| 1 | CIVIL WORKConstruction of Pump House- Cum-Chloronome of size 3.60 x 3.0 M x 3.0 & 1.80 x 1.20 x 3.0 M including supply of all materials, labour, T&P etc. required for proper completion of work prior approval of design & drawing. |
| 2 | OHTConstruction of OHT(200KL/20M Staging) inluding all Supply all materials, labours and t&p etc. required at the site of work and construct R.C.C. over head tank above mentioned capacity and staging including the cost of construction of following appurtenant works. 1m wide R.C.C. balcony alround the tank, 1m wide R.C.C. stair case from ground upto the balcony of the tank, Lightening conductor as per Indian electricity rules., Water level indicator as per deptt. specification20 mm. G.I. pipe railing with 50 x 50 x 6 mm. 1.2 m. high angle iron posts1.5 m. c/c on both sides of the stair case (pipe in 3 rows) and balcony (pipe in 3 rows) 50cm. wide M.S. ladder with 50x50x6 angle iron and 20 mm. rungs at 25 cm. c/c/, from balcony to the top dome of the tank and from there to the bottom dome of the tank inside it. 60x60 cm. M.S. manhole cover (light pattern)with locking device. Supply, erection, fixing in position and jointing of following D.I.D/F pipes with sluice valves and specials, ISI marked D.I.D/F pipes, K-9 class 'A' as per IS-1537/1960, Inlet- 200 mm, Outlet- 200 mm, Over flow - 250 mm, Washout - 100 mm. ISI marked C.I.D/F sluice valves as per IS- 780/1969, Outlet- as per distribution dia - 1 No. Washout - 100 mm - 1 No, ISI marked C.I.D/F specials as per IS 1538, Clamping the vertical pipes with columns by clamps of 50 x 6mm. M.S. flat 1.5m c/c/ including the cost of all jointing materials such as nut bolts and washers etc. Weather proof painting on outer surfaces of R.C.C. work with ISI marked cement paint in 3 coats. Painting of M.S. ladder, railing and vertical pipes with ISI marked enamel paint in 3 coats. Floor and apron at the ground level upto 15cm. beyond the entire projected area of the O.H.T. with 25mm. 1:2:4 P.C.C. over 75 mm., P.C.C. 1:4:8 as per deptt. specifications. Sluice valve chambers - 2 Nos. (As per type design) Testing of tank for water tightness etc. for propoer completion of the work. Apex painting over exposed part of OHT with 2 coats of approved apex paint over priming coat complete. Site. clearance |
| 3 | RISING MAINSupply of ISI mark DI K-9 pipes (push on joints) of following class and diameters inclusive of jointing material (Rubber gasket of EPDM Quality, Bend, Tee etc.) including all statutary duties work, unloading, stacking etc. complete as directed by Engineer –in-charge.200 mm DI K-9 |
| 4 | Supply of DI specials as per conformation to I.S.S.suitable for above DI pipes F.O.R.destimation including all taxes and insurance (10% amount of item No-3) |
| 5 | Excavation of earth in ordinary soil (loam, clay or sand) for pipe line and rising main trenches including lift upto 1.50 m and lead upto 50 m and refilling watering, ramming of the excavated earth into the trench and also disposal of surplus earth upto 50m from the center of the trenches including supply of all material labour, T&P etc complete as per instructions of Engineer ‐in ‐charge.Ordinary soil0.00-1.5 m |
| 6 | Carting from store (upto 8 Km.or within municipal limit which is more)following sizes of D.I.pipes,specials fittings etc.to the site of work. Lowering the same into trenches and laying to true alignment and gradient including testing of pipelines,cutting of pipes for making joints. |
| 7 | Supplying the following dia DI butterfly /sluice valves,class I,working pressure 10Kg/cm2 confirming to IS:780/1969 or its latest amendments, including valve fittings & Dismantling Joints as per requirement F.O.R. destination and lowering them into the already prepared trenches, complete and also including supply of jointing materials etc.complete.including all taxes and insurance,as per instructions of Engineer -in -charge.200 mm dia |
| 8 | Supply of all materials, labour,T&P etc.and construction of sluice valve /scour valve chamber as per type design. |
| 9 | Provision of construction of RCC thrust block of grade M-20 for water hammer at bends of pipe. |
| 10 | Distribution systemSupply of ISI mark DI K-7 pipes (push on joints) of following class and diameters inclusive of jointing material (Rubber gasket of EPDM Quality, Bend, Tee etc.) including all statutary duties work, unloading, stacking etc. complete as directed by Engineer –in-charge.200 mm dia k-7 |
| 11 | Supply of DI specials as per conformation to I.S.S.suitable for above DI pipes F.O.R.destimation including all taxes and insurance (10% amount of item No-10) |
| 12 | Excavation of earth in ordinary soil (loam, clay or sand) for pipe line and rising main trenches including lift upto 1.50 m and lead upto 50 m and refilling watering, ramming of the excavated earth into the trench and also disposal of surplus earth upto 50m from the center of the trenches including supply of all material labour, T&P etc complete as per instructions of Engineer ‐in ‐charge. |
| 13 | Carting from store (upto 8 Km.or within municipal limit which is more)following sizes of D.I.pipes,specials fittings etc.to the site of work. Lowering the same into trenches and laying to true alignment and gradient including testing of pipelines,cutting of pipes for making joints. |
| 14 | Supplying the following dia DI butterfly /sluice valves,class I,working pressure 10Kg/cm2 confirming to IS:780/1969 or its latest amendments, including valve fittings & Dismantling Joints as per requirement F.O.R. destination and lowering them into the already prepared trenches, complete and also including supply of jointing materials etc.complete.including all taxes and insurance,as per instructions of Engineer -in -charge.200 mm dia |
| 15 | Supply of all materials, labour,T&P etc.and construction of sluice valve /scour valve chamber as per type design. |
| 16 | Jointing the existing line into the main line complete including supply of materials required for completion of work as per direction of engineer-in charge. |
| 17 | Tube-wellsDrilling of Borehole for Tubewell construction by DC/RC Rig Machine including transportation, erection, dismantling of Rig and assosiated T&P complete in all respect including requried all material, labour etc. Logging of bore hole by departmental/Approved electric logger.Zone Testing in water quality problem areas including all required material, labour, T&P etc. complete in all respect.cement Sealing of Contaminated accufer/Zone including all required material, labour, T&P etc. complete in all respect.Supply & Lowering of 90 mm dia UPVC gravel feed pipe in both side of T.W. assembly. M.S. tubewell assembly with all required parts like plain, slotted pipe (as required upto 50% of plain pipes) rings, well cap, bail plug, clamp, reducer, central guide, support structure etc. as required & per typed design complete in all respect. As per IS- 4270.Lowering of Tube Well assembly duly welded including welding electrode and shrouding of pea Gravel complete in all respect. Pea Gravel.Transportation, Installation Dismantling of 350 PSI Compressor. Transportation, Erection Dismantling of 3 Cusec OP Unit and Yield test. Chemical and Bacteriological Test of water sample from departmental/ approved Lab. Barricading around the pit to prevent any posible Accident |
| 18 | SITC of Pumping plant including starter, control Panal, cable, complete in all respect with all required material T&P labour etc.Clear water submersible pump complete with electric motor capable to operate on 380/420 volts 3 phase 50 c/s A.C. for 1200 LPM. 56 Mtr. Head and 30 H.P.(i) Interior Switch fuse unit of 100 amp.(ii)Voltmeter 0-600 Volt range with seiector switch.(iii) Ammeter 0-100 amp. Range with seiector switch(iv) KWI meter for 30 H.P.(v) Power factor meter(vi) Frequency meter(vii) Single phase preventer(viii) Power capacitor of suitable capacity.(ix) Phase indicting lamps with toggle switch.(x) Instrument fuses of 6 amp capacity. SITC of Main Piping & Valves with 24 mtr. Column pipe, Power wiring, earthing, printing, Tools sets, wiring of pump house (internal & External) Chain Pulley block and gauges complete in all respect with all required material , T&P labour.three months trial & run including chlorination T& P required . Please Enable Macros to View BoQ information |