| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including disposal of excavated earth, lead upto 50m and lift upto1.5m, disposed earth to be levelled and neatly dressed-All kinds of soil |
| 2 | Supplying and filling in plinth, under floor, foundations etc. with sand (fine) from local quarry with all lifts including spreading in horizontal layers, watering, grading to required slope, ramming, consolidating and compacting each layer by using plate compactor or by any suitable method complete. |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering i) 1:3:6 ( 1 Cement: 3 fine sand: 6 graded stone aggregate 40 mm nominal size) |
| 4 | First class brick work in foundation and plinth including cost of all materials as required complete:-1) In cement mortar 1:4 ( 1 cement: 4 fine sand). |
| 5 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centering, shuttering, finishing and reinforcement-i) 1:1 ½:3 (1 Cement: 1 ½ fine sand 3 graded stone aggregate 20 mm nominal size) |
| 6 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and skirting courses, fillets, columns, pillars, piers, abutments, posts and struts etc. upto floor five level excluding cost of centering, shuttering, finishing and reinforcement-1) 1:1 ½:3 (1 Cement: 1 ½ fine sand 3 graded stone aggregate 20 mm nominal size) |
| 7 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15 landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto floor five level excluding the cost of centering, shuttering, finishing and reinforcement-a) 1:1½:3 (1 Cement: l½ fine sand 3 graded stone aggregate 20 mm nominal size) |
| 8 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.a) Thermo-Mechanically Treated bars of grade Fe-500D or more |
| 9 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete above plinth level.i) Thermo-Mechanically Treated bars of grade Fe-500D or more |
| 10 | Centering shuttering including struttings, propping etc. and removal of form work for: |
| 11 | Foundations, footings, bases for columns etc. for mass concrete with timber plank |
| 12 | Lintels, beams, plinth beams, girders, bressumers and cantilevers with shuttering ply |
| 13 | Columns, Pillars, Piers, Abutments, Posts and Struts with shuttering ply |
| 14 | First class brick work in superstructure above plinth level & upto floor-five level including cost of all materials as required complete:-i)In cement mortar 1:4 ( 1 cement: 4 fine sand) |
| 15 | 12 mm cement plaster of mixi. Cement mortar 1:4 (1 cement : 4 find sand) |
| 16 | 15 mm cement plaster on the rough side of single or half brick wall of mix :i) Cement mortar 1:4 (1 cement : 4 fine sand) |
| 17 | 6 mm cement plaster mixi) Cement mortar 1:4 (1 cement : 4 find sand) |
| 18 | Neat cement punning |
| 19 | Finishing walls with acrylic smooth exterior paint of required shade of approved brand and manufacture [Payment shall be made after submission of Test Certificate issued by the Manufacturer]:i) New work ( two or more coats applied @ 1.67 litre/10 sqm over and including priming coat of exterior primer [email protected] kg/10 sqm) |
| 20 | Providing and fixing M.S. grills of required pattern in frames of windows etc. with M.S. flats, square or round bars etc. all complete.i) Fixed to openings /wooden frames with rawl plugs screws etc. Please Enable Macros to View BoQ information |