| 1 | Earth work narrow excavation for foundation in all soils and sub soils and to full depth as may be directed except hard rock requiring blasting inclusive of shoring, shuttering and baling out water where ever necessary , refilling the sides of foundations with excabvated earth in layers of not more than 15cm thk watered, well rammed , consolidated and depositing the surplus earth on bank with initial lead of 10m and initial lift of 2m, clearing and leveling the site etc., complete as directed by the federation officers and as per standard specifications. |
| 2 | Supplying and filling with M. sand for foundation and basement to required thickness and in lyers on not more than 30cm thick, watered ,well rammed and consolidated etc., complete as directed by the Federation officers and as per the technical Specifications |
| 3 | Plain Cement Concrete 1:5:10 using 40 mm size HBG stones for foundation including de-watering if found necessary and laid in layers of not more than 15 cm thick for flooring including rendering the top surface rough to take floor finish including side shuttering if required and compaction ,curing etc., complete as directed by the Federation officers and as per the technical Specifications |
| 4 | Supplying, erecting steel centering using M.S. Sheet of size 90X60cm and BG 10 gauge stiffened welded with M.S. angel of size 25X25X3mm laid over silver osk/country wood joist of size 10X6.5cm spaced at about 90cm centre to centre and supported by casurinaprops of 10 to 13cm dia spaced at 75cm center to centre for all type of RCC roof slab, lintel beam,T,L,beam landing slab plinth beam, grade beam, column footing, column , sunshade, facia, sloped roof, waist slab, etc., Including necessary suppoerts with all cross bracings filling slits and holes in the surfaces(the retrieved materials should be taken back by the contrator) and side shuttering etc., complete as directed by the Federation officers and as per standard specification.For Column Surface - Upto Basement |
| 5 | upto basement height plain surface |
| 6 | 0 to 3.30m height plain surface |
| 7 | Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works excluding cost of reinforcement grill and fabricating charges centering and shuttering but including Super Plasticiser, mixing charges for machine mix,laying, vibrating with mechanical vibrators, finishing, curing, etc. and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary and bearing surfaces of walls, beams etc. shall be finished smooth with Cement Mortar 1:3 (One Cement and Three Sand) and kraft paper laid over it without claiming extra, etc., complete complying with standard specification and as directed by the departmental officers - machine mix - Upto basement height |
| 8 | Above basement height |
| 9 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel reinforcement grills of all variety like HYSD/CTD/TMTand all grade like Fe 500, Fe550D, Fe 500 D etc., for all RCC works as per design given including cost of steel reinforcement and G.I. binding wire, wastage etc. complete complying with standard specification and as directed by the departmental officers.(Contractor has to make his own arrangements for the supply of steel reinforcement and binding wire) |
| 10 | Brick work in Cement Mortar using best quality Burnt Clay Brick of size 9\\" x 4 3/8\\" x 2 3/4\\" with class designation of 7.5 conforming to IS 1077-1992 for foundation and basement including Cost of Mortar Plasticizer curing, etc.,complete complying with standard specification and as directed by the departmental officers. Brickwork shall be done as per IS 2212-1991 adopting English Bond generally.other type of bond shall be done as directed by the Executive Engineer in chargeUp to basement height |
| 11 | From 4.50 m to 9.00 m Height - First Floor |
| 12 | Flooring with unposlished Granite stone of 30 mm thick of approved quality set in CM 1:3, 20mm thick and pointing with white cement and adhesive componenets etc., complete as directed by the Federation officers and as per standard specification. |
| 13 | Supplying & erecting structural steel of various section like Joist, channel section and purlin in suitable position inclusive of all labour charges for making joints, clit angles, welding, placing in position Including Painting etc., as directed by the Federation officers and as per standard specifications |
| 14 | Supplying and fixing colour galvalume sheet roof of 0.47mm thick and fixing in position with all necessary accessories complete complying with standard specification and as directed by the departmental officers. (TATA/JSW or Equivalent ) |
| 15 | Supplying and fixing of Aluminium Sliding doors with partially panelled / Glazed with necessary fixtures hinges,rubber gasket, screws and fixing clips etc., including necessary filling up of gaps at junctions, at top, bottom and sides with sealent etc., Bottom 900mm height shall be with Prelaminated both side Bison lam sheet (Cement Particle Board) fixed to shutter. The door shall be provided with Aluminium handle, door closer, stopper, towerbolt, locking arrangement etc., The cost and conveyance of all materials to site and all labour charges etc., complete. |
| 16 | Fabricating Supplying and fixing in position of Aluminium anodized natural colour matt finish Two panels openable type window in all floors with aluminium sections of the Outer frame: 37.70x33x2mm @ 0.50 kg/m,Centre mullions:59x33x2.50mm @0.936 kg/m,Shutter frame : Z section 24.50x33x3mm @ 0.525kg/m,Aluminium clips:0.109 kg/m with neccessary accssories such as rubber beadings, special hinges, handle including supplying and fixing 4mm thick plain glass including cost of all materials, labours, power consumption required for fabrication, drilling holes in RCC column slab, masonry walls wherever necessary with power drills to the required extent and make good to the original conditons after fixing and also as directed. All the Aluminium sections are to the anodised with matt finish under electrically controlled conditons in accordance with Is 1868/1962 for an average anodic film thickness of 15 microns etc.Complete. |
| 17 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat etc., complete as directed by the departmental officials. |
| 18 | Fabricating Supplying and fixing in position of Aluminium anodized natural colour matt finish Two Panels openable type window with fixed Ventilator at Top at 0.30 m height in all floors with aluminium sections of Outer frame: 37.70x33x2mm @ 0.50 kg/m,Centre mullions: 59x33x2.50mm @0.936 kg/m,Shutter frame : Z section 24.50x33x3mm @ 0.525kg/m,Aluminium clips:0.109 kg/m and with neccessary accssories such as rubber beadings, special hinges, handle including supplying and fixing 4mm thick plain glass including cost of all materials, labours, power consumption required for fabrication, drilling holes in RCC column slab, masonry walls wherever necessary with power drills to the required extent and make good to the original conditons after fixing and also as directed. All the Aluminium sections are to the anodised with matt finish under electrically controlled conditons in accordance with Is 1868/1962 for an average anodic film thickness of 15 microns etc complete. |
| 19 | Plastering with Cement Mortar 1:5 (One cement and Five Plastering sand), 12mm thick in all floors including mortar plasticizer at 200ml per 50Kg of cement used, curing etc. complete complying with standard specification and as directed by the departmental officers. |
| 20 | Painting New Plastered Wall Surface with Two finishing coats of ready mixed (Emulsion) of approved quality and colour over one coat priming coat in all floors including the cost of primer etc., complete complying with standard specification and as directed by the departmental officers.(The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) |
| 21 | Supply and Fixing of Mechanically operated Turbo vent at required Height as directed by the engineer in charge of work, the cost including all materials, labourers and installation etc., complete and as per the standard Specification |
| 22 | Supply and fixing of RCC Hume pipe of 300 mm dia as per standard specifications . |
| 23 | Supply & laying Indian Patent Stone Flooring (I.P.S) in cement concrete 1:2:4 using 10 to 12mm chips for 40mm thick using waterproof compound 2% by weight of cement and the top finished with CM 1:1, 10mm thick neatly etc. complete as directed by the federation officers and as per standard specifications |
| 24 | GST (Note: The tenderer should quote the amount towards Goods and Service tax (GST) in the appropriate columns in terms of percentage (%). If not quoted, it will be considered that the rate quoted is inclusive of GST.) Please Enable Macros to View BoQ information |