| 1 | Working charges |
| 2 | 100.1.1:Excavating trenches of required width for pipes, cables, etc., including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering, etc., and disposing of surplus excavated soil as directed, within a lead of 50m, in all kinds of soil. |
| 3 | 100.59.1:Cutting the bituminous / concrete roads with cutting machine for a minimum depth of 200mm along the sides of proposed alignment of the pipe to be laid without causing any damage to other utilities, including the charges for hire and conveyance of tools and plant, cost of consumables and charges for lighting, watching, ribbon fencing, caution boards, traffic diversion, and as per the direction of departmental officers etc. complete, before carrying out the demolition of bituminous / concrete road by mechanical means and carrying out the excavation. |
| 4 | 15.43.2:Dismantling manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in-Charge:Bituminous road |
| 5 | 100.8.1:Fencing one side of trenches, 1.50m height with two rows of 10cm plastic caution tape in vertical casuarina pole (girth 15cm to 24cm) fixed at 2m intervals. |
| 6 | 100.9.8:Laying uPVC pipes of class 2 to class 6 and specials, lowering to the trenches already made, placing in position aligning the pipeline to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipeline with water to the required test pressure (excluding cost of pipes and specials): 90 mm nominal outside diameter pipes. |
| 7 | OD167962/2022-2023:Supply and laying 20 mm ASTM UPVC pipes and specials, lowering to the trenches already made, placing in position aligning the pipe line to the lines and levels and jointing the pipes and specials with solvent cement and testing the pipe line with water to the required test pressure. |
| 8 | OD167986/2022-2023:Taking connection from existing line of size 50 mm to 110 mm using PVC specials for street tap and service connnection including all earth work excavation, refiling trench, cost of specials for tap connection |
| 9 | 100.60.18.2:Repair work for 1m to 2m length in 20mm (3/4 inch) house connections, using 25mm PE Pipe, PE80, PN16, Conforming to IS 4984: 2016 or later edition and PP PN 16 Compression specials, including trenching and refilling in all kinds of soil, hire for tools, cost of consumables and labour charges, cost of materials, including charges for lighting, watching, providing caution boards, traffic control etc. complete, but excluding the cost of cutting of concrete / tarred / bituminous roads and as per the directions of the department officers. |
| 10 | 100.60.3.1.1:Providing additional length of house connection pipe using 20mm Indian Standard Class 6 uPVC pipe and specials and testing the joints etc., by trenching and refilling in all kinds of soil with trench of average cross section 0.3m x 0.75m for laying of connection pipe and service pipe, lighting, watching, providing caution boards, traffic control etc., including cost of materials, hire for tools, cost of consumables and labour charges etc. complete, but excluding the cost of cutting of concrete / tarred / bituminous roads etc., and as per the directions of the department officers |
| 11 | Cost of Materials |
| 12 | 100.98.213:Supply of PVC Pipe, 6kg/cm2, 90mm Dia. |
| 13 | OD167950/2022-2023:Cost of Specials 3% Please Enable Macros to View BoQ information |