| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In Cement mortar |
| 2 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. Nominal concrete 1:3:6 or richer mix (i/c equivalent designmix) |
| 3 | Removing mortar from bricks and cleaning bricks including stacking within a lead of 50 m (stacks of cleaned bricks shall be measured): From brick work in cement mortar |
| 4 | Brick work with available common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 5 | 12 mm cement plaster of mix 1:4(1 cement: 4 coarse sand) |
| 6 | Neat Cement punning |
| 7 | Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.) The Contractor has detect different utilities like sewer line, Water Supply Line, Electric Cable, Telephone Cable, Gas Pipe Line(using Utility Detecting MAchine Before Start of Excavation and Shall start Excavation only after getting Permission of Engineer-in-Charge. |
| 8 | Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. All kinds of soil |
| 9 | Earth work in excavation by mechanical means (Hydraulic excavator) /manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil |
| 10 | Excavating holes more than 0.10 cum & upto 0.5 cum including getting out the excavated soil, then returning the soil as required in layers not exceeding 20cm in depth, including consolidating each deposited layer by ramming, watering etc, disposing of surplus excavated soil, as directed within a lead of 50 m and lift upto 1.5 m. All kinds of soil |
| 11 | Filling availabe excavated earth ( excluding rock ) in trenches,plinth,side of foundation etc.in layers not exceeding 20 cm depth,comsolidating each deposited layer by ramming and watering lead up to 60 and lift upto 1.6m. |
| 12 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. |
| 13 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. |
| 14 | Cement Concrete with 4 cm gauge approved stone ballast, coarse sand & Cement in the proportion of 8:4:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of work |
| 15 | Cement concrete with 4 cm gaug approved stone ballast, course sand & cement in proportion of 4:2:1 including supply of all materials labour tools and plant etc. required for proper completion of work Same as above item No. 279 but with 2cm gaug stone grigt insted of 4 cm gauge stone ballast. |
| 16 | Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying , excluding the cost of centering, shuttering finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer-in-charge. (Note Cement content considered in this item is @ 330 kg/ cum.Excess/less cement used as per design mix is payable/recoverable separately). All works upto plinth level |
| 17 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns |
| 18 | Centering and shuttering including strutting, propping etc. and removal of form for : Walls (any thickness) including attached pilasters, butteresses,plinth and string courses etc. |
| 19 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Thermo- Mechanically Treated bars of grade Fe-500D or more. |
| 20 | Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. : In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 21 | Fabrication & Manufacturing of Prestressed Hollow Core slab (Hollow area 25 to 30%) of different thickness & modular width 1200 mm in Controlled Factory Environment with approved methodology informing to IS 10297- 1982 conforming to IS : 10297- 1982 by using long line casting method having arrangement of proper steel bed. Concreting should be done by batch mixing plant capable of producing zero slump concrete, transported through automatic shuttels of standard make & layed on bed with the help of extruder/Slipformer, finishing, curing and also provision of steam curing. Cutting, making necessary cutout/holes of required sizes for services in slab element after achieving required strength, yard handling & stacking all complete as per approved shop drawings & design mix as per the direction of the Engineer-in-charge. (Cost of strands should be paid separately). Note : Excess/ less cement over the specified cement content used as per design mix is payable / recoverable separately. Concrete Grade-M-40 (cement content 400 kg ) 150 mm thick hollow core slab |
| 22 | Erection & Installation of Precast/Prestressed Concrete elements in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge but excluding the cost of sim pads, non shrink grout and steel works i.e hangers. All work up to fifth floor. Prestressed hollow core Slab up to 200 mm thickness sqm 160.85 |
| 23 | Dewatering pump 10 HP |
| 24 | Earth work in embankment in ordinary soil embankmentto be in 20 cm layers includingramming Dressing the Surface to levels with half tone steel or wodden rammerand rolling every third and top most layer in roller 8 to 10 tone capacity and including 1.50 mtr ,lift and all lead ( earth shall be brought from a place which including cartage of earth by mechanically transport and T&P labour etc.required for proper compection).Earth should be arranged by the contractor at his own cost. |
| 25 | Providing and laying 60mm thick factory made cement concrete interlocking paver block of M-30 grade made by block making machine with strong vibratory compaction, of approved size, design and shape, laid in required colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with the sand etc. all complete as per the direction of Engineer-in- Charge. |
| 26 | Providing and placing in position 100 mm thick factory made machine batched & machine mixed Precast RCC Rectangular Covers on drains of footpath of various sizes, of M-25 grade cement concrete for RCC work, including cost of centering, shuttering, reinforcement of 8 mm dia TMT bars of Fe 500 grade @ maximum 100mm c/c on both ways , neat cement punning on finished surface, properly encased on all edges with 1.6 mm thick, 100 mm wide MS sheet duly painted over priming coat, reinforcement to be welded at edges with MS sheet and providing 2 Nos. 12 mm dia bar for hooks etc i/c cost of cartage, all leads & lift, handling at site etc. all complete as per direction of Engineer-in-Charge. |
| 27 | Providing wall Putty on new surface with approved quality material of Berger/J.K./Birla or similar make 2 coats. |
| 28 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade : 13.61.1 Two or more coats on new work |
| 29 | Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade : Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture |
| 30 | Precasting and placing in position 125 mm dia Bollards 600 mm high of required shape including providing M.S. Pipe Sleeve 50 mm dia 300 mm long in the Bollard and M.S. Pipes 40 mm dia and 450mm long with 150x150x6mm M.S. plate welded at bottom and embedded 150mm in cement concrete 1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size), including necessary excavation of size 250x250x450mm deep for the same in bitumen/ concrete pavement at specified spacing. Please Enable Macros to View BoQ information |