| 1 | Short Text : Blinding & deblinding: Hydrogen 1'' #600 Long Text : Blinding & deblinding activity of hydrocarbon feed line for hydrogen service, size 1\\"#600 of Reactor, RB-400: Loosening of stud bolts, opening of flanges, insertion/removal of tail blind or repositioning of spectacle blind, replacement of flange gaskets, box up and tightnening of stud bolts etc. | Short Text : Blinding & deblinding: Hydrogen 1'' #600 Long Text : Blinding & deblinding activity of hydrocarbon feed line for hydrogen service, size 1\\"#600 of Reactor, RB-400: Loosening of stud bolts, opening of flanges, insertion/removal of tail blind or repositioning of spectacle blind, replacement of flange gaskets, box up and tightnening of stud bolts etc. |
| 2 | Short Text : Blinding & deblinding: Pentane 2'' #300 Long Text : Blinding & deblinding activity of hydrocarbon feed line, Pentane, Size 2\\" #300, of Reactor,RB-400: Loosening of stud bolts, opening of flanges<(>,<)> insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc. | Short Text : Blinding & deblinding: Pentane 2'' #300 Long Text : Blinding & deblinding activity of hydrocarbon feed line, Pentane, Size 2\\" #300, of Reactor,RB-400: Loosening of stud bolts, opening of flanges<(>,<)> insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc. |
| 3 | Short Text : Blinding & deblinding: Butene 4'' #300 Long Text : Blinding & deblinding activity of hydrocarbon feed line, Butane, Size 4\\" #300, of Reactor<(>,<)> RB-400: Loosening of stud bolts, opening of flanges<(>,<)> insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc.# # | Short Text : Blinding & deblinding: Butene 4'' #300 Long Text : Blinding & deblinding activity of hydrocarbon feed line, Butane, Size 4\\" #300, of Reactor<(>,<)> RB-400: Loosening of stud bolts, opening of flanges<(>,<)> insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc.# # |
| 4 | Short Text : Blinding & deblinding: Ethylene 8'' #600 Long Text : Blinding & deblinding activity of hydrocarbon feed line, Ethylene<(>,<)> Size 8\\" #600; of Reactor, RB-400: Loosening of stud bolts<(>,<)> opening of flanges,insertion/removal of tail blind or repositioning of spectacle blind,replacement of flange gaskets, box up and tightening of stud bolts etc.# # | Short Text : Blinding & deblinding: Ethylene 8'' #600 Long Text : Blinding & deblinding activity of hydrocarbon feed line, Ethylene<(>,<)> Size 8\\" #600; of Reactor, RB-400: Loosening of stud bolts<(>,<)> opening of flanges,insertion/removal of tail blind or repositioning of spectacle blind,replacement of flange gaskets, box up and tightening of stud bolts etc.# # |
| 5 | Short Text : Blinding & deblinding:Nitrogen 3''#300 Long Text : Blinding & deblinding activity of hydrocarbon feed lines, Nitrogen,Size 3\\" #300; of Reactor, RB-400:Loosening of stud bolts<(>,<)> opening of flanges,insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc.# # | Short Text : Blinding & deblinding:Nitrogen 3''#300 Long Text : Blinding & deblinding activity of hydrocarbon feed lines, Nitrogen,Size 3\\" #300; of Reactor, RB-400:Loosening of stud bolts<(>,<)> opening of flanges,insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc.# # |
| 6 | Short Text : Blinding & deblinding: Silencer 6\\"#300 Long Text : Blinding & deblinding activity of Reactor silencer pipeline<(>,<)> flange size 6'' #300 of Reactor, RB-400:Loosening of stud bolts<(>,<)> opening of flanges<(>,<)> insertion/removal of tail blind or repositioning of spectacle blind,replacement of flange gaskets, box up and tightening of stud bolts etc.# # | Short Text : Blinding & deblinding: Silencer 6\\"#300 Long Text : Blinding & deblinding activity of Reactor silencer pipeline<(>,<)> flange size 6'' #300 of Reactor, RB-400:Loosening of stud bolts<(>,<)> opening of flanges<(>,<)> insertion/removal of tail blind or repositioning of spectacle blind,replacement of flange gaskets, box up and tightening of stud bolts etc.# # |
| 7 | Short Text : Blinding & deblinding:36''#300 I/L & O/L Long Text : Blinding & deblinding activity of hydrocarbon inlet & outlet lines of Reactor, RB-400, Size 36\\"#300: Loosening of stud bolts, opening of flanges,insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc.# # | Short Text : Blinding & deblinding:36''#300 I/L & O/L Long Text : Blinding & deblinding activity of hydrocarbon inlet & outlet lines of Reactor, RB-400, Size 36\\"#300: Loosening of stud bolts, opening of flanges,insertion/removal of tail blind or repositioning of spectacle blind<(>,<)> replacement of flange gaskets, box up and tightening of stud bolts etc.# # |
| 8 | Short Text : Manhole opening/boxup: Flng size24\\" #300 Long Text : Reactor manhole opening/box up, Size24\\"#300: Loosening <(>&<)> removal of stud bolts,opening of manhole (with dead weight) flange ,replacement of flange gaskets, box up and tightening of stud bolts etc. (provision of davit arm available)# Max. weight 256Kg# # | Short Text : Manhole opening/boxup: Flng size24\\" #300 Long Text : Reactor manhole opening/box up, Size24\\"#300: Loosening <(>&<)> removal of stud bolts,opening of manhole (with dead weight) flange ,replacement of flange gaskets, box up and tightening of stud bolts etc. (provision of davit arm available)# Max. weight 256Kg# # |
| 9 | Short Text : Manhole opening/boxup: Flng size48\\"#300 Long Text : Reactor manhole opening/box up, Size 48\\"#300 class: Loosening <(>&<)> removal of stud bolts,opening of manhole (with dead weight) flange ,replacement of flange gaskets, box up and tightening of stud bolts etc. (provision of davit arm available) Max. weight 127kg## # | Short Text : Manhole opening/boxup: Flng size48\\"#300 Long Text : Reactor manhole opening/box up, Size 48\\"#300 class: Loosening <(>&<)> removal of stud bolts,opening of manhole (with dead weight) flange ,replacement of flange gaskets, box up and tightening of stud bolts etc. (provision of davit arm available) Max. weight 127kg## # |
| 10 | Short Text : Dropping/boxup,Liquid injection nozzle Long Text : Reactor liquid injection nozzle dropping/box up<(>,<)> Size 4\\" #300: & 6\\"#300 Loosening & removal of stud bolts<(>,<)> dropping of component<(> ,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc. Equipment weight 430kg# # | Short Text : Dropping/boxup,Liquid injection nozzle Long Text : Reactor liquid injection nozzle dropping/box up<(>,<)> Size 4\\" #300: & 6\\"#300 Loosening & removal of stud bolts<(>,<)> dropping of component<(> ,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc. Equipment weight 430kg# # |
| 11 | Short Text : Dropping/boxup,Catalyst injection nozzle Long Text : Reactor catalyst injection nozzle dropping/box up, 4\\" #300: Loosening <(>&<)> removal of stud bolts<(>,<)> dropping of component<(>,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc. Equipment weight 53kg # # | Short Text : Dropping/boxup,Catalyst injection nozzle Long Text : Reactor catalyst injection nozzle dropping/box up, 4\\" #300: Loosening <(>&<)> removal of stud bolts<(>,<)> dropping of component<(>,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc. Equipment weight 53kg # # |
| 12 | Short Text : Dropping/boxup,TEAL LG injection nozzle Long Text : Reactor Loop gas plus TEAL injection nozzle dropping/box up, 10\\" #300: Loosening <(>&<)> removal of stud bolts,dropping of component<(> ,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # | Short Text : Dropping/boxup,TEAL LG injection nozzle Long Text : Reactor Loop gas plus TEAL injection nozzle dropping/box up, 10\\" #300: Loosening <(>&<)> removal of stud bolts,dropping of component<(> ,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # |
| 13 | Short Text : Dropping/boxup,DMW injection nozzle Long Text : Reactor DM water injection nozzle dropping/box up, 0.5\\" #300: Loosening <(>&<)> removal of stud bolts<(>,<)> dropping of component<(>,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # | Short Text : Dropping/boxup,DMW injection nozzle Long Text : Reactor DM water injection nozzle dropping/box up, 0.5\\" #300: Loosening <(>&<)> removal of stud bolts<(>,<)> dropping of component<(>,<)> replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # |
| 14 | Short Text : Dismantling/boxup of Reactor Gas cyclone Long Text : Reactor gas cyclone<(>,<)> 117-GJ-400A/B opening/boxup Flange ID 850mm Equipment weight 3.6 Ton Loosening <(>&<)> removal of stud bolts ,dismantling of cone portion from hinged joint, replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # | Short Text : Dismantling/boxup of Reactor Gas cyclone Long Text : Reactor gas cyclone<(>,<)> 117-GJ-400A/B opening/boxup Flange ID 850mm Equipment weight 3.6 Ton Loosening <(>&<)> removal of stud bolts ,dismantling of cone portion from hinged joint, replacement of flange gaskets, lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # |
| 15 | Short Text : Dropping/boxup,Reactor fines ejectors Long Text : Reactor fines ejector,117-JA-400A/B dropping/box up Equipment weight 776 kg.Nozzle list: a. Size: 6\\"300#, Tightening torque 160 N.m b. 4\\" 1500#,Tightening torque 500N.m c. 6\\" 1500#<(>,<)> Tightening torque 770N.m Loosening & removal of stud bolts, dropping ofcomponent, replacementof flange gaskets,lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # | Short Text : Dropping/boxup,Reactor fines ejectors Long Text : Reactor fines ejector,117-JA-400A/B dropping/box up Equipment weight 776 kg.Nozzle list: a. Size: 6\\"300#, Tightening torque 160 N.m b. 4\\" 1500#,Tightening torque 500N.m c. 6\\" 1500#<(>,<)> Tightening torque 770N.m Loosening & removal of stud bolts, dropping ofcomponent, replacementof flange gaskets,lifting and positioning of the components after cleaning, box up <(>&<)> tightening of stud bolts etc.# # |
| 16 | Short Text : Hydrotest of Exchanger, 117-EE-400 Long Text : Hydrotest of Exchanger<(>,<)> 117-EE-400, Dome dropping, Size/Weight: Inlet dome 2052mm/1572Kg, Outlet dome 2052mm/1728Kg<(>,<)> blinding of shell side DM water inlet/outlet line 24\\"#300, tube sheet drying, hydro testing, deblinding of shell side DM water inlet/outlet lines 24\\" #300, cleaning of rust/debris from the flange face, and final box up of MAIN LOOP CONDENSER (117-EE-400)# | Short Text : Hydrotest of Exchanger, 117-EE-400 Long Text : Hydrotest of Exchanger<(>,<)> 117-EE-400, Dome dropping, Size/Weight: Inlet dome 2052mm/1572Kg, Outlet dome 2052mm/1728Kg<(>,<)> blinding of shell side DM water inlet/outlet line 24\\"#300, tube sheet drying, hydro testing, deblinding of shell side DM water inlet/outlet lines 24\\" #300, cleaning of rust/debris from the flange face, and final box up of MAIN LOOP CONDENSER (117-EE-400)# |
| 17 | Short Text : Hydrotest of Exchanger, 117-EE-403 Long Text : Hydrotest of Exchanger,117-EE-403 Long description: Dome dropping, Size: Inlet dome 459mm, Outlet dome 459mm, blinding of shell side cooling water inlet/outlet line 4\\"#300, tube sheet drying, hydro testing,deblinding of shell side cooling water inlet/outlet lines 4\\"#300, cleaning of rust/debris from the flange face, and final box up of KA-401 discharge cooler(117-EE-403)# # | Short Text : Hydrotest of Exchanger, 117-EE-403 Long Text : Hydrotest of Exchanger,117-EE-403 Long description: Dome dropping, Size: Inlet dome 459mm, Outlet dome 459mm, blinding of shell side cooling water inlet/outlet line 4\\"#300, tube sheet drying, hydro testing,deblinding of shell side cooling water inlet/outlet lines 4\\"#300, cleaning of rust/debris from the flange face, and final box up of KA-401 discharge cooler(117-EE-403)# # |
| 18 | Short Text : Hydrotest of Exchanger, 117-EE-409 Long Text : Dome dropping, blinding of channel side inlet/outler lines 8''#600 and shell side cooling water inlet/outlet line 10\\"#300, tube sheet drying, hydro testing, deblinding of shell side cooling water inlet/outlet lines 8\\" #300 and final box up of PA-409 discharge cooler (117-EE-409) | Short Text : Hydrotest of Exchanger, 117-EE-409 Long Text : Dome dropping, blinding of channel side inlet/outler lines 8''#600 and shell side cooling water inlet/outlet line 10\\"#300, tube sheet drying, hydro testing, deblinding of shell side cooling water inlet/outlet lines 8\\" #300 and final box up of PA-409 discharge cooler (117-EE-409) |
| 19 | Short Text : Hydrotest of Exchanger, 117-EE-470 Long Text : Dome dropping, blinding of shell side cooling water inlet/outlet line 3\\"#150, tube sheet drying, hydro testing, deblinding of shell side cooling water inlet/outlet lines 3\\" #150 and final box up. | Short Text : Hydrotest of Exchanger, 117-EE-470 Long Text : Dome dropping, blinding of shell side cooling water inlet/outlet line 3\\"#150, tube sheet drying, hydro testing, deblinding of shell side cooling water inlet/outlet lines 3\\" #150 and final box up. |
| 20 | Short Text : Hydrotest of Exchanger, 117-EE-480 Long Text : Dome dropping, blinding of shell side cooling water inlet/outlet line 3\\"#150, tube sheet drying, hydro testing, deblinding of shell side cooling water inlet/outlet lines 3\\" #150 and final box up. | Short Text : Hydrotest of Exchanger, 117-EE-480 Long Text : Dome dropping, blinding of shell side cooling water inlet/outlet line 3\\"#150, tube sheet drying, hydro testing, deblinding of shell side cooling water inlet/outlet lines 3\\" #150 and final box up. |
| 21 | Short Text : Hydrotest of Exchanger, 117-EE-472 Long Text : Channel inlet/outlet cooling water line opening (6'' # 150), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 8\\"#150, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (6\\"#150) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 8\\"#150 and final box up of KA-470 1ST STAGE cooler (117-EE-472) with new set of gaskets. | Short Text : Hydrotest of Exchanger, 117-EE-472 Long Text : Channel inlet/outlet cooling water line opening (6'' # 150), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 8\\"#150, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (6\\"#150) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 8\\"#150 and final box up of KA-470 1ST STAGE cooler (117-EE-472) with new set of gaskets. |
| 22 | Short Text : Hydrotest of Exchanger, 117-EE-473 Long Text : Channel inlet/outlet cooling water line opening (6'' # 300), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#300 & 4\\"#300, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (6\\"#300) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#300 & 4\\"#300 and final box up of KA-470 DISCHARGE cooler (117-EE-473) with new set of gaskets | Short Text : Hydrotest of Exchanger, 117-EE-473 Long Text : Channel inlet/outlet cooling water line opening (6'' # 300), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#300 & 4\\"#300, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (6\\"#300) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#300 & 4\\"#300 and final box up of KA-470 DISCHARGE cooler (117-EE-473) with new set of gaskets |
| 23 | Short Text : Hydrotest of Exchanger, 117-EE-482 Long Text : Channel inlet/outlet cooling water line opening (4'' # 150), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (4\\"#150) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150 and final box up of KA-480 1ST STAGE cooler (117-EE-482) with new set of gaskets | Short Text : Hydrotest of Exchanger, 117-EE-482 Long Text : Channel inlet/outlet cooling water line opening (4'' # 150), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (4\\"#150) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150 and final box up of KA-480 1ST STAGE cooler (117-EE-482) with new set of gaskets |
| 24 | Short Text : Hydrotest of Exchanger, 117-EE-483 Long Text : Channel inlet/outlet cooling water line opening (4'' # 150), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (4\\"#150) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150 and final box up of KA-480 DISCHARGE cooler (117-EE-483) with new set of gaskets | Short Text : Hydrotest of Exchanger, 117-EE-483 Long Text : Channel inlet/outlet cooling water line opening (4'' # 150), Dome dropping, blinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150, tube sheet drying, hydro testing of channel side after dome boxup with new gasket & blinding of cooling water inlet/outlet line (4\\"#150) or pneumatic test of shell side after installation of test flange, deblinding of shell side process gas (hydrocarbon) inlet/outlet line 6\\"#150 and final box up of KA-480 DISCHARGE cooler (117-EE-483) with new set of gaskets |