| 1 | Excavation in foundations in ordinary soil (Loam clay or sand) including lift upto 1.5 m (5 fts.) and lead upto 30 mt. (100 fts.) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-Incharges upto a distance of 30mt. (100 fts) from the foundation trenches. |
| 2 | Excavating, supplying and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth,sides of foundation etc. complete. |
| 3 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete |
| 4 | Providing and laying cement concrete 1:4:8 (1 cement :4 coarse sand :8 graded Stone aggregate 40 mm nominal size) including supply of all materials, labour T & P rtc required for proper completion of the work and curing complete also including cost of formwork in foundation & floors. |
| 5 | Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: |
| 6 | With Chlorpyriphos E.C. 20% with 1%concentration |
| 7 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 8 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level inall shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 9 | Half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level. Cement mortar 1:4 (1 cement :4 coarse sand) |
| 10 | Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources). (Plinth beam) |
| 11 | As in item no. 9 above but for R.C.C. work in Slab (Using 1:1.5:3 Mix concrete) M-20 |
| 12 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. (Mild steel and Medium Tensile steel bars) |
| 13 | 15 mm cement plaster on rough side of single or half brick wall of mix: 1:4 (1 cement: 4 coarse sand) |
| 14 | 12mm cement plaster in single coat on fair side of single or half brick wall for exterior plastering up to floor two level including internal rounded angles chamfers, and/or rounded angles not exceeding 80mm in girth and finished even and smooth no extra for mixing any additive. (1)1 cement : 6 fine sand |
| 15 | 12 mm cement plaster in single coat on rough side of single or half brick wall for interior plastering up to floor two level including internal rounded angles not exceeding 80 mm in girth and finshed even and smooth. (1) 1 cement : 6 fine sand. |
| 16 | Water proof plaster on roof with neat cement finish |
| 17 | Providing and laying Ceramic glazed floor tiles of size 300x300 mm (thickness to be specified by the manufacturer) of 1st quality conforming to IS : 15622 of approved make in colours such as White, Ivory, Grey, Fume Red Brown, laid on 20 mm thick cement mortar 1:4 (1 Cement : 4 Coarse sand), Jointing with grey cement slurry @ 3.3 kg/sqm including pointing the joints with white cement and matching pigment etc., complete. |
| 18 | Providing and fixing Ist quality ceramic glazed wall tiles conforming to IS: 15622 (thickness to be specified by the manufacturer), of approved make, in all colours, shades except burgundy, bottle green, black of any size as approved by Engineer-in-Charge, in skirting, risers of steps and dados, over 12 mm thick bed of cement mortar 1:3 (1 cement : 3coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm, including pointing in white cement mixed with pigment of matching shade complete. |
| 19 | Providing and fixing angle iron frames for doors, windows and ventilators of mild steel angle sections of size 35x35x5 mm, joints mitred and welded by angle iron 35x35x5 mm or 35x 5 mm flat pieces to the existingT-iron frame or to the wall with dash fastener, including fixing of necessary butt hinges and screws and applying a priming coat of approved steel primer, all complete as per the direction of Engineer-In-charge. |
| 20 | Z-Section |
| 21 | Painting two coat over priming coat (but including cost of priming coat) on steel and other metal surfaces up to 10 cm. width or girth or small articles not exceeding 0.10sqm in area white superior synthetic enamel such as LUXOL3,Hi-gloss apcolite superlac, DULUX specified brushing to give an even shade and including cleaning the surface of all dirt,dust and other foreign matter sand papering and stoping including cost of all materials, labour tools and plants etc. required for proper completion of the work. |
| 22 | Distempering with 1st quality acrylic distemper (ready mixed) having VOC content less than 50 gms/litre, of approved manufacturer, of required shade and colour complete, as per manufacturer's specification. Two or more coats on new work. (Ceiling) |
| 23 | Providing & fixing glass panes with putty and glazing clips in steel doors, windows, clerestory windows, all complete with : 4.0 mm thick glass panes. |
| 24 | Making of Apron Drain |
| 25 | Providing and fixing factory made uPVC white colour casement/ Casement cum fixed glazed door comprising of uPVC multi-chambered frame, sash and mullion (where ever required) extruded profiles duly reinforced with 1.60 ± 0.2 mm thick galvanized mild steel section made from roll forming process of required length (shape & size according to uPVC profile), uPVC extruded glazing beads of appropriate dimension, EPDM gasket, zinc alloy (white powder coated) 3D hinges and one handle on each side of panels along with zinc plated mild steel multi point locking having transmission gear, cylinder with keeps and one side key, G.I fasteners 100 x 8 mm size for fixing frame to finished wall and necessary stainless steel screws, etc. Profile of frame & sash shall be mitred cut and fusion welded at all corners, mullion (if required) shall be also fusion welded including drilling of holes for fixing hardware's and drainage of water etc. After fixing frame the gap between frame and adjacent finished wall shall be filled with weather proof silicon sealent over backer rod of required size and of approved quality, all complete as per approveddrawing & direction of Engineer-in-Charge. (Single / double glass panes and silicon sealent shall be paid separately). Variation in profile dimension in higher side shall be accepted but no extra payment on this account shall be made. |
| 26 | Providing and fixing factory made uPVC door frame made of uPVC extruded sections having an overall dimension as below (tolerance ±1mm), with wall thickness 2.0 mm (± 0.2 mm), corners of the doorframe to be Jointed with galvanized brackets and stainless steel screws, joints mitred and Plastic welded. The hinge side vertical of the framesreinforced by galvanized M.S. tube of size 19 X 19 mm and 1mm (± 0.1 mm) wall thickness and 3 nos. stainless steel hinges fixed to the framecomplete as per manufacturer’s specification and direction of Engineerin-charge |
| 27 | Extruded section profile size 48x40 mm |
| 28 | S/F Bench With all Complete Rate. |
| 29 | Grassing with selection No. 1/ Doob grass including watering and maintenance of the lawn for 30 days or more till the grass forms a thick lawn, free from weeds and fit for mowing including supplying good earth, ifneeded (the grass and good earth shall be paid for separately |
| 30 | Providing and fixing of hedges and groundcover, plants as per drawing for the landscape and maintaining for three months M.R |
| 31 | Supply of palm tree |
| 32 | Supply and Fixing Board Excluding G.S.T |
| 33 | Add for Internal w/s & sewerage |
| 34 | Add for Septic tank |
| 35 | Add Internal Electrical Work |
| 36 | COST OF BORING & SUBMERSIBLE PUMP |
| 37 | 18% GST Please Enable Macros to View BoQ information |