| 1 | Earth Work in ordinary soil within 50met. Initial lead and 1.5met. Initial lift including rough dressing and levelling the bed including all labour T&P etc. complete as directed by the Engineer - in Charge. |
| 2 | Filling in foundation and plinth with sand well watered,rammed etc including all cost conveyance roalty ,labour and T&P etc. complete as directed by the Engineer - in Charge. |
| 3 | Cement concrete (1:3:6) using: 4cm size hard granite hand broken metal with all cost conveyance,royalty,taxes etc all complete. |
| 4 | R.C.C. Work with M-20 using 20 mm & down grade HGCB Stone chips incluiding hoisting, laying,curing etc. complete but excluiding cost of steel reinforcement. |
| 5 | Supplying , fitting , fixing & placing uncoating bar reinforcement complete as per drawing & technical specification complete. |
| 6 | Rigid and smooth centring,shuttering for RCC works including false work and dismantling them after casting including cost of materials complete. |
| 7 | Supplying all labour T&P material for 1st ClassFly Ash Bricks in CM (1:6) in foundation and plinth |
| 8 | 12mm thk Cement Plaster in CM (1:6) incl all cost |
| 9 | Painting 2coat plastic emulsion paint over 1 coat primer of approved shade incla ll cost |
| 10 | Supplying & fixing of M.S. Grill for Door and window incl all cost |
| 11 | Supplying, fitting & fixing of two track UPVC sliding Window of approved make with 6mm thk glass of approved quality with all frame fitting etc complete |
| 12 | Supplying, fitting & fixing of two track openable UPVC door with door frame of approved make with 6mm thk glass of approved quality with all frame fitting etc complete |
| 13 | Fixing tiles in floors treads or steps and landing on 25mm thick bed of cement mortar 1:1 (1cement : 1sand) jointed with neat cement slury mixed with pigment tiles including cost of vitrified tiles |
| 14 | Fixing tiles in dados skirting and risers of steps on 12mm thick cement plaster (1:3) jointed with neat cement slurry mixed with pigments to match the shade of the tiles including cost of vitrified tiles. |
| 15 | Providing and Fixing of 80mm thk Paver Block |
| 16 | Provision for PH and Electrification |
| 17 | Provision for Display board and photography Please Enable Macros to View BoQ information |