| 1 | HT LINE with Tapping point :AAAC 7/4.26 mm2 conductor additional 1% (Sag, Jumpering and wastage} |
| 2 | 9Mtr. Long ISI marked, Swaged Steel Tubular poles as per IS:2713 / 1980 (Part-I-III) as amended from time to time, along with Cap Welded on top & Cast iron Base plate of designation 410SP-32. |
| 3 | 11 Mtr. Long ISI marked, Swaged Steel Tubular poles as per IS:2713/1980 (Part-I-III) as amended from time to time, along with Cap Welded on top & Cast iron Base plate of designation 410SP-56. |
| 4 | RCC Muff 2000mm Long with concrete filling material |
| 5 | GO AB Switch Unit (11KV, 400A,25KA) Tripple pole O/D type |
| 6 | D.O Fuse Unit |
| 7 | MS Chanel Iron (75x40x6 mm), Length: 460 mm x ( 1 No. for GO Switch Handle mounting). |
| 8 | MS Angle Iron (50X50x6 mm), Length : (450 mm) x 1 Nos |
| 9 | X-Arm (Horizontal) - MS Channel Iron C type: 100X50x5, Length: 2340 mm x 2 No.] ∆ Formation |
| 10 | X-Arm (Horizontal) - MS Channel Iron C type: 100X50x5, Length: 2600mm x 2 No.] ∆ Formation |
| 11 | MSAI Bracing Set for X-Bracing set for double pole str of Size (50X50x6, Length :2125mm each ( 2 Nos per set ). |
| 12 | Belt Set - MS Angle Iron: 50x50x6, Length :1800 mm x 2 No. |
| 13 | Discs insulator sets |
| 14 | 11 kV Pin Insulators |
| 15 | HT Stay Set Complete i/c Guy Assembly and Helically fittings) |
| 16 | Stay wire 7/3.15 mm@ 10.00 kG per stay set |
| 17 | HT Earthing set complete |
| 18 | Continous Earth wire (GI, 8 SWG) {alongwith 1 wire lengths for avg.one road crossing @ 20 m and Additional 3% (Sag and wastage)} including Cross Lacings (GI, 8 SWG) [ 2.2 m x 9 Nos @ 2 m spacing] at road crossings {0.102 kg/m} |
| 19 | Eye Hook for for Earth wire |
| 20 | MS AI.of Size (2800x50x50x6 mm) |
| 21 | M.S.Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm² or more (with flat and spring washers)] |
| 22 | Barbed Wire |
| 23 | Danger Plate (250X200X1.6 mm) |
| 24 | Half Clamp made of M.S. Flat of size(50 x 6mm). |
| 25 | Full Clamp made of M.S. Flat of size(50 x 6mm). |
| 26 | Aluminium Paint |
| 27 | LT LINE : 9Mtr. Long ISI marked, Swaged Steel Tubular poles as per IS:2713/1980 (Part-I-III) as amended from time to time, along with Cap Welded on top & Cast iron Base plate of designation 410SP-32.. |
| 28 | RCC Muff 2000 mm long with concrete filling material |
| 29 | Channel iron Iron (75X40x5 mm), ( Length-1.50Mtr+0.2Mtr)mm x1 Nos. Per Pole |
| 30 | Shackle Insulator (16 kN) |
| 31 | D-Iron (U- Clamps)made of MS Flat 50x6mm with Nut & Bolts |
| 32 | Earh Knob |
| 33 | LT Stay Set Complete i/c stay clamp) |
| 34 | Stay wire 7/3.15 mm (6.00 kg. per stay set) |
| 35 | Stay Clamp / Full Clamp made of M.S. Flat of size (50 x 6mm). |
| 36 | Half Clamp made of MS Flat 50x6mm |
| 37 | LT Earthing Set complete in all respect |
| 38 | Continous Earth wire (GI, 8 SWG) {alongwith 1 wire lengths and Additional 1% (Sag and wastage)} {0.102 kg/m} |
| 39 | Nuts and Bolts of various sizes (Galvanised / Coated) [Preferably 16mm² or more (with flat and spring washers)] |
| 40 | Aluminium Paint |
| 41 | PVC Spacer |
| 42 | ERECTION OF 11KV HT LINE : Erection of Single Pole Run through Structure with Steel Tubular Pole 9Mtr Long as per latest standard practices /specification of REC / HPSEBL : (including Digging of pit for poles, muffing of pole, drilling of holes in poles and X-arms ,fixing of insulators,X-arms, erection of poles, fixing of barbed wire,danger plate,filling of pit ramming and painting painting of structure with Redoxide Primer & then with Aluminium Paint etc.Complete in all respect. |
| 43 | Erection of Double Pole / Dead Pole Structure with Steel Tubular Pole 11Mtr Long as per latest standard practices /specification of REC / HPSEBL : (including Digging of pit for poles, muffing of pole, drilling of holes in poles and X-arms ,fixing of insulators,X-arms, erection of poles, fixing of barbed wire,danger plate,filling of pit ramming and painting painting of structure with Redoxide Primer & then with Aluminium Paint etc.Complete in all respect. |
| 44 | Erection of Stay Set (HT) as per latest standard practices /specification of REC / HPSEBL including Digging of pit (size0.9x0.7x1 .5 M),fixing of Stay Rod, filling and ramming of pit, nozzelling and tightening etc. complete in all respect. |
| 45 | Erection of HT Earthing Set as per latest standard practices /specification of REC / HPSEBLincluding digging of pit of size 1.80x 1.2 x1.2 Mtrs, fixing of HT Earth Set, refilling the same and prov. earthing connection complete in all respect. |
| 46 | Laying of Conductor, Stringing, Sagging of ACSR, 80-100mm² and binding with Insulators (3 wires) and fixing of jumper. |
| 47 | Erection of Continous Earth Wire / Guaring wire i.e. Laying of GI Wire 8SWG , Stringing, Sagging of and binding with Insulators including erection of Guarding wire & Cross Lacings etc. at road crossings/ where ever necessary. |
| 48 | Erection of GO switch unit complete in all respect |
| 49 | ERECTION OF LT LINE : Erection of LT Pole structure with Steel Tubular Pole 9 mtr. Long as per latest standard practices /specification of REC / HPSEBL : (including Digging of pit for pole, muffing of pole, erection of poles, refilling of pit & ramming , drilling of holes in pole and X-arm, fixing of X-arm, Shackle Insulators and painting of structure with Redoxide Primer & Aluminium Paint etc.Complete in all respect as per the standard practices / specifications of the REC /HPSEBL. |
| 50 | Erection of Stay Set (LT) as per latest standard practices /specification of REC / HPSEBLincluding digging of pit (size0.9*1.20*1.33),fixing of Stay Rod, filling and ramming of pit, nozzelling and tightening etc. complete in all respect. |
| 51 | Erection of LT Earthing as per latest standard practices /specification of REC / HPSEBL including digging of pit fixing of LT Earth Set, refilling the same and prov. earthing connection completein all respect. |
| 52 | Laying of Earth wire with GI Wire 8SWG , Stringing, Sagging of and binding with Insulators. |
| 53 | Add Transportation charges/mannual carriage , loading unloding of material from site to store & store to site as instruction from Site Incharge complete job in all respect. Please Enable Macros to View BoQ information |