| 1 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil : |
| 2 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size) |
| 3 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 4 | landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering, finishing and reinforcement with 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 6 | Cement concrete flooring 1:2:4 (1cement: 2 coarse sand: 4 graded stone aggregate) finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. complete. 50 mm thick with 20mm nominal size stone aggregate. |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns etc. for mass concrete. |
| 8 | Dismantling old plaster or skirting, raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 meters lead. |
| 9 | 12mm Cement plaster of mix: 1 : 6 ( 1 cement : 6 coarse sand) |
| 10 | 15mm Cement plaster on the rough side of single or half brick wall of 1 : 6 ( 1 cement : 6 coarse sand) |
| 11 | Excavating, supplying and filling of local earth (including royalty)by mechanical transport upto a lead of 5 km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete |
| 12 | Demolishing mud phaska in terracing and disposal of material within 50 meters lead |
| 13 | Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade on New work (two or more coats) over and including priming coat with water thinnable cement primer |
| 14 | Finishing walls with water proofing cement paint of required shade: Old work (one or more coats applied @ 2.20 kg/10sqm) over priming coat of primer applied @ 0.80 liters/10sqm complete including cost of priming coat. |
| 15 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade. Two or more coats on new work |
| 16 | Distempering with 1st quality Acrylic/oil bound washable distemper (ready-made) having VOC content less than 50 grams/litre of approved manufacturer and of required shade and colour complete as per manufacturers’ specifications, one or more coats on old work |
| 17 | Removing white or colour wash by scrapping and sand papering and preparing the surface smooth including necessary repairs to scratches etc. Complete |
| 18 | Providing and fixing Ist quality ceramic glazed wall tiles conforming to IS : 15622 (thickness to be specified by the manufacturer), of approved make, in all colours, shades except burgundy, bottle green, black of any size as approved by Engineer- in-Charge, in skirting, risers of steps and dados over 12 mm thick bed of cement mortar 1:3 ( 1 cement : 3 coarse sand) and jointing with grey cement slurry @ 3.3 kg per sqm, including pointing in white cement mixed with pigment of matching shade complete. |
| 19 | Engaging of welders for various works at site as directed by engineer-in-charge. |
| 20 | Engaging of Labours for clearance of site as directed by engineer-in-charge. |
| 21 | Carriage of sand avg distance 3.0 Km by MT |
| 22 | Carriage of aggregate above 40 mm avg distance 3.0 Km by MT Please Enable Macros to View BoQ information |