| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum |
| 2 | Supplying and filling in foundation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. |
| 3 | Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers. -Mixing by manual means |
| 4 | Brick work in CM 1:5 (one cement & Five Crushed Stone Sand (M- Sand)) using II class ground moulded bricks of size 9\\" X 43/8\\"X 2 3/4\\" including finishing, curing, etc., complete complying with standard specification - 100CFT |
| 5 | Painting two coats with Ready Mixed Enamel Paint over the new iron works of approved quality and colour without priming coat including the cost all materials etc.,complete, in all floors. |
| 6 | Plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)) 12mm, thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications |
| 7 | Painting New Plastered Wall Surface with Two finishing coats of ready mixed (Emulsion) of approved quality and colour over one coat priming coat in all floors including the cost of primer etc., complete complying with standard specification and as directed by the departmental officers.(The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) |
| 8 | Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. |
| 9 | Supplying and laying of Interlocking Paver Block Stone 63mm thick Over a base layer of crushed stone sandfilling incl. Cost of materials laying and Labour charges etc complete complying with the standard specification and as directed by the departmental officers. |
| 10 | Repair and Refixing of Play material including Materials , welding , Painting and Labour cost for refixing etc complete Please Enable Macros to View BoQ information |