construction joints, admixtures as approved, curing of concrete slabs for14- days, using water finishing to line sand grade as per drawing and MoRTH Specification Clause 602 including vaccumde watering process with all required equipments (Dowel Bars will be paid seprately) |
| 4 | Part -B (Drain work) |
| 5 | Earth work in excavation by mechanical means (Hydraulic Excavator )/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter. All kinds of soils |
| 6 | CARRIAGE OF MATERIALSEarth, Sand, Lime, Morrum manure or sludge UP TO 5 KM |
| 7 | Providing and laying in position cement concrete including curing, compaction etc. complete in specified grade excluding the cost of centering and shuttering - All work up to plinth level. M10 grade Nominal Mix 1: 3: 6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size). |
| 8 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor five level. ('Original producers' who manufacture billet directly from iron ores and roll the bilets to produce steel conforming to IS:1786) Thermo-mechanically Treated bars (Conforming of relevent IS code) |
| 9 | Centering and Shuttering with plywood or steel sheets including strutting, propping bracing both ways and removal of formwork for foundation , footings, strap beam, raft , bases of columns etc. |
| 10 | Providing and laying in position specified grade of cement concrete for all RCC structural elements upto plinth level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1 cement: 3 coarse sand) and making good the joints and cost of plastizers( if required) excluding the cost of centering, shuttering and reinforcement. M20 grade Nominal Mix / Design Mix |
| 11 | Rough Chisel dressed Sand stone 35 mm thick flooring of approved shade set over 20mm thick base of cement mortar 1:6 (1 cement : 6 coarse sand) and pointing with cement sand mortar 1:3 with pigment to match the shade of stone with joint thickness up to 15 mm complete in all respects :Red sand stone (Karauli stone) |
| 12 | Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes (IS 15778 : 2007 code) having thermal stability for hot & cold water supply including all CPVC plain & brass threaded fittings i/c fixing the pipe with clamps at 1 metre spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and testing of joints complete as per direction of Engineer in Charge. (Internal work Exposed on wall) |
| 13 | 25 mm nominal size |
| 14 | P&F rigid PVC Pipe (IS:4985 mark) class II/ (4 Kg. /Cm2.) approved quality /make including joining the pipe with solvent cement rubber ring and lubricant. |
| 15 | 110 mm dia |
| 16 | Dismantling of cement concrete pavements by mechanical means using pneumatic tools breaking to pieces not exceeding 0.02 cum in volume and stock piling at designated locations and disposal of dismantled materials upto a lead of 1000 m, stacking serviceable and unserviceable materials separately Please Enable Macros to View BoQ information |