| 1 | Supplying all labour T&P,for earth work in all kinds of soil within 50 mtr initial lead and 1.5 mtr initial lift including dressing and leveling the bed and site and breaking the clouds to maximum 5 cm to 7 cm and laying in layers not exceed 0.30 mtr. In depth and as per the direction of Engineer- in-charge. |
| 2 | Supplying all labour,T&P, for laying in trenches High Density Polythene pipes and specials of following outsisde diameter and class 1 to 3 jointing by fusion welding method including testing as per specification confirming to IS: 4984-1995 with ISI marked specials & fittings & testing as per specification etc. complete as per the direction of Engineer-in-Charge. ( pipes are to be supplied by contractor with pre & post delivery inspection certificate from CIPET and manufacturing test certificate from the manufacturer). |
| 3 | 110 mm HDPE Pipe Grade PE 80 PN 6.0 |
| 4 | 90 mm HDPE Pipe Grade PE 80 PN 6.0 |
| 5 | Supplying all labour T & P and refilling the trenches with excavated materials including watering and ramming etc. all complete as per the direction of Engineer-in-Charge. |
| 6 | Supplying all materials, labour,T&P and laying of G.I pipes of required sizes and length including earth work in pipe line trenches in all kinds of soil and refilling of the pipe line trenchs with the excavated materials and aligning the pipeline as per the site requirement and making ARC welding at the site painting both side of pipe with anticorosive paint over a coat of primer with all complete etc as per direction of Engineering-in-charge(G.I pipe shall be of BIS specification and TATA/Jindal or any other reputed make) thicknes of pipes. |
| 7 | 80 mm dia G.I Pipe |
| 8 | 80 mm dia G.I Bend |
| 9 | 80 mm dia G.I Flange |
| 10 | Supplying all materials, labour,T&P for fitting and fixing of Nut bolt of different size. |
| 11 | Supplying all materials, labour,T&P for fitting and fixing of rubber insertion. |
| 12 | Supplying all labour T&P & materials for House Connection for 85LPCD projects for new connections to the house hold premises with provision of concrete stand post, GI pipe, & fittings etc complete in all respect as per direction of Engineer-in-Charge.(on the side of ferrule) |
| 13 | Supplying all labour T&P & materials for House Connection opposite to ferruel side (after road crossings) for 70LPCD projects for new connections to the house hold premises with provision of concrete stand post, GI pipe, & fittings etc complete in all respect as per direction of Engineer-in-Charge |
| 14 | Supplying all labour, T&P & materials for fitting & fixing of HDPE pipe of 20mm dia size of maximum 6 mtr length on ferruel side for 135 nos of connection and maximum 12 mtr length on opposite of ferruel side for 90 nos of connection to accomodation the shifting of FHTC to suitable place inside the premises of the beneficiary complete in all respect etc. as per direciton of Engineer-in-charge. |
| 15 | Supplying of all labour,T&P,materials for cutting CC roads cutting for taking pipelines all. complete as per direction of the Engineer in charge. |
| 16 | Supplying of all labour,T&P,materials for making good to the damages of C.C Road in C.C (1:2:4) all. complete as per direction of the Engineer in charge Please Enable Macros to View BoQ information |