| 1 | Painting of 1.6MVA,6.9/0.4KV service transformer complete with radiator, conservator with one coat red oxide metal and two coat spray painting with smoke grey colour acolyte enamel paint after thoroughly cleaning the surface of the equipment’s to be done as per procedure. (Approx. area of each transformer 175 square mtr.). | Painting of 1.6MVA,6.9/0.4KV service transformer complete with radiator, conservator with one coat red oxide metal and two coat spray painting with smoke grey colour acolyte enamel paint after thoroughly cleaning the surface of the equipment’s to be done as per procedure. (Approx. area of each transformer 175 square mtr.). |
| 2 | Washing and cleaning of 1.6MVA, 6.9/0.4KV service transformer (UST, ESP, SST, CHP, AHP, WTP & stacker reclaimer transformer) | Washing and cleaning of 1.6MVA, 6.9/0.4KV service transformer (UST, ESP, SST, CHP, AHP, WTP & stacker reclaimer transformer) |
| 3 | Preventive maintenance of marshalling boxes of 1.6MVA,6.6KV/0.4KV service transformers of WTP, Ash handling, Coal handling, SST, UST, ESP etc. | Preventive maintenance of marshalling boxes of 1.6MVA,6.6KV/0.4KV service transformers of WTP, Ash handling, Coal handling, SST, UST, ESP etc. |
| 4 | Round the clock supervision & maintenance of various power transformers and service transformers: | Round the clock supervision & maintenance of various power transformers and service transformers: |
| 5 | Pre overhauling, centrifuging activities: | Pre overhauling, centrifuging activities: |
| 6 | Minor overhauling and centrifusing of service transformer | Minor overhauling and centrifusing of service transformer |
| 7 | Draining of oil from main tank and disconnecting HV/LV chamber. | Draining of oil from main tank and disconnecting HV/LV chamber. |
| 8 | Dismantling of complete transformer including core coil assembly, hot oil flushing and final assembly | Dismantling of complete transformer including core coil assembly, hot oil flushing and final assembly |
| 9 | Filling of new transformer oil and filtration of oil till required BDV and PPM. | Filling of new transformer oil and filtration of oil till required BDV and PPM. |
| 10 | Replacement of LV bushing oil seals of service transformers (UST, SST, ESP, AHP, WTP and CHP transformers): | Replacement of LV bushing oil seals of service transformers (UST, SST, ESP, AHP, WTP and CHP transformers): |
| 11 | Replacement of OTI, WTI, relay, starter, coil, etc. On transformers. if any alteration needed in mounting of same, it has to be done by firm | Replacement of OTI, WTI, relay, starter, coil, etc. On transformers. if any alteration needed in mounting of same, it has to be done by firm |