| 1 | Supply and erection of follwing material |
| 2 | 11 KV fuse set |
| 3 | Bolt & nut for shackel |
| 4 | MS Guarding angle |
| 5 | G. I. wire 6 /8/10 Swg |
| 6 | Clamp with nut bolt |
| 7 | LT clamp with nut and bolt |
| 8 | LT Fuse Set (upto 100KVA) |
| 9 | LT shackel insulator |
| 10 | Safe loading Carriage & unloading of following material from store centre to pit site/JE dump store approx 35 Km. |
| 11 | PCC Pole 11 Mtr Long |
| 12 | PCC Pole 8.5 Mtr Long |
| 13 | 11 kv metering cubial unit |
| 14 | CT/PT pole unit |
| 15 | 11 KV F bracket |
| 16 | 11 KV polymeric 'Disc Insulator |
| 17 | 11 KV Polymeric pin Insulator with nut |
| 18 | 11 KV V type X-arm MS Angle 65x65x6 mm with Clamp |
| 19 | 11kv Dropper Channel |
| 20 | 11kv T-off Channel |
| 21 | 11kv Top Channel |
| 22 | MS Earthing Complete 20mm |
| 23 | ACSR Rabbit Conductor |
| 24 | ACSR Waeasel |
| 25 | Stay Set Complete |
| 26 | Transformer 100 KVA |
| 27 | Transformer 25 KVA |
| 28 | Transformer 63 KVA |
| 29 | I/D cable termination box 3x185/3x120 sqmm |
| 30 | O/D cable termination box 3x185/3x120 sqmm |
| 31 | 11 KV XLPE cable 3x185/3x120 sqmm |
| 32 | AB conductor 3x120 |
| 33 | AB conductor 3x95 |
| 34 | AB conductor 3x50 |
| 35 | AB conductor 1x16 |
| 36 | Erection & Stringing and Sagging of 11 KV & LT line |
| 37 | Erection of PCC 8.5 mtr long Single pole with all accessories(All neccessary item like clamp, Nut bolt, Top channel, Dropper channel, Base angle, etc. will be provided by the contractor at his own cost) |
| 38 | Erection of PCC 8.5 mtr long Double Pole with all accessories(All neccessary item like clamp, Nut bolt, Top channel, Dropper channel, Base angle, etc. will be provided by the contractor at his own cost) |
| 39 | Erection of PCC single pole 11 mtr. Long all necessary accessories ( All neccesary item like clamp, Nut bolt etc. will be provided by the contractor at his own cost). |
| 40 | INSTALLATION OF PILFER METERING CUBICAL OR METERING WITH ALL CONNECTION AND ACCESSORIES |
| 41 | Mounting of 100 KV T/F form dump place to newly constructed Double pole/Plinth & its commissioning including jumepring with all system ((All the required material for above job shall be provided by contractor except T/F) |
| 42 | Mounting of 25 KV T/F form dump place to newly constructed Double pole & its commissioning including jumepring with all system ((All the required material for above job shall be provided by contractor except T/F) |
| 43 | Mounting of 63 KV T/F form dump place to newly constructed Double pole & its commissioning including jumepring with all system ((All the required material for above job shall be provided by contractor except T/F) |
| 44 | ACSR Rabbit Conductor stringing sagging binding and jumpering with all accessories |
| 45 | ACSR Waeasel stringing sagging binding and jumpering with all accessories |
| 46 | Hoisting of 11 kv XLPE (3x120/3x 185 )sq.mm with the provision of G.I. Pipe of size 150 mm dia. |
| 47 | Grouting of Pole in deep 1/6 the length of Pole in ratio 1:4:6 in cement sand & bla ST |
| 48 | Erection of PCC Double pole 11 mtr. Long all necessary accessories ( All neccesary item like clamp, Nut bolt etc. will be provided by the contractor at his own cost). |
| 49 | Grouting and Nozzling of 11 KV / 33 kv stayset complete including fixing of necessary clamps. Accessories required including its grouting by civil material (sand, brick blast & cement). All material except stay wire shall be supplied by the contractor. |
| 50 | Ordinary earthing by 11 KV MS earth Rod 2500 mm long as per RESPO schedule. All material except earthing rod shall be supplied by the contractor. |
| 51 | CHEMICAL EARTHING WITH PROPER CONNECTION FROM NUT BOLT AND STRIP |
| 52 | Laying of 11KV XLPE single cable 3x185/3x120 sq mm in HDPE pipe by drill method. (All material including HDPE pipe 150 mm dia PN- 6PE-100 shall be provided by the contractor. Only cable will be provided by the department.) |
| 53 | Installation of 11 kv O/D cable box (3x185/3x120). All material shall be supplied by the Department. |
| 54 | Installation of 11 kv I/D cable box (3x185/3x120). All material shall be supplied by the Department. |
| 55 | Stringing & Sagging ABC (3X95+1X35+1X16)Sqmm |
| 56 | Stringing & Sagging ABC (3X50+1X35+1X16)Sqmm |
| 57 | Stringing & Sagging ABC (1x25+1X16)Sqmm |
| 58 | Stringing & Sagging ABC (3X120+1X95+1X16 Sqmm) Please Enable Macros to View BoQ information |