| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m All kind of soil |
| 2 | Ordinary Rock |
| 3 | Providing and laying of dry stone solling tightly hand packed. |
| 4 | Providing and laying in position cement concrete of specified grade excluding thecost of centering and shuttering - All work up to plinth level 1:2:4 (1 cement : 2 coarse sand (zone-III) derived from natural sources : 4 gradedstone aggregate 20 mm nominal size derived from natural sources) |
| 5 | Random rubble masonry with hard stone in foundation and plinth includinglevelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 gradedstone aggregate 20 mm nominal size) at plinth level with cement mortar 1:6 (1cement :6coarse sand )including carriage of materials at site of work by MT including cost of loading and stacking &H/L 500MTR |
| 6 | 12 mm cement plaster On the rough side of single or half brick wall finished with a floating coat of neat cement mix 1:4 (1cement :4 fined sand ) including cost and carriage of all material from source to site of work |
| 7 | Providing and laying in position cement concrete of specified grade excluding thecost of centering and shuttering - All work up to plinth level 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 gradedstone aggregate 20 mm nominal size derived from natural sources) |
| 8 | Steel work welded in built up sections/ framed work, including cutting, hoisting,fixing in position and applying primer coat of aproved steel primer using structural steel etc.as required in greating frames guard bar ,ladders railing bracked, gates &similar works. |
| 9 | Centering and shuttering including strutting, propping etc. and removal of formwork for foundation |
| 10 | Structural steel work in single section, fixed with connecting plate,including cutting, hoisting, fixing in position and applying coat aproved steel all completed including carriage of every materials by means of mechanical transport and had load |
| 11 | Providing and fixing G.I. chain link fabric fencing of required width in mesh size50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers completed including carriage of every materials by means of mechanical transport and had load |
| 12 | Cement coping 1:3 mixed D.P.C band 12mm nominal size |
| 13 | Providing laying and fitting of 80mm dia GI Pipe pipe conforming to IS 4984:1995 with latest amendments and conveying to work site including loading and unloading ar both destination and rolling, lowering into the tranch, laying true to line and jointing of pipes by electro fusion welding as per standard procedure and guidelines, including encasing the pipes around to a depth not less than 15cms with soft earth or selected earth available from the execvation site completed giving hydraulic test as per relevant ISI with all leads and lift including testing commissioning welding fitting .the devition /bend is to be fabricated form available g.i pipe 80mm dia the job shall be inclusive of all costs and carriage complete job as directed by engineer incharge (contractor will make own arrangement for procuring water for testing )including transportation charge from divisional store to site work . |
| 14 | Providing laying and fitting of 90mm dia HDPE pipe conforming to IS 4984:2016 with latest amendments and conveying to work site including loading and unloading ar both destination and rolling, lowering into the tranch, laying true to line and jointing of pipes by electro fusion welding as per standard procedure and guidelines, including encasing the pipes around to a depth not less than 15cms with soft earth or selected earth available from the execvation site completed giving hydraulic test as per relevant ISI with all leads and lift including testing commissioning electro fusion fitting like couplers ,tee, redcers, bends, union, end cap etc. conforming to BS EN 12201; part-3 suitable for drinking water in black/blue colour manufactured from compounded PE 100 virgin polymer and compatible with PE 80/100 pipes in pressure rating SDR11 with minimum PN 16 rate for water application and shall be inclusive of all costs and carriage, completed job as per directon by sire engineer (contractor wil make own arrangment for procuring water for testing) including transportation charges from divisional store to site work. |
| 15 | Providing laying and fitting of 75mm dia HDPE pipe conforming to IS 4984:2016 with latest amendments and conveying to work site including loading and unloading ar both destination and rolling, lowering into the tranch, laying true to line and jointing of pipes by electro fusion welding as per standard procedure and guidelines, including encasing the pipes around to a depth not less than 15cms with soft earth or selected earth available from the execvation site completed giving hydraulic test as per relevant ISI with all leads and lift including testing commissioning electro fusion fitting like couplers ,tee, redcers, bends, union, end cap etc. conforming to BS EN 12201; part-3 suitable for drinking water in black/blue colour manufactured from compounded PE 100 virgin polymer and compatible with PE 80/100 pipes in pressure rating SDR11 with minimum PN 16 rate for water application and shall be inclusive of all costs and carriage, completed job as per directon by sire engineer (contractor wil make own arrangment for procuring water for testing)including transportation charge from divisional store site work 90mm Gate valve |
| 16 | 90mm Gate Valve |
| 17 | Filling available excavation earth (excluding rock) in trenches plinth sides of foundation etc. layer not exceeding 20mtr in depth.Consolidation each deposite layers by remaining waking, lead upto50mm & lift upto 1.50m. |
| 18 | Providing , supply & fitting of electro fusion fitting in accordance with BS EN12201: PART-3 suitable for drinking water with in black/blue colour manufacturung from compounded PE80/PE100 pipes , in pressure rating SDR11 with minium PN 12.5 rated for water applicatin and shall be inclusive of all cost such as testing, inspection charges transportation upto, transit insurance loading. |
| 19 | 75mm bal valve |
| 20 | 90 Degree of 90mm dia |
| 21 | Providing and fixing 3 layer PP-R (Poly propylene Random copolymer) pipes SDR7.4 U V stabilized & anti - microbial fusion welded, having thermal stability for hot& cold water supply including all PP-R plain & brass threaded polypropylenerandom fittings i/c trenching .refilling & testing of joints complete as per directionof Engineer in Charge. (External work 40mm dia PN -16 |
| 22 | 25MM DIA PN -16 |
| 23 | Providing and fixing PPR union 25mm dia |
| 24 | 40mm dia |
| 25 | Design, Supply and installation testing and commissioning of 10-15HP dual solar submersible pump, (Grundfos or equivalent parameter specification and Properties) discharge of 5 LPS and hgead of 96Mtr .Nominal operating cell temperature (NOCT : 45+/- 20 C), Temperature Co-efficient at NOCT (-0.286 to 0- 4), Maximium power at NOCT, Maximium power at STC, Performance Ration (79% to 82%),Module Efficiency (21 or more), Required system peak output power (with module orientation-south ) 400Wp or above, Capacity per module, Type of Module (Nano perc) Nmber of cels in each module (as per provide)., Certification Standards (Compliance as per specifications), Number of modules (as per provider), IP rating for Module (IP 67), Weight (Kg) and size (LXHXWmm) of each module (as per provider), IP rating for VFD and DB (IP 54 with additional encloseure/ IP 65), Solar Cell Material (Mono perc), Percentage of depreciaition in performance (as per provder), Minimum ower generation )(____)KWh/sq.M/Dy, Product Warranty (Vendor to declare), PV Module (Minimum 12 years), VFD (minimum 2 Years), Installation Warranty (minimum 2 years), System Performance guarantee (minimum till break even) RIO/ Beak even (Years),TCO in INR (20 Years) (Indicate \\"-ve\\" for benefits), DP (Years), Note: Vendor shall be responsible for solar power generation, Solar PV modules, Stainless steel solar submersible pump and motor, Motor controller, GI Mounting structure set, DC cable as persite requirement, Cable AC as per site requirement, Safety rope as per diameter of pump, Chain pulley of 1 ton capacity. The job also include any other Civil/ Mech. item required to make the system functional |
| 26 | Transportation of boreing equipment , machine tools to the new site of bore well fixing of complete camp by way of erection of equipments tools , accessorries, attachment fixing of tent for labor and stacking of material at bore well site . The job included leveling of ground ,drilling machine and other charges on account of POL etc. For 1st shifting of boring machine and equipment. |
| 27 | Drilling of bore hole with 225mm dia bit using ODEX method of drilling as per site condition conglomerate, boulders pebbels, clay etc including cost of M.S casing pipe consumable store , drilling bits POL etc, with the system of simultaneously lowering of 200 mm dia ID M.S casing pipe required thickness which shall be welded together. |
| 28 | Providing and fixing of suitable shoe 200 mm dia having adequate thickness |
| 29 | Development of bore well with compressor till sand free water is available and suitable strata in establish. |
| 30 | Providing and fixing of water tap Please Enable Macros to View BoQ information |