| 1 | Supply and inoculation of probiotic microbial liquidculture for commissioning inert media and fordevelopment of microbial bio-film on the surface of theinert media1.3 (make: OSI/ Envirosense/Ecolog) |
| 2 | SITC of water meter in the treated water discharge lineSize:25 mm 14 (make: Kranti) |
| 3 | SITC of monobloc self priming Sewage Transfer pumps (Motor Capacity: 1.0 HP)suitable for handling upto7mm solid particles having a liquid discharge rate of8000 Ltr/hr (each) at a head of 10-12 metresincorporatingC.1. casing, CIimpeller, CI motor bodysuitable for operation on 3-phase 415- Volt AC supplywith similar specification.2NosPump- [01 Working plus 01 SB]complete etc. asreqd.(make: Kirloskar/Crompton/CR |
| 4 | SITC of submersible Sewage Transfer pumps (MotorCapacity:1.0 HP) suitable for handling upto 35mmsolid particles having a liquid discharge rate of 3500Lr/hr (cach) at a hcad of 10 metres incorporating C.1.casing. Cl impeller, CI motor body suitable foroperation on single phase along with 7mtr nylon rope.2Nos Pump - [01 Working plus 01 SB] complete etc. asreqd.(make: Kirloskar/Crompton/CRI) |
| 5 | SITC of submersible Sewage Transfer pumps (MotorCapacity:0.5 HP)having a liquiddis charge rate of3000 Lr/hr (cach) ata head of 5-8 metres incorporatingC.I. casing, Climpcller,CI motor body suitable foroperation on single-phase.(make: Kirloskar/Crompton/CRI) |
| 6 | SITC of 2000 Kgs of Organic biosorption mediaconsisting of carbon rich material along with unloadingand filling into the Advanced Eco Reactor.(Make: Locally available substrate) |
| 7 | SITC of ASTM approved UPVC Sch 40 Piping work forwith all necessary accessories Iike ball valves,b/rvalves, elbow,unions, flange,Non returnable valMTA, FTA,coupler,tees, reducers,pressuregaupe, clamps,fastners etc for making piping complete asrequired 16(make: Prince/Supreme/Astral |
| 8 | Operation and Maintenance of STP based on Sustainable Microbial Advanced Eco reactor Technology including min. dosing of 150 litrs of activated OSI culture along with 01 no. operator (8.5 hrs shift) 06 days a week. Cost includes basic preventive maintenance. |
| 9 | Repair of Motor Control Panel including re-wiring ofDOL starters for operation of 02 no. sewage pumps, 02nos. AER feed pumps, 01 no. treated water tank feedpump..................... |
| 10 | SITC of unarmoured/flexible Copper control wiring ofsuitable size in pve channel/conduit/MS pipe from STPpanel to all the pumps and other electrical equipmentscomplete as required.(make: Polycab/Havels/LandT) |
| 11 | SITC of PVC tanks of 1000 litres. Capacity fitted with tank Nipple and ball valve for bacteria activation and dosing etc as reqd. (Make : Gang/sheetal/Sintex Reno |
| 12 | Cleaning of equalisation tank |
| 13 | SITC of openwell submersible pumps (Motor Capacity:1.5 HP) suitable having a liquid discharge rate of 9000 Ltr/hr (each) at a head of 24 metres incorporating C.I. casing, CI impeller, CI motor body suitable for operation on single phase along with 7 mtr nylon rope. (make: Kirloskar/Crompton/CRI) kosi-1.540 |
| 14 | Operation and Maintenance of STP based on Sustainable Microbial Advanced Eco Reactor Technology including min. dosing of 150 litres of activated OS1 culture along with 01 no. operator (8.5 hrs shift) 06 days a week. Cost includes basic preventivemaintenance (Year 2) |
| 15 | Replenishment of 2000 Kgs of Organic biosorption media consisting of carbon rich material along with unloading and filling into the Advanced Eco Reactor in Year 3(Make: locally available substrate) Please Enable Macros to View BoQ information |