| 1 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. III. EVENT MANAGEMENT : 2) Hire and labour charges for100 mm dia bamboo railing on Jhau/Eucalyptus post 1.40 m above G.L and 0.60 m below G.L tied strongly with bamboo railing with coir rope, digging holes for posts in any sort of soil or concrete surface packing the sides etc including cost of carriage of all materials and labour complete including cost of restoration to the damages of the ground to its original condition as per direction of Engineer- in- chargeafter removing the barricade. (Cost of restoration to be paid separately). (a) 100 mm. dia bamboo railing and 150 mm. dia. Jhaubullah/Eucalyptus posts @ 1.80 m. apart. (i) Railing with 4 rows. |
| 2 | CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.29Hire charges for engaging Air Compressor machine with minimum pressure capacity of 5.0 Kg/sq.cm arrangement including all necessary equipments and operating staff, carriage, fuel, Tools and plants all complete for cutting Road / hard crust cutting with pneumatic hammer at desired point in water supply works as per direction of EIC . a) With Pneumatic hammers For minimum engagement of 8 hrs. In a day |
| 3 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. |
| 4 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete (b) Depth of excavation for additional depth beyond 1,500 mm. and upto 3,000 mm. but not requiring shoring |
| 5 | BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( 3rd Corrigenda & addenda dated 04.06.2018) |
| 6 | PROTECTIVE AND LINING WORKS IN CANALS & CHANNELS AND OTHER FLOOD PROTECTIVE MEASURES 2.24.Supplying to site empty cement polythene bags (capacity 50kg) in good condition including stacking, incedental charges etc. all complete (capacity 50 kg). |
| 7 | PROTECTIVE AND LINING WORKS IN CANALS & CHANNELS AND OTHER FLOOD PROTECTIVE MEASURES 2.27.Labour charges for filling empty cement gunny bag / polythene bag (capacity 50 kg) with all kinds of earth (wet or dry), sand or agreegates(stone / brick) and sewing as done in case of cement bags ,( tying with a knot after filling will not be accepted ) , and stacking within a lead of 30 metre as per direction of Engr-in-charge (cost is excluding the cost of any types of filling materials). NB:- Volume of earth/ sand filled bags should not be less than 0.028 cum/bag |
| 8 | PROTECTIVE AND LINING WORKS IN CANALS & CHANNELS AND OTHER FLOOD PROTECTIVE MEASURES 2.29.Dumping in position earth / sand filled gunny / poly bags (capacity 50kg) within a lead of 30 metre inclusive of all lifts. |
| 9 | PROTECTIVE AND LINING WORKS IN CANALS & CHANNELS AND OTHER FLOOD PROTECTIVE MEASURES 2.32.Removing earth/sand filled poly bags/gunny bags from the channel bed/slope and initially depositing the same near channel bank at a place as directed by the Engineer-in Charge for measurement of Bag. & then disposing off the same at a distance not less than 150 metre from the channel site. |
| 10 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.14 Signalling arrangement at both sides of site to avoid any accident during working period 4 nos. red flags during sunlight at 4 corners and 2 nos light (lamp) in other than sunlight. |
| 11 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.12 Supplying sign-board made of 25 mm thick sal plank with frame on all side of sal batten 50 mm x 32 mm with nailed on post 3.15m x 100mm x100mm and fitting fixing such with digging holes of dia 300 mm and depth 750 mm in all sorts of soil and repacking and consolidating the gap aroundthe post with cement concrete (1 : 3 : 6) painting 2 coats including cost of nails, bolts and nuts etc. complete in all respect as per direction of theEngineer-in-charge. Payment of concrete and painting to be made separately. (i) 600 mm. x 450 mm. size of board. |
| 12 | CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.26 Hire charges of moveable crane with fuel & manpower having load handling capacity upto 14MT with the 45 deg. moveable arrangement & the boom length of 40 feets for loading & unloading of various materials / accessories of water supply works. For minimum engagement of 8 hrs. In a day |
| 13 | Supplying Eucalyptus-bullah piles at work site,including dressing and maiking one end pointed iii)150mm dia meter |
| 14 | Labour for diving Sal_bullah/Eucalyptus bullah piles by monkey in sorts of soil including hoisting and placing piles in position ,protecting the pile head with iron ring and cutting and shapping heads before and after driving and including hire and labour for necessary driving appiances and all tackles. (iii)150 mm diameter |
| 15 | Hire and labour charges for 5 cm. thick close timbering with planks battens, runners struts etc. complete removing them incl. penetration of shoring as per direction of the Engineer-in-Charge. (Vertical surface of contact area with supporting earth to be measured, payment for penetration will not be allowed) a) Beyond 1.0 M. upto 2.0 M trench width . depth upto 6.00 M below G.L. |
| 16 | STEEL PLATES : (E250 CONFORMS TO IS : 2062 - 2006 ) 6 TO 40 |
| 17 | CHAPTER - II LAYING & JOINTING PIPES, SPECIALS ETC.2.1 C.I. / D.I. Pipe & Specials 2.1 C.I. / D.I. Pipe & Specials 2.3.5 Fabricating M.S. pipes of different diameter in shop out of 8mm to12mm thick M.S plates supplied depart-mentally, cutting the plates to exact size &shape by gas cutting device and/or by adopting any other approved type of mechanical means, bending the same in true curvature by template and rolling machine of approved design including proper marking, levelling joints followed by electric arc welding as per relevant I.S. specification - longitudinal and circumferential, as necessary, usiug standard electrodes including edge preparation, electricity charges and hydraulic testing of the fabricated piece all complete as per speci-fication and direction of the Engineer-in-Charge. [The Engineer-in-Charge shall approve the electrodes for arc weldingbefore use.]a) Diameter from 450 mm & upto 600 mm j) 1400 mm diameter ii)12mm thick |
| 18 | BUILDING WORKS (F) STRUCTURAL STEEL WORKS, GRILLS, GATES ETC. B. REPAIRING 2. Welding in M.S. structural work with gas or electric: (a) Tack weld |
| 19 | CHAPTER - II LAYING & JOINTING PIPES, SPECIALS ETC.2.1 C.I. / D.I. Pipe & Specials 2.1 C.I. / D.I. Pipe & Specials 2.3.9 LowerIng M.S pipes & specials in trench up to a depth of 3.00 metre below G.L,laying and jointing the same inside the trench / over ground by meansof electric arc welding using standard electrodes as per l.S. specification, all complete as per direction of the Engineer-in-Charge. [The Engineer-in-Charge shall approve the electrodes for arc welding before use. (For laying over ground. the rates shall be reduced by 10% and that is inclusive of holding arrangements) ] 1400mm |
| 20 | CHAPTER - VII MISCELLANEOUS ITEMS Coating of 'Epoxy' Resin of thickness not less than 160 micron with a lowviscosity,crystallization-resistant epoxy resin base with a reactive diluents combined with high build epoxy amine adducts as per BS 5493 standard and a polyamide or amido polyamine or any other suitable hardener. It shall react with epoxy resin at normal ambient temperature, suitable for solvent-free coatings as per recommended proportion for use on metal,concrete and wood surface to protect from corrosion as well as damagefrom chemical reaction after makingthe surface free from dust, oil and moisture etc. all complete as per instruction and to the satisfaction of ElC. [This item will be operated on prior permission from the concerned SE/Dy Chief Engineer] |
| 21 | CHAPTER - VIII SUPPLYING OF MATERIALS 8.24 Carriage of Different materials including loading into truck at the lifting point, unloading at destination and stacking properly in godown or yard etc. as directed (Including carriage by head load upto 30 metres at each of the two points. The rate covers all the above operations, actual transport all complete ) steel upto 5km |
| 22 | CHAPTER - VII MISCELLANEOUS ITEMS Dewatering by pumps including all leads, lifts and making all arrangements of disposal. where continuous flow of water from a source other than natural or ground water is encountered in case of emergency maintenance works related to leakage. breakage and making wet connections. [Note ;- In case of any other situation demanding such emergency dewatering. use of this item is to be approved by the Superintending Engineer/Tender Accepting Authority. This item shall be executed on the specific direction duly supported by proper clarification of the E.I.C. who will be satisfied in absolute discretion that such work has not been necessitated due to any natural source of water or any fault of the Contractor] |
| 23 | SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(ii) 225 mm |
| 24 | SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(iii) 150 mm |
| 25 | 22.Construction of gullypit 1100mmX625mm. inside measurement and depth of invert 1500mm. below G.L. with 250mm. thick cement brick work (1:4) over 100mm. thick jhama cement concrete (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing, brickon-edge flooring in the invert, 20 mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside of walls and invert including supplying,fitting and fixing R.C.P.C. gully grid (15-M.T.load bearing capacity) and 225 mm. dia. C.I. Syphone including cutting hard crust, excavation, dewatering, back filling and removal of spoils as per standard drawing |
| 26 | 23.Construction of Catch pit 600mmX525mm. (inside measurement) and depth of invert 1000mm. below G.L. with 250mm. thick cement brick work (1:4) over 100mm. thick jhama cement concrete (1:4:8) bed over a layer of brick flat soling including providing 100mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing, brickon- edge flooring with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying and fixing R.C.P.C. gully grid (5 M.T.load bearing capacity) and 150 mm. dia. C.I. Syphone including cutting hard crust, excavation, dewatering, back filling and removal of spoils as per standard drawing |
| 27 | COST OF SPIGOT / SOCKET TYPE OF PIPE WITH RUBBER GASKET bore dia in mm 600 thickness in mm 85 standard length in m. 2.5 |
| 28 | COST OF SPIGOT / SOCKET TYPE OF PIPE WITH RUBBER GASKET bore dia in mm 500 thickness in mm 75 standard length in m. 2.5 |
| 29 | Laying of R.C.C. pipe with spigot ... socket/Roll on jointed pipe, lowering the same into the trench laying on the bed in trenches in prescribed gradient, depth and alignment, filling the end grooves with necessary bitumastic compound, filling caulking space with tarred gasket or with rubber gasket of appropriate size & covering with cement mortar (1:2) & testing the joints etc. complete as per drawing, specification including carriage of pipes from site stacks to the place of laying etc. & as per direction of the Engineer-in-charge.(Payment tobe made on the basis of actual finished length of the pipe line). A) Class NP-3 Pipe m) 600 mm. dia. |
| 30 | Laying of R.C.C. pipe with spigot ... socket/Roll on jointed pipe, lowering the same into the trench laying on the bed in trenches in prescribed gradient, depth and alignment, filling the end grooves with necessary bitumastic compound, filling caulking space with tarred gasket or with rubber gasket of appropriate size & covering with cement mortar (1:2) & testing the joints etc. complete as per drawing, specification including carriage of pipes from site stacks to the place of laying etc. & as per direction of the Engineer-in-charge.(Payment tobe made on the basis of actual finished length of the pipe line). A) Class NP-3 Pipe n) 500 mm. dia. |
| 31 | 25.Construction of manhole with chamber of size as given below as per requirement and 600mm X 600mm. (inside measurement) squareshaft, with cement brick work (1:4) over 150 mm. thick jhama cement concrete (1:4:8) bed, over a layer of brick flat soling including providing 150mm. thick R.C.C.slab with ordinary concrete (mix 1:1.5:3) with reinforcement as per standard drawing over the chamber, brick-on-edge flooring with ordinary cement concrete (mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing R.C.P.C. cover and frame (35 M.T.load bearing capacity) with ordinary cement concrete (mix 1:2:4) and C.I.steps (4 Kg. each) including cutting hard crust, excavation, de-watering, back filling and removal of spoils but excluding shoring complete as per standard drawing.(Depth of invert shall not be less than 1.80M below G.L. With 375 mm. thick brick work b) Above 400 mm to 600 mm dia having internal size (1500mmx1100mm) |
| 32 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (a) 1:3:6 proportion. ( 3rd Corrigenda & addenda dated 04.06.2018) |
| 33 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (b) 1:4:8 proportion. ( 3rd Corrigenda & addenda dated 04.06.2018) |
| 34 | BUILDING WORKS(P) SOLING, EDGING AND METALLING??(1)Brick soling with picked jhama bricks including preparation of bed as necessary with brick joints properly filled in and packed with powdered earth and including necessary cushion of similar material below the soling (and in between layers when more than one layer is used) completes as per direction.(f) Soling or dry pavement with one brick-on-edge laid in herring bone pattern (thickness 125 mm.) |
| 35 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a)In foundation and plinth. ( 3rd Corrigenda & addenda dated 04.06.2018) |
| 36 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (a) 20 mm thick plaster(3rd Corrigenda & addenda dated 04.06.2018) |
| 37 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary.(a) Depth up to 150 mm. ( Ref :PWD (Rds & Brdgs)-2018, It. No. 3.16Page No.240) |
| 38 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary.(b) For each additional Depth of 150mm and part thereof. ( Ref :PWD (Rds & Brdgs)-2018, It. No. 3.16 Page No.240) |
| 39 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire andlabour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(ii) For Construction of Sub Base by consolidating Brick Bats / Laterite(90 mm to 45 mm) ( Ref :PWD (Rds & Brdgs)-2018, It. No. 4.10 (ii) Page No.247 & page-222 sl. No-5 (f)) |
| 40 | Wet Mix Macadam Base Course Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including screening of aggregates and granular materials, premixing the material with water at OMC in Wet Mix Plant,carriage of mixed material by tipper to site, laying in uniform layers with Paver in Sub- base / Base course on well prepared surface and compacting with Vibratory Roller to achieve the desired density, including supply of all materials, machinery, fuel and lubricants, including incidental costs for lighting. guarding, barricading, making earthen bundh to protect the edges including cost of quality control complete as per Clause 406 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(Rate as per PWD(WB) schedule ofrates 2018(Roads & Bridge Work) , page-249(item-4.12) & 212(table3.3-1) and 4th Addenda & Corrigenda) |
| 41 | Supplying and Laying in the specified pattern of Interlocking ConcreteBlock Pavements (ICBP) with concrete blocks (with concrete grade as specified as per Table 1 of IS 15658 : 2006) manufactured in steel mould clamped to a vibrating table by hydraulic pressure (as per cl. no. 6.30 of IRC: SP: 63 (2018), from BIS licensee manufacturer, with spacer nib (Small protruding profiles on the vertical face of a paver block used as a device for keeping minimum joint gap in between the paving blocks, as per Cl. No 3.26 of IS: 15658)and of specified sizeand shape with aspect ratio (The ratio of length to thickness of a paver block, as per CLNo.3.3 of IS: 15658) as per Table of IS :15658 with flexural strength/breaking load as per Annexure G of IS: 15658, on the prepared base course of specified CBR as per Table 1 of IRC SP 63 (2018) or else as mentioned in design and drawing with a cushion of compacted bedding sand of 25-35 mm thick (grading of the bedding sand as per clause 6.5.1 of IRC SP 63) and filling up the gaps in between paver blocks with joint filling sand (the grading of thejoint filling sand will be as per clause 6.5.2 of IRC SP 63) and completing the edges with cut blocks us per Cl. No. 8.7 of IRC SP-63(2018) with proper confinement of bedding and joint filling sand,compaction levelling and filling up of the edge gap. 100 mm thick. a) Grey (12th Corrigenda & addenda dated14.10.2020) |
| 42 | COAST OF HOT MIX COVERAGE 12.50 SQ/MT |
| 43 | Supplying and laying factory made vertical kerb stone of cement concrete M-20 (1:1.5:3) machanicaly vibrated size 500mm X 350mm X 150mm tapered at top, making joints with cement mortar (1:4) incldg cost of all materials and labours but excluding the cost of underbed (for road-diveder / footpath) ( Ref :Rate based on PWD Current SOR [PWD(B) 2017, p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 ,p-191 (i -6)and 3rd Corr. & Adda, page-52, PWD-2018(R & B) p-332 (it -18.05)), Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, ) |
| 44 | Supplying and laying factory made flat channel stone of cement concrete M-20 (1:1.5:3) machanicaly vibrated; size 500mm X 300mm X 100 mm; making joints with cement mortar (1:4) incldg cost of all materials and labours but excluding the cost of under bed (for road-diveder) ( Ref :Rate based on PWD Current SOR [PWD(B) 2017, p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6)and 3rd Corr. & Adda, page-52, PWD-2018(R & B) p-332 (it -18.05)), Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, ) |
| 45 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT4. (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) |
| 46 | CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.27Hire charges of moveable type mounted earth excavator having minimum cutter size (1.0 cubic meter) & loader size (2.0 meter length x 0.75m width) for cutting & removal of any kind of soil, spoli etc. including cost of fuel, lubricants & manpower etc. in Water Supply Works. [ This item will be operated on prior permission from the concerned SE/Dy. Chief Engineer] For minimum engagement of 8 hrs. In a day |
| 47 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 13. Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge |
| 48 | Estimated amount |
| 49 | Add: 9%SGST |
| 50 | Add: 9%CGST |
| 51 | 1% LWC Please Enable Macros to View BoQ information |